That approval be granted to the 2007/08 Highway Works Plan as set out in Appendices 2 and 3 to the interleaved report. 2. That, following consultation with residents and businesses, all proposed Compulsory Parking Zone schemes be referred to the Executive for decision. 3. That all other schemes which require consultation but where the results show lack of support also be referred back to the Executive for decision. 4. That the progress on the 2006/7 Highways Works Plan be noted.
Word for word from the decision Haringey published for this meeting.Source: www.minutes.haringey.gov.uk
3.1Approve the 2007/08 Highway Works Plan as set out in Appendices 2 & 3. 3.2 Agree that all proposed CPZ schemes following consultation with residents and businesses will be referred to the Executive for decision. 3.3 Agree that all other schemes which require consultation but where the results show lack of support, will be referred back to the Executive for decision. 3.4 Note progress on the 2006/7 Highways Works Plan.
1 Report authorised by: Niall Bolger, Director of Urban Environment
Contact officer: Alex Constantinides Telephone: 0208 489 1777
4. Director of Finance Comments
4.1A substantial Highways related investment programme has been put together for next year. The currently approved programme for 2007/08 is £11.595m funded as follows:
Funding Source £m TfL Grant 4.184 DfT Grant (Spine Road) 4.000 Council Investment 3.236 Section 106 0.175 Total 11.595
4.2Further potential capital investment has been identified from various sources as listed below. The schemes in respect of this funding will be included in the 2007/08 Urban Environment capital budget once final confirmation/approval has been obtained from the appropriate funding source/body.
4.3The Service has developed a highways asset management plan to address the identified investment shortfall in the Borough’s road network. Consideration is being given to the use of prudential borrowing to fund some of this investment and markedly improve road conditions and indicators.
4.4To successfully deliver an investment programme of this size for the next financial year will require good forward planning and project management skills. Firm targets for phasing and achieving spend will be necessary as most of the funds are time limited and will have to be spent by 31 March 2008. Back loading of spend to the end of the financial year should be avoided as far as possible. Where schemes require consultation with residents and other parties this should be programmed in as early as possible.
4.5The Highways Work programme for 2006/07 is mainly on target to spend at its revised budget allocations by 31 March 2007 except for projected underspend of £477k on parking plan cpz schemes where slippage has occurred due to an extended consultation process and £162k against the TfL allocation for Cycling LCN+, where approval is being sought to undertake the scheme next year.
2 5. Head of Legal Services Comments
5.1The Head of Legal Services has been consulted, agrees with the recommendations and has no specific additional comments.
6.0Local Government (Access to Information) Act 1985
6.1The following background papers were used in the preparation of this report:-
• Local Implementation Plan 2007/08 (LIP). • Letter from Transport for London dated 19 December 2006. • Highways Works Plan 2006/07. • Draft Highways Asset Management Plan.
For access to the background papers or any further information please contact Alex Constantinides on 020 8489 1777.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.