CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
London Borough of Haringey
Cabinet Procurement Committee, Tuesday 27 April 2010 at 6.00pm

Consultants for Construction Work (Additional Services) Framework Agreement Extension

Agreed Executive 1 paper

Cabinet Procurement Committee agreed this item on Tuesday 27 April 2010. Below is the council's own wording, with the papers it was decided on.

Item111

Resolved

RESOLVED 1. That In accordance with Contract Standing Order 13.02 the Consultants for Construction Works (Additional Services) framework agreements be extended for the following companies: · Gardiner & Theobald · Frankham Consultancy Group · Keegans · Potter Raper Partnership · John Burke Associates 2. That the framework agreements be extended for a period of 1 year with an estimated total value of £500,000.
Word for word from the decision Haringey published for this meeting. Source: www.minutes.haringey.gov.uk

Follow this further

Built from Haringey's papers

What the report saysPro

Report to Cabinet Procurement Committee

Agenda item: [No.] th Cabinet Procurement Committee On 27 April 2010

Report Title. Consultants for Construction Works (Additional services) framework agreement extension

Report of Director of Corporate Resources

Signed :

Contact Officer : David Mulford, 020 8489 1037

Wards(s) affected: All Report for: Key Decision

1 Purpose of the report 1.1 To seek Cabinet Procurement Committee approval to extend the Consultant for Construction Works (Additional services) framework agreements for a period of 1 year.

2 Introduction by Cabinet Member 2.1 I concur with the recommendations set out in this report.

3 State link(s) with Council Plan Priorities and actions and /or other Strategies: 3.1 The procurement of long term agreements for construction consultancy fits in with the Council’s Category Management strategy.

4 Recommendations 4.1 In accordance with CSO 13.02 that the Consultants for Construction Works (Additional services) framework agreements be extended for the following companies: § Gardiner & Theobald § Frankham Consultancy Group § Keegans § Potter Raper Partnership § John Burke Associates

4.2That the framework agreements be extended for a period of 1 year with an estimated total value of £500,000.

5 Reason for recommendation(s) 5.1 The extension of the existing framework agreements will enable the Construction Procurement Group to conduct a procurement exercise for the subsequent arrangements to be put in place for the provision of construction consulting. Consultation with key client groups has already begun in order to shape the structure of mechanism to be used under these arrangements.

6 Other options considered 6.1 The Construction Procurement Group examined the option of using other public sector arrangements for the provision of construction consulting. There are public sector framework agreements in place that may be used for the provision of construction consulting, whereby the user can select consultants through a tender competition. The service providers under the existing framework agreements have been trained in the Council’s internal processes and procedures, so the use of the in-house frameworks also provides efficiency savings in terms of the time officers would otherwise spend training new consultants. The use of the existing framework agreements also provides a consistency of service that would not be provided by an external arrangement.

7 Summary 7.1 The Consultant for Construction Works (Additional services) (CfCWA) framework agreement was awarded in March 2008 for a period of 2 years, with the option to extend for up to a further 2 years subject to satisfactory performance. The current framework agreement expires on 27th April 2010.

7.2The framework agreements provide the following services: § CDM (Construction Design & Management) co-ordinator services – Gardiner & Theobald § Quantity surveying – Frankham Consultancy Group, Keegans and Potter Raper Partnership § Clerk of works services – John Burke Associates

7.3The framework agreements were awarded to run concurrently with the Consultants for Construction Works framework agreement to provide cost, quality and health &

Report Template: Formal Bodies 2 safety assurance to the work carried out by the one-stop-shop service provider.

7.4The performance of the service providers has been satisfactory throughout the initial term of the framework agreement and client satisfaction has been satisfactory.

8 Chief Financial Officer Comments 8.1 The Chief Financial Officer has been consulted over the contents of this report and has no further comments to add.

9 Head of Legal Services Comments 9.1 The framework agreements which the report relates to were advertised in the Official Journal of the European Union in accordance with the Public Contracts Regulations 2006.

9.2As stated in paragraph 7.1 above the framework has provision for extension for up to a further 2 years.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Consultants for Construction Work (Additional Services) Framework Agreement ExtensionMinutes 136 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

3 of 4 attended
BH
Councillor Bob HarrisChair, present
JB
Councillor John BevanCommittee Member, present
CK
Councillor Claire KoberCommittee Member, apologies
LR
Councillor Lorna ReithCommittee Member, present

On this subject at Haringey

Search all
  1. Consultants for Construction Work (Additional Services) Framework Agreement ExtensionThis decision
  2. Homes for Haringey - Award of contract for multidisciplinary construction -related consultantsApproved
  3. Delegation of award for Lot 7 CDM co-ordinator of the construction related consultants services framework agreementApproved
  4. Consultants for Construction Work Framework Agreement - Award of ContractApproved
  5. Consultants for Construction Works Framework Agreement (Additional Services) - Award of ContractApproved

More from Haringey Cabinet Procurement Committee

All decisions
MeetingDecisionOutcome
12 Apr 2012 Financing the Leisure Service Fitness Suite EquipmentRESOLVED · That the report be noted. Noted Open
12 Apr 2012 Award of coroners' removals contractRESOLVED · That approval be granted for the award of contract for a Coroners’ removal service to Dignity Funeral Ltd ... Approved Open
12 Apr 2012 Contract for the support and maintenance of the Council's IT network, IT security and data centresRESOLVED · That approval be granted to award the replacement contract for the management of the IT network, IT securi... Approved Open
12 Apr 2012 Healthy Alliance - Primary and Secondary Community HIV Prevention Programme for Enfield and HaringeyRESOLVED · That approval be granted to a waiver of the requirements to tender as required under CSO 9.01 as allowed u... Approved Open
12 Apr 2012 Sport and physical activity coaching services suppliers frameworkRESOLVED · That approval be granted for the award of a framework agreement as set out in the report for a minimum per... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies