North Tottenham Decent Homes Works Phase NT9

Approved Executive 1 paper

Cabinet Procurement Committee approved this item on Thursday 16 October 2008. Below is the council's own wording, with the papers it was decided on.

Item53

Resolved

That, in accordance with Contract Standing Order 11.03, approval be granted for the award of the contract for Phase NT9 of the North Tottenham Decent Homes Programme 2008/09 to the contractor named in the interleaved exempt Appendix A. That the Agreed Maximum Price excluding fees as detailed in Paragraph 2.2 of Appendix A be noted.
Word for word from the decision Haringey published for this meeting. Source: www.minutes.haringey.gov.uk

Follow this further

Built from Haringey's papers

What the report saysPro

Report to Cabinet Procurement Committee

Agenda item: [No.] th Procurement Committee Date: 16 October 2008

Report Title: Decent Homes Works: North Tottenham Phase 9

Forward Plan reference number

Report of: Niall Bolger, Director of Urban Environment

Wards(s) affected: Northumberland Park Report for: Key Decision

1. Purpose 1.1 This reports sets out a detailed programme of works as it relates to the delivery of the Decent Homes Programme at properties known as Northumberland Park . The works outlined in this report is scheduled to commence on 6th October 2008. As such, this report is seeking Procurement Committee approval to proceed to award the contract and commence with the works in this phase.

2. Introduction by Cabinet Member)

2.1In accordance with our stated commitment to improve the quality of homes for our tenants and to meet housing need, this report informs Members of the Procurement Committee of the current packages of work to commence under the Decent Homes programmes as delivered by Homes for Haringey.

3.0Recommendations 3.1 To facilitate the delivery of the decent homes works Members of the Procurement Committee are requested to agree:

3.2To award the contract for the above Project to the contractor named in Appendix A as allowed under Contract Standing Order (CSO) 11.03 and that the AMP (Agreed Maximum Price) excluding fees as detailed in Para 2.2 of Appendix A be noted.

Report Authorised by: Niall Bolger, Director of Urban Environment Contact Officer: Larry Ainsworth Strategic Client Representative Homes for Haringey, River Park House (6th Floor) 225 High Road. London N22 4HQ Tel no: (020 8489 1134 .e.mail: [email removed]

4.0Chief Finance Officer Comments 4.1 It should noted that on 13th Feb 2007, this committee approved framework agreements with Decent Homes contractors and compliance teams, to cover 4 areas. This report details the specific works needed to Northumberland Park, N17, priced in accordance with the framework agreement.

4.2Members will be aware that DCLG has approved the funding for Decent Homes, totalling £198.5m phased over six years of which £27.5m has been approved for 2008-09. This scheme is included in the schedule for 2008-09. However, as some of the works are going to be completed in the next financial year funding for this element will be a first call against the Decent Homes allocation for 2009/10.

4.3It should be noted that so far (excluding the reports on this agenda) 24 contracts have been approved by this committee; totalling some £25.6m. With the approval of the three Contracts on this agenda, this will bring the total commitments to £30.1m based on the flat roof option. The extra costs above the currently approved budget is proposed to be funded from recharges made to leaseholders for works to their properties.

4.4The report also provides information for a pitched roof option. The additional cost of this is £0.505m. The Decent Homes funding does not include resources for pitched roofs and therefore currently there is no budget to fund this work.

5.0Head of Legal Services Comments

5.1This report is seeking Procurement Committee approval to award a call-off contract for Decent Homes works at 104 properties in the North Tottenham area of the borough (details of which are set out in Paragraph 15.2 below), to the contractor named in Paragraph 2.1 of Appendix A to this report.

5.2Cabinet Procurement Committee had on 13th February 2007 granted approval to the award of four Decent Homes Constructor Partner Framework Agreements in respect of four areas within the Borough (Wood Green, Hornsey, North Tottenham and South Tottenham) to four respective contractors, of which the recommended contractor is one.

5.3The Framework Agreements were tendered in the EU and selection of the Framework contractors was undertaken in compliance with the Public Contracts Regulations 2006, as confirmed by external legal advisers (Trowers and Hamlin) who provided legal advice on the procurement of the Framework Agreements.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
North Tottenham Decent Homes Works Phase NT9Minutes 125 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

4 of 4 attended
GM
Councillor George MeehanCommittee Member, present
CA
Councillor Charles AdjeChair, present
LS
Councillor Liz SantryCommittee Member, present
JB
Councillor John BevanCommittee Member, present

On this subject at Haringey

Search all
  1. North Tottenham Decent Homes Works Phase NT9This decision
  2. Application for the Grant of a New Premises Licence under the Licensing Act 2003 Milcana Café Annexe, 50 Park Lane, Tottenham, London N17 0JS (NORTHUMBERLAND PARK)Noted
  3. Approve extension (and variation where it applies) of the Bounds Green, Bruce Grove, Harringay, Noel Park, Northumberland Park, Seven Sisters, St Anns, Tottenham Green, Tottenham Hale, West Green and Woodside Wards Alcohol Control PSPO'sDecided
  4. Adoption of Conservation Area Appraisal and Management Plans for North Tottenham, Scotland Green, Bruce Grove, Tottenham Green, Seven Sisters/Page Green and South TottenhamNoted
  5. Approval to enter into grant agreements with Tottenham Hotspur FC to deliver heritage and public realm improvements for north TottenhamApproved
  6. North Tottenham Townscape Heritage Initiative - Appointment of Principal Contractor for Phase 1 worksApproved

More from Haringey Cabinet Procurement Committee

All decisions
MeetingDecisionOutcome
12 Apr 2012 Financing the Leisure Service Fitness Suite EquipmentRESOLVED · That the report be noted. Noted Open
12 Apr 2012 Award of coroners' removals contractRESOLVED · That approval be granted for the award of contract for a Coroners’ removal service to Dignity Funeral Ltd ... Approved Open
12 Apr 2012 Contract for the support and maintenance of the Council's IT network, IT security and data centresRESOLVED · That approval be granted to award the replacement contract for the management of the IT network, IT securi... Approved Open
12 Apr 2012 Healthy Alliance - Primary and Secondary Community HIV Prevention Programme for Enfield and HaringeyRESOLVED · That approval be granted to a waiver of the requirements to tender as required under CSO 9.01 as allowed u... Approved Open
12 Apr 2012 Sport and physical activity coaching services suppliers frameworkRESOLVED · That approval be granted for the award of a framework agreement as set out in the report for a minimum per... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies