Internal Audit Management Actions Progress Report

Noted Finance 1 paper

AI summaryHampshire fire authority audit committee notes progress on internal audit actions, with two high-priority premises risk actions overdue and target dates extended to 31 March 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCommittee noted update on overdue medium and high audit actions
MoneyNot stated
What happens next31 March 2026Revised target date for two overdue Premises Risk actions
Who it affectsHIWFRS and Heads of ServiceService responsible for completing outstanding audit actions

What was decided

The Committee noted progress on implementation of internal audit management actions and delivery of the audit plan. Report P2

Seven previously overdue audit actions from the Premises Risk and Fire Safety Audits are reported as now complete. Report P18

The Health and Safety Investigations Audit action has been closed, completing that audit. Report P19

Why

The Committee has a scrutiny role in monitoring the implementation of internal audit management actions. Report P1

Failure to implement audit recommendations would leave the Authority exposed to identified risks and control weaknesses. Report P33

What happens next

Two overdue high-priority Premises Risk actions have target dates revised to 31/03/26 to match Business as Usual activity. Report P15, P16

The Planning, Change and Assurance team will continue to monitor 26 actions overall and refer ongoing issues to the relevant Director. Report P21, P9

Implications

  • Risk: Unimplemented audit recommendations leave the Authority vulnerable to identified risks and weaknesses in controls. Report P33
  • Legal: No legal implications, but provision of Internal Audit is required by the Accounts and Audit Regulations 2015 and the Public Sector Internal Audit Standards. Report P31
  • Staffing: Management of internal audit actions is carried out within current resources. Report P28
  • Other: Progress supports the Safety Plan priorities of making buildings safer and ensuring best use of funding, people and assets. Report P23

Who and where

  • Hampshire and Isle of Wight Fire and Rescue Service (HIWFRS) Report P3, P4
  • Heads of Service, who own delivery of actions in their areas Report P4, P37
  • Director of Corporate Services and Head of Corporate Governance and Support, who monitor outstanding recommendations Report P9

Timeline

  • 31 December 2025: Original target date for the two Premises Risk actions, subsequently revised Report P15, P16
  • 31 March 2026: Revised target date for the two overdue high-priority Premises Risk actions, to match Business as Usual activity Report P15, P16

Plain English for the jargon

  • SIAP: Southern Internal Audit Partnership, the provider of internal audit.
  • HIWFRS: Hampshire and Isle of Wight Fire and Rescue Service.
  • HMICFRS: His Majesty's Inspectorate of Constabulary and Fire and Rescue Services.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item85

Resolved

The Committee noted the progress made towards the implementation of internal audit management actions and the delivery of the audit plan.
Word for word from the decision Hampshire published for this meeting. Source: democracy.hants.gov.uk

Follow this further

Built from Hampshire's papers

What the report saysPro

Report to HIWFRA Audit and Governance Committee

Summary

1. The purpose of this report is to provide the Audit and Governance Committee Members with the latest update on the medium and high internal audit management actions that have not been completed within the agreed target date and are now overdue. The Audit and Governance Committee have a key scrutiny role in monitoring the implementation of internal audit management actions.

Recommendation

2. That the progress made towards the implementation of the internal audit management actions and the delivery of the audit plan be noted by the HIWFRA Audit and Governance Committee

Background

3. Internal audit is provided by the Southern Internal Audit Partnership (SIAP) and is one of various assurance mechanisms that the Service utilises as part of our wider assurance programme. Our assurance programme includes internal and external assurance mechanisms with external mechanisms including from His Majesty’s Inspectorate of Constabulary and Fire and Rescue Services (HMICFRS) and ISO certification testing.

4. In terms of internal audit, the Hampshire and Isle of Wight Fire and Rescue Service (HIWFRS) Planning, Change and Assurance Team maintains mechanisms to monitor management actions that are as a result of finalised internal audits. The team records whether management actions are in progress and on target, have been delayed and extended or have been completed. Heads of Service are responsible for the delivery of management actions that fall within their areas of responsibility.

5. Once a final audit report has been issued, the agreed management actions are recorded along with:

a) the priority of the recommendation;

b) the target date for implementation; and

c) the person responsible for the action.

6. The Planning, Change and Assurance team will request evidence that an action has been completed, or if it has not been completed when it is expected to be. Any management actions that continue to remain outstanding are referred to the relevant Director. Outstanding audit recommendations are monitored regularly by the Director of Corporate Services and the Head of Corporate Governance and Support

MANAGEMENT ACTIONS

7. Only medium and high overdue management actions are reported to the Committee. There are currently two overdue actions.

8. The table below lists those recommendations that are currently outstanding beyond their agreed target date and states if they are of medium (M) or high (H) priority. There is a brief commentary against each management action.

Internal Audit Management Actions

Premises Risk

Create Premises Risk Strategy 31 December H The BAU activity which aligns document to set out guiding 2025, revised to this has the target date of principles on building to 31 March 31/03/26, this action target prioritisation and intervention 2026. date has been revised to (by FRS) across community match the BAU Activity. safety and include priority for risk information capture allowing for the creation of a risk collection programme based on what HIWFRS see as the riskiest premises. National guidance on risk- based interventions relating to building risk and PORIS categories will be utilised (A new draft national guidance on Risk Based Intervention Programme and latest CRMP data)

Once Premises Risk Strategy 31 December H The BAU activity which has been created, an updated 2025, revised aligns to this has the target 3-year plan will be created and to 31 March date of 31/03/26, this action taken to Executive Group for 2026. target date has been revised approval and sign off. to match the BAU Activity.

MANAGEMENT COMMENTARY

9. The seven previously overdue audit actions from the Premises Risk and Fire Safety Audits are now complete.

10. The remaining Health and Safety Investigations Audit action has been closed, and this Audit is now complete.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Internal Audit Management Actions Progress ReportReport 144 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

5 of 5 attended
DH
Councillor David HarrisonChairman, present
DD
Councillor David DrewVice-Chairman, present
SP
Councillor Stephen ParkerCommittee Member, present
SG
Councillor Sally GoodfellowCommittee Member, present
LP
Councillor Louise Parker-JonesCommittee Member, present

On this subject at Hampshire

Search all
  1. Internal Audit Management Actions Progress ReportThis decision
  2. Annual Internal Audit Conclusion 2025/26Noted
  3. Internal Audit Management Actions Progress ReportNoted
  4. Governance - Annual Internal Audit Conclusion 2025-26Noted
  5. Annual Internal Audit Conclusion 2025-26Noted
  6. Governance: Internal Audit Progress ReportNoted

More from Hampshire HIWFRA Audit and Governance Committee

All decisions
MeetingDecisionOutcome
9 Sep 2026 HIWFRA's Audit and Governance Committee - Annual Report 2025/26The HIWFRA Audit and Governance Committee approved the Audit and Governance Committee Chair’s Annual Report 2025/26, ... Approved Open
9 Sep 2026 Annual Governance Statement 2025-2026 And Local Code Of GovernanceThe HIWFRA Audit and Governance Committee: · approved the Annual Governance Statement 2025/26, as set out in Appendix... Approved Open
9 Sep 2026 2025/26 Annual Assurance StatementThe HIWFRA Audit and Governance Committee approved the and its publication on the Hampshire & Isle of Wight Fire and ... Approved Open
9 Sep 2026 Annual Internal Audit Conclusion 2025/26The HIWFRA Audit and Governance Committee noted the annual conclusion. Noted Open
9 Sep 2026 EY Audit Planning Report 2025/26The Committee noted the audit planning report for 2025/26 from EY presented at Appendix A, the report on rebuilding a... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies