RESOLVED 1. That in accordance with Contract Standing Order 11.03 framework agreements for conservation building construction works be awarded to the following companies – · Apollo Property Services Group Ltd · Quinn London Ltd · Coniston Limited · T&B (Contractors) Limited · ISG InteriorExterior Plc · Diamond Build plc 2. That the framework agreements be awarded for a period of 2 years with an option to extend for a further 2 years and with an estimated total value of £600,000 per year.
Word for word from the decision Haringey published for this meeting.Source: www.minutes.haringey.gov.uk
Agenda item: [No.] th Cabinet Procurement Committee On 27 April 2010
Report Title. Framework Agreement for Conservation Building Construction Works
Report of Director of Corporate Resources
Signed :
Contact Officer : David Mulford, 020 8489 1037
Wards(s) affected: All Report for: Key Decision
1 Purpose of the report 1.1 To seek Cabinet Procurement Committee approval to award framework agreements for the provision of conservation building construction works for buildings owned or managed by the Council.
2 Introduction by Cabinet Member 2.1 I concur with the recommendations set out in this report.
3 State link(s) with Council Plan Priorities and actions and /or other Strategies: 3.1 The opportunity to procure long term agreements for conservation building construction works was identified through the Council’s Category Management strategy.
4 Recommendations 4.1 In accordance with CSO 11.03 that framework agreements for conservation building construction works be awarded to those companies listed in Appendix 1. 4.2 That the framework agreements be awarded for a period of 2 years with an option to extend for a further 2 years and with an estimated total value of £600,000 per year.
5 Reason for recommendation(s) 5.1 Framework agreements for minor and major building construction works were awarded in January 2006 for a period of 2 years, with the option to extend for up to a further 2 years. Framework agreements were awarded for a period of 2 years from April 2006 and have subsequently be extended twice. The current framework agreements are due to expire on 31st March 2010.
5.2A number of projects for conservation construction works have been procured through these framework agreements, with selection of contractors based on experience of conservation work. However, key client departments expressed a need for specialist conservation work contractors to undertake this type of work in future. The decision was taken to procure a separate framework agreement for the provision of conservation work contractors.
5.3The framework agreements will provide a mechanism for the procurement of building contractors for individual conservation building projects of value less than £500,000.
5.4Selection of contractors will either be through a mini-tender or call-off process. Selection of contractors through a call-off process will be on the basis of the most economically advantageous tender (MEAT) based on the results of the procurement process for the framework agreement and performance measured through key performance indicators (KPI).
5.5The use of a framework agreement will provide a robust contract management process, with key performance indicators used to monitor contractor performance.
6 Other options considered 6.1 The Construction Procurement Group examined the option of using other public sector arrangements for the provision of conservation building construction works. No such arrangements exist which cover the form of contract and extent of this procurement.
7 Summary 7.1 The procurement followed an EU tender process. A contract notice was published on 20th February 2009 via the Official Journal of the European Union (OJEU).
7.2A consultant was commissioned to act as an additional resource to CPG and Council officers in the evaluation of pre-qualification questionnaires and to prepare
Report Template: Formal Bodies 2 the pricing mechanism for the tender document for the procurement. The consultant was commissioned from the Council’s framework agreement for the provision of construction consultants with NPS London Ltd.
7.3Pre-qualification Questionnaires (PQQ) were received from 44 companies. The pre-qualification questionnaires were assessed by officers from CPG, Economic Regeneration and the commissioned consultant.
7.4The 12 companies with the highest scores following evaluation of pre-qualification questionnaires were invited to tender for the framework agreement on 04/11/09. One tenderer declined the opportunity to tender. Tenders were received from 11 companies.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Award of coroners' removals contractRESOLVED · That approval be granted for the award of contract for a Coroners’ removal service to Dignity Funeral Ltd ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.