CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
London Borough of Haringey
Alexandra Park and Palace Board, Tuesday 4 July 2006 at 7.30pm

HERITAGE LOTTERY FUNDED LANDSCAPE DEVELOMENT PROJECT UPDATE : tO UPDATE ON PROGRESS MADE TOWARDS THE PROGRAMME OF WORKS FOR THIS YEAR'S PROJECT ITEMS. (Report of the Development Manager)

Agreed Committee 1 paper

Alexandra Park and Palace Board agreed this item on Tuesday 4 July 2006. Below is the council's own wording, with the papers it was decided on.

Item8

Resolved

i. That the report be agreed and noted; and ii. That the action to monitor and address the overall problems be noted and that a progress update be given at the next meeting of the Board.
Word for word from the decision Haringey published for this meeting. Source: www.minutes.haringey.gov.uk

Follow this further

Built from Haringey's papers

What the report saysPro

Report to Alexandra Park and Palace Board

Agenda item: 8 Alexandra Park & Palace Board Meeting On 4th July 2006

Report Title: Heritage Lottery Funded Landscape Development Project - Progress Report.

Report of: Matthew Baker, Development Manager – Parks

1. Purpose 1.1 To update the Board of progress towards the achieving completion of the works specified in the HLF refurbishment of the Park.

2. Recommendations 2.1 That the Board notes the report.

Report Authorised by: Matthew Baker, Development Manager:

Contact Officer: Matthew Baker, Development Manager

3. Executive Summary 3.1 This report provides a statement of progress toward the achievement of the HLF funded programme of works.

4. Reasons for any change in policy or for new policy development (if applicable) 4.1 N/A

5. Local Government (Access to Information) Act 1985 5.1 Further information about this report can be obtained from Matthew Baker, Development Manager – Parks, Alexandra Palace & Park, Alexandra Palace Way, Wood Green, London, N22 7AY. Telephone number 0208 365 2121

1 6. Background 6.1 Blakedowns Southeast are making good progress with the phase two package of works as specified by Land Use Consultants in accordance with the approved purposes of the Heritage Lottery Grant.

The contractor had previously prepared a programme of works with the intention of completing all the works by July 2006, leaving a six month period between August 2006 – January 2007 for any additional works and to attend to defects. Unfortunately due to the early announcement of a national hose pipe ban and potential water restrictions a decision has been taken to postpone the majority of the planting phase until the end of the summer 2006 to ensure the best conditions for establishment of new stock.

In addition to this all tree work has been suspended until the autumn in order to prevent disturbance during the nesting season.

Please note general tree maintenance/Emergency works will be still be carried out in order to reduce the risk to visitors.

6.2Blakedowns are contracted to complete the improvements to the main road as part of the Civil engineering package of works. Work commenced in February following the Motorcycle show and has been phased over a seven month period. Colin Buchanan and Partners who were responsible for this aspect of the project have continued to liaise with Highways Authority and Transport for London to ensure the design proposal satisfies all of the requirements.

Due to changes in the regulations for new bus stops introduced in January 2006 it has not been possible to reduce the number of Bus stops to the West of the Palace as previously reported. Transport for London have stated that they would not support the removal of the existing stops as they are networked to there electronic timetable system. In addition to this the location which had been identified for the single stop has does not comply with their new regulations.

For reasons of Health & Safety it will be necessary to operate temporary traffic lights during much of the Civils works. Blakedowns have contracted ‘A-Plant’ Traffic Systems assist with all traffic management issues to ensure that the works are in accordance with the regulations for highways work.

In broad terms these improvements are focused at reducing the speed of vehicles within the park, increasing the number of pedestrian links between the Palace and Park and improving the general road layout.

The improvements which fall outside of the Park Boundary will be completed by the highway authority and LUC will liaise to ensure that these works are carefully phased with Blakedowns programme.

6.2.1 Bedford Road Entrance The Gantry will be removed and the main entrance realigned with a speed table constructed to slow vehicles when entering and exiting the

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
HERITAGE LOTTERY FUNDED LANDSCAPE DEVELOMENT PROJECT UPDATE : tO UPDATE ON PROGRESS MADE TOWARDS THE PROGRAMME OF WORKS FOR THIS YEAR'S PROJECT ITEMS. (Report of the Development Manager)Minutes 113 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

11 of 11 attended
BH
Councillor Bob HareCommittee Member, present
CA
Councillor Charles AdjeChair, present
DB
Councillor David BeachamCommittee Member, present
PE
Pat EganVice-Chair, present
SP
Councillor Sheila PeacockCommittee Member, present
SR
Councillor Sheila RaingerCommittee Member, present
SG
Councillor Sheik G L ThompsonCommittee Member, present
DL
David LiebeckObserver, present
VP
Val PaleyNon-voting, present
MT
Mike TarpeyNon-voting, present
NW
Nigel WillmottNon-voting, present

On this subject at Haringey

Search all
  1. HERITAGE LOTTERY FUNDED LANDSCAPE DEVELOMENT PROJECT UPDATE : tO UPDATE ON PROGRESS MADE TOWARDS THE PROGRAMME OF WORKS FOR THIS YEAR'S PROJECT ITEMS. (Report of the Development Manager)This decision
  2. Regeneration report - heritage lottery fund project (hlf)Noted
  3. HLF Project - Approval for Chair to sign covering letter to the Heritage Lottery Fund (HLF) Project bidAgreed
  4. Heritage lottery funded landscape development project update (report of the park manager) to update the committee on progressNoted
  5. Heritage lottery funded landscape development project update (report of the park manager) - to update on progressNoted
  6. Heritage lottery funded landscape development project update - report of the parks facilities managerNoted

More from Haringey Alexandra Park and Palace Board

All decisions
MeetingDecisionOutcome
29 Oct 2026 Charitable Trust Progress ReportThe Committee noted the report. Noted Open
29 Oct 2026 FRRAC Chair's Report (Verbal update)The Committee noted the report. Noted Open
29 Oct 2026 Finance ReportThe Committee noted the 2026/27 forecast against revised budget. Noted Open
29 Oct 2026 Panorama Room ReportThe Committee noted the report. Noted Open
29 Oct 2026 Environmental Sustainability UpdateThe Committee noted the contents of this report and approve the Carbon Reduction Plan at Appendix 1. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies