Cabinet Member Signing, Monday 10 August 2026 at 2.00pm

Major Works Programme Broadwater Farm Estate

Approved Executive 1 paper

AI summaryHaringey Cabinet Member approves contract variation for Broadwater Farm Estate major works, extending programme to April 2027 to cover fire safety compliance and concealed defects across eight blocks. Cost details are in an exempt appendix.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedProgramme extended, final account position endorsed
MoneyNot disclosedFigures in exempt Appendix A
What happens nextCompletion by April 2027Works to eight blocks continue
Who it affectsBroadwater Farm Estate residentsEight residential blocks

What was decided

The Cabinet Member approved a variation to the contract sum and programme for the Broadwater Farm External Major Works Programme, under Contract Standing Orders 2.01(d), 2.01(e) and 18.03.3. Report 3.1

The anticipated final account position was approved, covering cost drivers from regulatory, technical and contractual requirements, with commercial controls applied to ensure value for money. Report 3.2

The professional services contract with Ridge and Partners must also be varied to reflect the added scope. Report P46

Why

Once contractors gained full site access, previously concealed defects and constraints emerged, requiring further surveys, revised methodologies and changes to scope to meet statutory requirements, including fire safety legislation for Higher Risk Residential Buildings. Report 6.4, 6.7, P19

The works cover concrete repairs, balcony waterproofing, flooring renewal, sandblasting, drainage repairs and redecorations using A2 fire-rated coating, intended to keep the buildings safe, weather-tight and compliant pending the wider estate regeneration. Report 4.1, 4.2

Additional requirements included asbestos and lead-based paint surveys, intrusive concrete testing, fire risk mitigation, security upgrades and balcony repairs instead of replacement due to planning constraints. Report 6.8, P22

What happens next

Completion of the eight-block programme is now anticipated in April 2027, with the scope revised and sequencing adjusted accordingly. Report 6.9, 8.2

Final account discussions are ongoing, with further variations to be reviewed as part of capital programme management. Report P42

Lessons learned, including the need for intrusive surveys, early regulatory engagement and clearer risk allocation, are being embedded into future capital delivery strategies. Report P35

Options considered

  • Rejected: Do nothing. A contractor has already been appointed and works are in progress; delay would leave the eight blocks incomplete, cause further deterioration and continued water ingress from balconies. Report P6, P7
  • Rejected: Pause works and complete them as part of the full estate regeneration. Lengthy timescales for the wider regeneration programme and unacceptable risk of continued deterioration of the blocks during the interim period. Report 5.2

Implications

  • Legal: The variation is treated as a modification under Regulation 72(1)(b) of the Public Contracts Regulations 2015, with the increase within the 50% threshold, and the original procurement was via Lot 2.2 of the London Construction Programme Framework Agreement. Report P49, P50, P51, P52, P53, P54, P56
  • Financial: Costs have been subject to commercial challenge; existing contract rates have been applied where possible, with benchmarking used where required. The original provisional allowance for unforeseen works was not sufficient. Report 8.3, P32, P43
  • Equalities: The decision primarily impacts council tenants, with BAME and disabled people overrepresented in the housing stock; works will be adapted where residents have disabilities and engagement will identify specific needs. Report P61, P63
  • Climate: The project is expected to have minimal carbon and climate impact, though replacement of external lighting with low-energy components and repair of fractured drainage will contribute to carbon and water savings. Report 10.1
  • Risk: Risks around latent defects, regulatory change, programme and budget have been managed through technical assurance, early regulatory engagement and commercial oversight; the overall position is considered stable and controlled. Report 9.1, P34, P35
  • Other: Strategic Procurement flagged scope creep and cost risk where requirements were not fully defined at the outset, and noted reputational and operational consequences if health and safety works were not undertaken. Report P44, P45

Who and where

  • Residents of eight blocks on the Broadwater Farm Estate, including overrepresented BAME and disabled tenants Report 6.1, P61
  • The contractor delivering the External Major Works Programme Report 6.5, 6.6
  • Ridge and Partners, the professional services provider whose contract must be varied Report P46

Timeline

  • 18 June 2025: Original contract for the External Major Works Programme approved by Cabinet, with a provisional allowance for unforeseen works Report 6.5
  • 2026-08-10: Cabinet Member Signing approves the contract variation and final account position
  • April 2027: Anticipated completion of the eight-block works, following programme extension Report 6.9, 8.2

Plain English for the jargon

  • CSO: Contract Standing Orders, the council's rules for procuring and varying contracts
  • A2 fire-rated coating: A coating meeting A2-s1, d0 classification under fire safety standards for building materials
  • Reg 72(1)(b): A rule under the Public Contracts Regulations 2015 allowing contract modification without a new procurement for necessary additional works, where change of contractor is not feasible and price rise is under 50%
  • BWF: Broadwater Farm, referring to the estate and its major works programme
  • Higher Risk Residential Building: A residential building classified as high risk under fire safety legislation, requiring stricter compliance
  • Latent defects: Building faults concealed within the structure and not discoverable at the time of survey
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item6

Resolved

DECLARATIONS OF INTEREST FOR THIS ITEM: NONE RESOLVED It was recommended that the Cabinet Member: Approve pursuant to Contract Standing Orders CSO 2.01(d), 2.01(e) and 18.03.3, the variation to the contract sum and programme for the Broadwater Farm External Major Works Programme, as set out in Appendix A (Exempt Report). Approve the anticipated final account position, including the principal cost drivers arising from regulatory, technical and contractual requirements, and the commercial controls applied to ensure value for money, as set out in the report. Reasons for decision The BWF - External Major Works Programme was brought forward to prevent further deterioration of key external and some internal building elements while the estate ? wide refurbishment programme is developed and delivered. Works had been identified to eight blocks on the estate and included concrete repairs, balcony waterproofing, renewal of flooring to internal areas, sandblasting to remove existing paint from concrete elements, drainage repairs, and redecorations using an A2 fire-rated coating. These works would ensure the buildings remain safe, weather-tight, and compliant with current fire-safety regulations, helping to prevent increased safety risks, accelerated asset deterioration, and additional pressure on the responsive repairs budget. Alternative options considered Do nothing: This option was considered but discounted. A contractor had already been appointed, and works were currently in progress. Any delay in approving the variation to the contract sum and programme would leave the eight blocks incomplete, which would negatively affect the condition of the buildings and lead to further deterioration of key building elements. Failure to approve the variation would also result in continued water ingress from the balconies, which in turn would lead to increased resident dissatisfaction due to the ongoing issues affecting the blocks. The project team also considered pausing the works and completing them as part of the full estate regeneration. This option was discounted due to the lengthy timescales associated with the wider regeneration programme and the unacceptable risk of continued deterioration of the blocks during the interim period.
Word for word from the decision Haringey published for this meeting. Source: www.minutes.haringey.gov.uk

Follow this further

Built from Haringey's papers

What the report saysPro

Report to Cabinet Member Signing

Recommendations

It is recommended that the Cabinet,

3.1Approves, pursuant to Contract Standing Orders CSO 2.01(d), 2.01(e) and 18.03.3, the variation to the contract sum and programme for the Broadwater Farm External Major Works Programme, as set out in Appendix A (Exempt Report).

3.2Approves the anticipated final account position, including the principal cost drivers arising from regulatory, technical and contractual requirements, and the commercial controls applied to ensure value for money, as set out in the report.

Reasons for decision

4.1The BWF - External Major Works Programme was brought forward to prevent further deterioration of key external and some internal building elements while the estate‑wide refurbishment programme is developed and delivered.

4.2Works have been identified to eight blocks on the estate and include concrete repairs, balcony waterproofing, renewal of flooring to internal areas, sandblasting to remove existing paint from concrete elements, drainage repairs, and redecorations using an A2 fire-rated coating. These works will ensure the buildings remain safe, weather-tight, and compliant with current fire-safety regulations, helping to prevent increased safety risks, accelerated asset deterioration, and additional pressure on the responsive repairs budget.

5. Alternative options considered 5.1 Do nothing: This option was considered but discounted. A contractor has already been appointed, and works are currently in progress. Any delay in approving the variation to the contract sum and programme would leave the eight blocks incomplete, which would negatively affect the condition of the buildings and lead to further deterioration of key building elements.

Failure to approve the variation would also result in continued water ingress from the balconies, which in turn would lead to increased resident dissatisfaction due to the ongoing issues affecting the blocks.

5.2The project team also considered pausing the works and completing them as part of the full estate regeneration. This option was discounted due to the lengthy timescales associated with the wider regeneration programme and the unacceptable risk of continued deterioration of the blocks during the interim period.

6. Background information

6.1The Broadwater Farm External Major Works Programme was developed as a time‑limited interim intervention to address deterioration across eight residential blocks, pending the delivery of the wider estate regeneration programme.

6.2The works were intended to maintain buildings in a safe, compliant and weather‑tight condition, reduce responsive repairs, and mitigate risks associated with structural deterioration and water ingress.

6.3The original scope focused on repair and protection works and was developed based on visual, non-intrusive surveys. Intrusive investigations and full regulatory assessments were not undertaken at tender stage.

6.4Once on site, with full access enabled (including removal of coatings and scaffold installation), previously concealed defects and constraints became apparent. This required further surveys, revised methodologies and changes to scope to ensure compliance with statutory requirements.

Original Contract Position

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Major Works Programme Broadwater Farm EstateMinutes 271 KB DownloadRead as text

At this meeting

Whole meeting
6Major Works Programme Broadwater Farm EstateThis decision
7Exclusion of the Press and PublicOn the agenda

Who was there

1 of 1 attended
DJ
Councillor Dixie-Ann JosephCommittee Member, present

On this subject at Haringey

Search all
  1. Major Works Programme Broadwater Farm EstateThis decision
  2. Hamilton Close Major Works ProgrammeApproved
  3. Hostels - Major Works ProgrammeDecided
  4. Tower Gardens - Major WorksDecided
  5. Turner Avenue Estate External Major Works Phase Two (2025-2026)Approved
  6. Broadwater Farm Major works programmeApproved

More from Haringey Cabinet Member Signing

All decisions
MeetingDecisionOutcome
2 Nov 2026 Deaf Outreach Services ContractDECLARATIONS FOR THIS ITEM: NONE Decided Open
28 Oct 2026 Administrative amendment to Merchant Acquirer Re-ProcurementRESOLVED 1. To note the administrative error in the original report referring to Global Pay and Global Payments; 2. T... Noted Open
20 Oct 2026 Approval of Additional Expenditure and Final Payment to Accora Limited reportDECLARATIONS FOR THIS ITEM: NONE RESOLVED The Cabinet Member for Adults and Health: 1. Approved the variation of cont... Approved Open
16 Oct 2026 Approve Funding from Arts Council England to Haringey Music Service for the North London Music HubDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
13 Oct 2026 Filming at meetingsThe notice of filming at meetings was noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies