Resolved
RESOLVED i. That the progress on capital works completed during 2011-12 be noted; and ii. That the proposed bid to the LB Haringey for further Capital funding for 2012-13 be endorsed.
Alexandra Park and Palace Board noted this item on Tuesday 18 October 2011. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED i. That the progress on capital works completed during 2011-12 be noted; and ii. That the proposed bid to the LB Haringey for further Capital funding for 2012-13 be endorsed.
Agenda item:
ALEXANDRA PALACE & PARK BOARD On 18th October 2011
Report Title: Capital Works Update and the Capital Bid 2012-13
Report of: Andrew Gill, Interim General Manager, Alexandra Palace & Park Charitable Trust
1. Purpose 1.1 To update the Board on the progress of 2011-12 Capital Projects. 1.2 To advise the Board on the proposed further 2012-13 Capital Bid to the Council.
2. Recommendations 2.1 The Board is asked to note the progress on capital works during 2011-12. 2.2 The Board is asked to endorse the proposed further bid to the Council for Capital funding for 2012-13
Report Authorised by: Andrew Gill, Interim General Manager
Contact Officer: Mark Neale, Facilities Manager, Alexandra Palace & Park, Alexandra Palace Way, Wood Green N22 7AY Telephone Number: 020 8365 4199.
3. Executive Summary 3.1 The following report summarises the progress on the capital works that are taking place during 2011-12 addressing the condition of the building fabric and services. 3.2 It is proposed that a further bid of £500k be made to the Council for capital funding during 2012-13 to further address the compliance, health & safety issues and poor condition of the building fabric and services at the Palace. Also to support the regeneration strategy which will the subject of a separate report 3.3 These monies would be allocated to further works on the external fabric, replacement of the fire detection systems, replacement of the faulty street and emergency lighting plus refurbishment to the public lifts.
4. Reasons for any change in policy or for new policy development. Not applicable
5. Local Government (Access to Information) Act 1985 5.1 Previous capital bids for 2009-10 and 2010-11. 5.2 Potter Raper Independent Review of the Building and Services
1 6 Capital Expenditure 2011-12
6.1Progress Report on 2011-12 Capital Expenditure The Council allocated a Capital grant of £500,000 to the Trust for 2011-12. In addition £50,000 from the CAPEX grant in 2010-11 has been carried over into 2011-12 to mitigate any outstanding claims that could result for extra works on the ice rink which is still being finalised with the project team and the main contractor.
The following is a progress report on the works that are currently taking place:-
6.1.1 Ice Rink Finalisation of Project Account Further meetings have been held with the Councils Project Management team in order to place pressures on the Principal contractor to finalise the accounts. This is still an ongoing item.
6.1.2 Upgrade of the Data/Comms Infrastructure. The BT data/comms system has now been upgraded to 10 MB/sec with the ability to upgrade to 100 MB/sec should it be required (i.e. at extra cost). A WiFi connection has also been installed in “The Bar & Kitchen”; with access managed through the Bar staff issuing security access codes to customers.
A contract has been placed for the replacement of the site telephone system. Installation has been completed and the system is now live. This project will have addressed the business critical issues of the poor state of the old obsolete telephone system plus providing modern voice communication systems and reduced the operating costs.
6.1.2 Building Dilapidations The second phase of the dilapidation works programme produced though the Councils frameworks consultants NPS in 2010-11 has now been tendered. Initially the costs of the tenders exceeded the allocated capital budget. However by re- engineering the solutions (e.g. netting the South Terrace, fencing off unstable areas and strengthening the fire escape) the costs have been driven down to within the available budget.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
CAPITAL WORKS UPDATE AND CAPITAL BIDMinutes | 230 KB | DownloadRead as text |
Follow Alexandra Park and Palace Board at Haringey and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 29 Oct 2026 | Charitable Trust Progress ReportThe Committee noted the report. | Noted | Open |
| 29 Oct 2026 | FRRAC Chair's Report (Verbal update)The Committee noted the report. | Noted | Open |
| 29 Oct 2026 | Finance ReportThe Committee noted the 2026/27 forecast against revised budget. | Noted | Open |
| 29 Oct 2026 | Panorama Room ReportThe Committee noted the report. | Noted | Open |
| 29 Oct 2026 | Environmental Sustainability UpdateThe Committee noted the contents of this report and approve the Carbon Reduction Plan at Appendix 1. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.