Enterprise Partnership Board (HSP) noted this item on Wednesday 10 December 2008. Below is the council's own wording, with the papers it was decided on.
That the letter from the Chair of the HSP regarding the ABG Review be noted. That a sub group should be created to form a draft commissioning document setting out a programme of activity and intentions relating to LAA outcomes. That, once a draft document had been formed, it should be circulated to Board members for comment.
Word for word from the decision Haringey published for this meeting.Source: www.minutes.haringey.gov.uk
2.1A review of ABG activity took place in July / August 2008, as requested by the Performance Management Group (PMG).
2.2144 projects were assessed against agreed criteria. Of these, 116 (81%) received a GREEN overall status, 22 (15%) were assessed as AMBER and 6 (4% as RED).
2.3Appendix 1 shows the detailed outcomes of the review.
2.4A number of recommendations are made in section 3 for improving the management and monitoring of activity funded through the ABG.
2.5The review process has been assessed against Compact criteria and was found to be fair and transparent.
2.6Section 8 summarises the requirements for the financial management and reporting of the area based grant.
ABG Review v0.5 HSP 1 3. RECOMMENDATIONS
3.1That clear, measurable objectives and outputs, linked to outcomes, are agreed with the Thematic Boards at project start-up and prior to funding being agreed. The review and assessment process must also be agreed at this time. The Haringey Strategic Partnership (HSP) has already agreed that Thematic Boards have responsibility for financial and performance management.
3.2That there should be a link between ABG funded activity and the delivery of local and national priorities, including the achievement of LAA targets. The HSP may consider mapping all activity, regardless of funding sources, contributing to a particular outcome as part of a future Commissioning Framework. This will enable a holistic view of activities across all partner organisations and will provide opportunities for improved planning, reduction of duplication and achievement of value for money.
3.3That consideration is given to rationalising the number of projects within the ABG i.e. where projects have common objectives these could be grouped and reported as a single programme. For example, projects BP14 and BP-15 (Vulnerable Communities Programme and Working with Education & Voluntary Sectors). As with the previous recommendation, this will provide opportunities for improved planning, reduction of duplication and achievement of value for money.
3.4That the discipline of regular monitoring and reporting, against agreed objectives and spend for each project is embedded across all ABG funded activity as set out in the agreed performance management framework for the HSP.
3.5That principles of project and programme management based on national best practice is applied to the management of ABG activity.
3.6From April 2008 the government allocated the ABG on a three-year basis to maximise stability and certainty. It is recommended that this arrangement is extended to the HSP theme boards’ ABG funded activity, subject to meeting the requirements of an annual review.
3.7That from 2009/10 a fund is created within the ABG allocation, to manage unforeseen risks and underperformance against the delivery of outcomes.
3.8That consideration is given to aligning ABG funding allocation with existing business planning across partner organisations. This will enable improved planning and alignment of resources. Appendix 2 shows a proposed timetable.
3.9That the PMG provides the outcome of this review to the Thematic Boards and for them to take action to ensure that activity funded through their allocated grant will deliver against the agreed outcomes. Remedial action taken will need to be detailed in the quarterly thematic performance report.
ABG Review v0.5 HSP 2 4. BACKGROUND INFORMATION
4.1In November 2007 the Department for Communities and Local Government detailed the arrangements for the new Area Based Grant as part of the publication 'Development of the New LAA Framework' Operational Guidance. Further guidance was published in February 2008.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.