RESOLVED i) That, in consideration of legal advice and guidance from CPG, a proposed construction final account sum of £14,658,917.00 be agreed with the Contracotr , Mulalley and Co Ltd, in advance of the project completing. This figure is based on being within the range produced by CPG on review of the construction contract Final Account. ii) This figure makes allowances for loss and expense to the Contractor relating to delays and extensions of time claims on all three phases of the project and also makes allowances for negotiation on variators where there is a discrepancy between the figures presented by the project Quantity Surveyor and the Contractor’s Quantity Surveyor. iii) That approval is granted to increase the cash limited budget by £1,425,119.00 to account for the final account sum and includes allowances for professional fees, furniture, fittings and equipment, ICT and disbursements. Alternative options considered Set out under exempt item 24. Reason for decision Set out under exempt item 24.
Word for word from the decision Haringey published for this meeting.Source: www.minutes.haringey.gov.uk
3.1In consideration of legal advice and guidance from CPG it is recommended that a proposed construction final account sum of £14,658,917 is agreed with the Contractor, Mulalley & Co Ltd, in advance of the project completing. This figure is based on being within the range produced by CPG on review of the construction contract Final Account.
3.2This figure makes allowances for loss and expense to the Contractor relating to delays and extensions of time claims on all three phases of the project and also makes allowances for negotiation on variations where there is a discrepancy between the figures presented by the project Quantity Surveyor and the Contractor’s Quantity Surveyor.
3.3It is recommended that approval is granted to increase the cash limited budget by £1,426,119.00 to account for the final account sum and includes allowances for professional fees, furniture, fittings & equipment, ICT and disbursements.
Alternative options considered
4.1Please refer to the exempt section, Part B, of this report for the alternative options considered.
5. Background information
5.1The Broadwater Farm Inclusive Learning Campus is a construction project to combine three primary schools on the Broadwater Farm estate, comprising of two special schools and one mainstream primary school, to form an inclusive learning campus. The contract was awarded under a competitive tendering exercise to Mulalley & Co Ltd in July 2010 at a contract value of £11,990,415 within an approved project cash limited budget of £16,925,491.
Page 2 of 4 5.2 The project is being completed over three phases, Phase 1 commenced in July 2010 and completed in September 2011, phase 2 commenced in July 2011, and completed in December 2012, Phase 3 commenced in January 2013 and is due to complete in June 2013. The schools have remained open and in operation throughout the construction works through a phased decant and occupation strategy.
5.3A revised cash limit budget for the project was approved by Cabinet in October 2012 at £17,619,955 and includes allowances for construction costs, professional fees, furniture, fittings & equipment, ICT and disbursements.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.