Resolved
RESOLVED That the minutes of the meeting held on 17 November 2011 be approved and signed.
Cabinet Procurement Committee approved this item on Thursday 12 January 2012. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED That the minutes of the meeting held on 17 November 2011 be approved and signed.
MINUTES OF THE CABINET PROCUREMENT COMMITTEE THURSDAY, 17 NOVEMBER 2011
Councillors Reith and Strickland
Apologies Councillor Bevan, Kober and Goldberg
MINUTE ACTON NO. SUBJECT/DECISION BY PROC22. APOLOGIES FOR ABSENCE
Apologies for absence were received from Cllrs Bevan, Goldberg and Kober. Cllr Strickland attended as a substitute. The Committee resolved that Cllr Reith chair proceedings.
PROC23. URGENT BUSINESS
There were no items of urgent business.
PROC24. DECLARATIONS OF INTEREST
There were no declarations of interest.
PROC25. MINUTES
RESOLVED
That the minutes of the meeting held on 6 October 2011 be approved HLDM and signed. S
PROC26. DELEGATION OF AWARD FOR LOT 7 CDM CO-ORDINATOR OF THE CONSTRUCTION RELATED CONSULTANTS SERVICES FRAMEWORK AGREEMENT The Committee considered a report seeking approval to delegate the award of one of the 11 Lots of construction disciplines incorporated in the Pan London Construction Related Consultants Services 2011 framework (CRCS 2011). Haringey was the lead authority for this collaborative procurement approach undertaken as part of the North London Strategic Alliance and the Committee had approved the implementation strategy and action plan for the framework in November 2010. This report constituted the first of two reports seeking the award of various Lots of construction consultancy services, with the appointment of Lot 7 CDM co-ordinators needing to be awarded earlier to fit in with one of the programmes of work. A subsequent report would be submitted to the Committee in January 2012 covering the award of the remaining Lots.
RESOLVED
• That approval be granted to delegate the award of Lot 7 CDM co- ordinators framework agreement within the Construction Related Dir CR MINUTES OF THE CABINET PROCUREMENT COMMITTEE THURSDAY, 17 NOVEMBER 2011
Consultants Services 2011 (CRCS 2011) to the Director of Corporate Resources.
PROC27. INSTALLATION OF SOLAR PANELS ON COUNCIL BUILDINGS USING THE SOLAR PV INSTALLATION AND MANAGEMENT FRAMEWORK AND SOLAR PV COMPONENTS FRAMEWORK LET BY BIRMINGHAM CITY COUNCIL The interleaved report was the subject of a motion to exclude the press and public from the meeting as it contained exempt information relating to the business or financial affairs of any particular person (including the Authority holding that information).
The Committee considered a report updating on implementation of the procurement strategy for the solar photovoltaic installation programme agreed by Cabinet in July and centred on the intended use of frameworks let on behalf of Birmingham City Council. The Committee noted with disappointment the recent government announcement on the reduction of feed in tariffs from 12 December 2011 thereby necessitating the Council placing a hiatus on installations until the market was able to realign with the new tariffs. A second government review of tariffs was planned in due course. It was intended that by virtue of having a framework already in place, the Council would be in a good position to proceed once the market readjusted and installations became viable again. The Committee noted that the framework agreement did not obligate the Council to commit to a programme of works within a set timescale. It was also noted that the anticipated expenditure relating to installation work at key sites in the borough as listed within the exempt appendix was indicative and could be subject to change post December.
RESOLVED • To note the intended use of the Management, supply and installation Dir of energy efficiency and renewable energy and heat measures P&S framework, let by Buy For Good Community Interest Company on behalf of Birmingham City Council, for the installation of solar photovoltaic arrays for any number and combination of the sites listed in the exempt appendix of the interleaved report.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
MINUTESMinutes | 59 KB | DownloadRead as text |
Follow Cabinet Procurement Committee at Haringey and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 12 Apr 2012 | Financing the Leisure Service Fitness Suite EquipmentRESOLVED · That the report be noted. | Noted | Open |
| 12 Apr 2012 | Award of coroners' removals contractRESOLVED · That approval be granted for the award of contract for a Coroners’ removal service to Dignity Funeral Ltd ... | Approved | Open |
| 12 Apr 2012 | Contract for the support and maintenance of the Council's IT network, IT security and data centresRESOLVED · That approval be granted to award the replacement contract for the management of the IT network, IT securi... | Approved | Open |
| 12 Apr 2012 | Healthy Alliance - Primary and Secondary Community HIV Prevention Programme for Enfield and HaringeyRESOLVED · That approval be granted to a waiver of the requirements to tender as required under CSO 9.01 as allowed u... | Approved | Open |
| 12 Apr 2012 | Sport and physical activity coaching services suppliers frameworkRESOLVED · That approval be granted for the award of a framework agreement as set out in the report for a minimum per... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies