It was agreed that the title of the park expenditure line could be amended to read Park and Road, in order to reflect that this included the costs associated with the road, for clarity. · The Finance and Resources Director advised that much of the work of APTL could be viewed as fulfilling the Trust’s charitable purpose, and reported that the Palace was working with its auditors to find ways of making this more explicit. · In response to a question from the Board, it was confirmed that re-classification of the funding received from the Council would have no impact of the Palace’s tax position. It was noted that the financial arrangements between the Palace and the Council had been extensively reviewed from a legal position, and care had to be taken that any changes in this treatment did not go beyond that which had already been established. NOTED
Word for word from the decision Haringey published for this meeting.Source: www.minutes.haringey.gov.uk
3.1The management accounts for the Trust for the year ended 31st March 2013 are tabulated against budget at Appendix 1
3.2The provisional Trust deficit before regeneration costs, and excluding accrued Gift Aid, is £2,428k compared to the budget of £2,602k, an underspend of £174k. Net regeneration expenditure was £556k, £294k lower than the operating budget.
3.3Gift Aid from the Trading Company is expected to be £1.2m. If this is taken into account, the provisional net deficit for the Trust before Regen is £1,228k compared to budget of £1,600k - £372k better than budget. We are requesting that the underspent be carried forward to fund future regen costs.
3.4The Trust’s capital expenditure budget was originally set at £500k but this was later increased to £682k as a consequence of the additional expenditure required for the HHH event. The provisional result of £504k represents an underspend of £178k against the approved revised budget. The underspend is the result of a delay in the start of the English Heritage funded Colonnade works. The Trust requests that the
1 underspend be carried forward to allow the completion of that project.
4. Reasons for any change in policy or for new policy development (if applicable) 4.1 N/A
5. Local Government (Access to Information) Act 1985 5.1 No specific background papers were used in compiling this report.
6. Trust Financial Results
6.1The management accounts for the year ended 31st March 2013 are tabulated against budget at Appendix 1, broken down by the major areas of Trust activity.
7. Legal and Financial Comments
7.1The Council’s Head of Legal Services has no comments on this report.
7.2The London Borough of Haringey Chief Finance Officer notes the provisional figures and confirms that requested carry forward will be included in the June Cabinet report. It is further noted that the Trust plans to bring the final audited accounts to the July Board for ratification.
Equalities implications
8.1There are no perceived equalities implications
9. Use of Appendices / Tables / Photographs
9.1Appendix I – Management accounts for the period ended 31st December 2012
2 Appendix 1
ALEXANDRA PARK AND PALACE CHARITABLE TRUST ALEX02 Mangement Accounts for the 12 Months Ended 31 March 2013 2012 12
Month YTD Budget Actual Variance Budget Actual Variance
INCOME Palace 4,979 4,313 -667 59,750 55,598 -4,152 Licence Fee 15,000 15,000 0 180,000 180,000 0 Park 11,326 23,963 12,637 135,910 143,684 7,774 Other 13 - -13 150 961 811 Total Before Regen 31,318 43,275 11,958 375,810 380,173 4,363 Regen - - 0 40,800 40,760 -40 TOTAL INCOME 31,318 43,275 11,958 416,610 420,933 4,323
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.