That the 2006/07 Highway Works Plan be approved That no other non-emergency traffic and highway schemes are prioritised during 2006-7 That all proposed CPZ schemes following consultation with residents and businesses be referred to the Executive for decision That all other schemes requiring consultation but where results show lack of support, to be referred back to the Executive for decision. That progress on the 2005/6 Highways Works Plan be noted. That the Executive receive a report outlining the Highways Works Plan in March 2007 for the 2007/08 programme of proposed schemes. That the Executive receive a report in April 2007 outlining achievements of the 2006/7 works programme.
Word for word from the decision Haringey published for this meeting.Source: www.minutes.haringey.gov.uk
3.1It is recommended that the Executive: 3.2 Approve the 2006/07Highway Works Plan set out in this report in Appendices 1 & 2. 3.3 Agree that no other non-emergency traffic and highway schemes are prioritised during 2006/07. 3.4 Note, that all proposed CPZ schemes following consultation with residents and businesses will be referred to the Executive for decision 3.5 Note, that all other schemes which require consultation but where the results show
1 lack of support, will be referred back to the Executive for decision. 3.6 Note progress on the 2005/6 Highways Works Plan. 3.7 Receive a report outlining the Highways Works Plan in March 2007 for 2007/08
programme of proposed schemes. 3.8 Receive a report in April 2007 outlining achievements of 2006/7 works programme.
Report authorised by: Anne Fisher, Director of Environmental Services
Contact officer: Alex Constantinides Telephone: 0208 489 1777
Executive summary
4.1Each year the Council funds improvements to the borough’s highways infrastructure from a number of sources. This funding pays for a wide variety of projects including walking and cycling initiatives, bus priority measures, local safety schemes, resurfacing of footways & roads and road & bridge maintenance. This report sets out the proposed programme of capital works for 2006/07 (refer to Appendices 1 & 2) and informs Members on the progress of projects approved in the Highways Work Plan for 2005/06 (refer to Appendix 3). The report ends by updating Members on the progress in developing Asset Management Plan and the actions undertaken to date to satisfy the requirements of the Traffic Management Act 2004.
5.0Reasons for any change in policy or for new policy development:
There is no change in policy
6.0Local Government (Access to Information) Act 1985
6.1The following background papers were used in the preparation of this report:-
• Borough Spending Plan 2006/07 (BSP). • Letter from Transport for London dated 12 December 2005. • Highways Works Plan 2005/06. • Draft Highways Asset Management Plan.
6.2For access to the background papers or any further information please Contact Alex Constantinides on 020 8489 1777.
2 7.0 Background
7.1For the last three years, the Highways Service has produced an annual Highways Works Plan for agreement by the Executive. This report outlines a programme of investment for the Highways Works Plan (2006/07), based on funding from:-
• TfL’s Borough Spending Plan (BSP) capital allocation of £3.4m for principal road renewal, bridge strengthening, local safety schemes and 20 mph zones, walking and cycling initiatives, bus accessibility and priority measures, streets-for people and safer routes to schools;
• The Council’s capital investment of £1m for street lighting, £0.875m for resurfacing of classified and unclassified roads, £500k footway treatments, £200k for road accident reduction improvements, £200k for street furniture, £974k for parking controls;
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.