Education Advisory Panel, Thursday 12 March 2026 at 2.30pm

Children's Services Capital Programme

Noted Committee 1 paper

AI summaryHampshire Education Advisory Panel noted the Children's Services Capital Programme for 2026/27 to 2028/29, with planned spending of 632,555 in the unit labelled £'M on schools, SEND and social care.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedEducation Advisory Panel noted the update on the programme
Money632,555 (£'M as labelled)Total programme across the three years
What happens nextSelect Committee then ExecutiveSelect Committee, then Executive Member decision
Who it affectsPupils and families in HampshireIncludes SEND pupils, primary and secondary children

What was decided

The Education Advisory Panel noted the presentation on the Children's Services Capital Programme covering 2026/27 to 2028/29. Report P26

Why

The council is planning for 30,000 new houses between 2025 and 2030, and pupils with EHCPs have grown from 17,731 in December 2024 to 20,301 in November 2025. Report P4, P9

Between 2015 and 2025 the council created 14,404 new school places, and the proposals would create a further 3,410 primary and secondary places. Report P4

What happens next

Recommendations in section 1 of the report will go from the Children and Young People Select Committee to the Executive Lead Member for Children's Services and Young People. Report P26

Detailed project appraisals will go to future Decision Days. Report P22

Future High Needs Capital funding is to be announced in the Spring. Report P9

The money

  • 632,555 Total programme 2026/27 to 2028/29 (£'M as labelled) Report P14
  • 428,315 New schools and extensions (£'M as labelled) Report P13
  • 75,761 Social Care (£'M as labelled) Report P13
  • 62,536 SEND improvements (£'M as labelled) Report P13
  • 22,911 Other items, including inclusion projects, Early Years and other improvements (£'M as labelled) Report P13
  • 19,526 Schools Devolved Capital (£'M as labelled) Report P13
  • 13,262 Contingency (£'M as labelled) Report P13
  • £233m Developer contributions secured 2015 to 2026 Report P21

Options considered

  • Chosen: Note the presentation Report P26

Implications

  • Financial: Capital programme totals 632,555 in the unit labelled £'M, with the largest allocation for new schools and extensions at 428,315. Report P13, P14
  • Equalities: Significant SEND expansion, with EHCP numbers rising from 17,731 in December 2024 to 20,301 in November 2025. Report P9
  • Financial: Construction industry inflation is forecast to increase 16% to 2030, putting pressure on the programme. Report P21
  • Risk: Pressures include ongoing primary and secondary demand, SEND demand, construction inflation, size of programme, devolution and Local Government Reorganisation. Report P21
  • Climate: Future design solutions will consider the impact of climate change. Report P22

Who and where

  • Pupils across Hampshire, particularly those with EHCPs Report P9
  • Families in new housing developments (30,000 new homes planned 2025 to 2030) Report P4
  • Schools receiving devolved formula capital Report P15, P16, P17, P18, P19
  • Children in social care, given the 75,761 social care allocation Report P13

Timeline

  • 2026/27 to 2028/29: Capital programme period Report P1, P12
  • Autumn 2026: Luminous Oak Academy (up to 125 places, ages 8 to 16, SEMH) opens in Eastleigh Report P6, P9
  • Sept 2026: Multiple SEND resourced provision expansions open across the county Report P10
  • Sept 2027: Hartland Village Primary and Whiteley Secondary expected to open Report P6, P7
  • Sept 2028: Bordon/Whitehill Primary, Welborne Primary and One Horton Heath Primary expected to open Report P8
  • Jan 2029: Windmill Academy (up to 135 places, ages 4 to 19, SLD) opens in Whiteley Report P8, P9
  • Sept 2029: Hazelton Farm primary, Manydown Primary and North Whiteley Primary expected to open Report P8
  • 2025 to 2030: 30,000 new houses planned across the county Report P4

Plain English for the jargon

  • EHCP: Education, Health and Care Plan, a legal document for children and young people with special educational needs and disabilities
  • SEMH: Social, Emotional and Mental Health
  • SLD: Severe Learning Difficulty
  • MLD: Moderate Learning Difficulty
  • ASC: Autistic Spectrum Condition
  • HI: Hearing Impairment
  • RP: Resourced Provision, specialist support within a mainstream school
  • fe: Form of entry, a measure of school size (about 30 pupils per year group)
  • SEND: Special Educational Needs and Disability
  • LGR: Local Government Reorganisation
  • YrR: Year R, the reception year in primary school
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item110

Resolved

That the Education Advisory Panel note the presentation.
Word for word from the decision Hampshire published for this meeting. Source: democracy.hants.gov.uk

Follow this further

Built from Hampshire's papers

What the report saysPro

Report to Education Advisory Panel

Childrens Services Capital Programme Briefing 2026/27 – 2028/29

Richard Vaughan Head of Strategic Development

People & Organisation

Hounsome Fields Primary School Children’s •Exciting investment •Continues significant schools' construction activity Services •County Council 26 February 2026 Capital •National funding policy – Basic Need, School Condition Allocation, SEND and Early Years Programme •Role of Local Authority to strategically plan school places and capital investment 2026/27 – •30,000 new houses planned between 2025 - 2030 2028/29 •2015 to 2025 – 14,404 new school places •Proposals in report create a further 3,410 primary and secondary places •Potential capital projects listed -Table 6 •Where appropriate, alignment of Capital Maintenance •School Places Plan – 2026 to 2030 at Appendix 6 Primary numbers and movement into the secondary phase at Year 7 Hampshire – 4-year-olds

Sept 2025 15,322 YrR places available, and only 13,740 offers made Proposed New Schools to September 2029

Area / School Size & Type of School Proposed Sponsor Status Opening Date Luminous Oak Academy, Eastleigh Up to 125 place 8-16 Autumn 2026 Solent Academies Trust SEMH School Hartland Village Primary, Fleet 2fe Primary Sept 2027 The Circle Trust

Whiteley Secondary, North Whiteley 6fe Secondary Sept 2027 Henry Cort relocation

Bordon/Whitehill Primary, Bordon 2fe Primary Sept 2028 tbc Welborne Primary, Fareham 2fe Primary Sept 2028 tbc One Horton Heath Primary, Horton 2fe Primary Sept 2028 tbc Heath Windmill Academy, Whiteley Up to 135 place 4-19 SLD Jan 2029 Solent Academies Trust School Hazelton Farm/Land East of Horndean 1.5fe Primary Sept 2029 tbc Manydown Primary, Basingstoke 2fe Primary Sept 2029 tbc North Whiteley Primary, Winchester 2fe Primary Sept 2029 tbc Special Educational Needs and Disability Guillemont Junior, Farnborough

▪ Significant increase in pupils with EHCPs – Nov 25, 20,301 (Dec 24, 17,731) ▪ Luminous Oak 125-place, co-educational, aged 8-16 SEMH (Social, Emotional & Mental Health) School in Boorley Green, Eastleigh ▪ Windmill Academy 135-place, co-educational, aged 4-19 SLD (Severe Learning Difficulty) School in Whiteley, Winchester ▪ Focus on county wide provision of Resourced Provision in mainstream ▪ £62.536m planned investment ▪ Future High Needs Capital to be announced in the Spring.

Austen Academy, Basingstoke Major SEND Expansion Schemes in Development School / Area Designation of Places Proposed Opening Date Kings Academy Bay House, Gosport 15 SEMH RP Sept 2026 Boorley Park Primary, Eastleigh 15 SEMH RP Sept 2026 Crofton Anne Dale Jnr, Stubbington 12 AS RP Sept 2026 Danebury Academy, Stockbridge 15 SEMH RP Sept 2026 Deer Park School, Hedge End 15 ASC RP Sept 2026 Fair Oak Infant, Fair Oak 9 ASC RP Sept 2026 Hamble Primary, Hamble 10 ASC RP Sept 2026 Hamble School, Hamble 15 ASC RP Sept 2026 Shepherds Down School, Winchester 16 SLD Sept 2026 Harrow Way School, Andover 15 ASC RP Sept 2026 Lift New Forest, Holbury 15 SEMH RP Sept 2026 Kings Academy Lord Wilson, Sarisbury Green 20 SEMH Sept 2026 Maple Ridge School, Basingstoke 10 MLD Sept 2026 Morelands Primary, Waterlooville 8 ASC Sept 2026 Poulner Junior, Ringwood 12 AS RP Sept 2026 Stanmore Primary, Winchester 10 SEMH RP Sept 2026 Wavell School, Farnborough 15 SEMH RP Sept 2026 • Key ASC – Autistic Spectrum Condition MLD – Moderate Learning Difficultly SEMH – Social, Emotional & Mental Health SLD – Severe Learning Difficulty HI – Hearing Impairment RP – Resourced Provision Priority Investment Areas

• New School Places • Maintenance of Existing Buildings • Special Educational Needs and Disability • Early Years • Social Care • Suitability investment • Proposed 3-year programme - Table 3

Deer Park Secondary School Children’s Services Capital Programme 2026/27 to 2028/29 £’M

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Children's Services Capital ProgrammeReport 6.6 MB DownloadRead as text

At this meeting

Whole meeting

Who was there

5 of 17 attended
JB
Councillor Jackie BransonChairman, apologies
FC
Councillor Fran CarpenterVice-Chairman, present
DD
Councillor David DrewCommittee Member, present
BD
Councillor Barry DunningCommittee Member, apologies
TG
Councillor Tim GrovesCommittee Member, present
JH
Councillor Juliet HendersonCommittee Member, apologies
LM
Councillor Lesley MeenaghanCommittee Member, apologies
NP
Councillor Neville PenmanCommittee Member, present
JP
Councillor Jackie PorterCommittee Member, present
AT
Councillor Andy TreeCommittee Member, absent
AM
Amanda Mullett Hampshire Primary SchoolsCo-opted Member, apologies
CA
Chris Anders Hampshire Secondary SchoolsCo-opted Member, apologies

All 17 on the meeting page

On this subject at Hampshire

Search all
  1. Children's Services Capital ProgrammeThis decision
  2. Introduction to Select Committee - Children's ServicesDecided
  3. 2026/27 Revenue Budget and Savings Report for Children's ServicesApproved
  4. Children's Services Capital Programme 2026/27 - 2028/29Approved
  5. Annual Safeguarding Report - Children's Services 2024-25Noted
  6. Children's Services Capital Programme 2025/26 - 2027/28Approved

More from Hampshire Education Advisory Panel

All decisions
MeetingDecisionOutcome
17 Jun 2026 Introduction to Education and InclusionThe Education Advisory Panel noted the presentation. Noted Open
12 Mar 2026 Recruitment, retention and complaints - supporting schools and school leadersThat the Education Advisory Panel note the presentation. Noted Open
12 Mar 2026 Virtual School UpdateThat the Education Advisory Panel note the presentation. Noted Open
19 Nov 2025 2025 Ofsted InspectionThat the Education Advisory Panel notes the presentation. Decided Open
19 Nov 2025 Best Start and Community Hubs, Families First Early Prevention work and the Local Offer LiveThat the Education Advisory Panel notes the presentation. Decided Open