Resolved
RESOLVED That the Board note the progress made by LBH, APPCT and APTL in implementing the recommendations of the report and approve the updated Terms of Reference of the Regeneration Working Group.
Alexandra Park and Palace Board noted this item on Tuesday 16 July 2013. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED That the Board note the progress made by LBH, APPCT and APTL in implementing the recommendations of the report and approve the updated Terms of Reference of the Regeneration Working Group.
Alexandra Palace & Park Board 16th July 2013
Report Title: Response to Governance Review
Report of: Duncan Wilson, Chief Executive, Alexandra Palace Charitable Trust
1. Purpose 1.1 This paper summarises Alexandra Palace’s response to the internal audit report on the governance arrangements for the Regeneration Programme, as reported to the FRAC on 7 July.
2. Recommendations 2.1 The Board is asked to note the progress made by LBH, APPCT, and APTL in implementing the recommendations of the report and approve the new proposed Terms of Reference of the Regeneration Working Group.
Report Authorised by: Duncan Wilson, Chief Executive Alexandra Place and Park Trust
Contact Officer: Duncan Wilson, Chief Executive, Alexandra Palace & Park, Alexandra Palace Way, Wood Green N22 7AY Tel No. 020 8365 4340
3. Executive Summary In response to the internal Audit review 3.1 financial procedures have been updated although there is still more work to do 3.2 further work is needed on detailed specification of key roles 3.3 Regen Working Group membership will be increased 3.4 the Project Initiation Document is being rewritten as 3.5 New Terms of reference for RWG are included for approval
4. Reasons for any change in policy or for new policy development (if applicable) 4.1
5. Local Government (Access to Information) Act 1985 5.1 N/A 6. Background
6.1A Gateway Review of the regeneration project in July 2012 identified the need to “develop a unified and credible client”, by which it meant that the respective roles and responsibilities of LBH, APPCT, the Regeneration Working Group (RWG) needed clarifying and working relationships needed to be improved. In the light of this, Deloitte were commissioned to undertake their internal audit review of governance arrangements.
The report, which was completed in May 2013, gave limited assurance and made recommendations in five key areas. It is reproduced in full in Appendix 1 with management response.
• KEY RECOMMENDATIONS AND PROGRESS IN IMPLENTING THEM
A commitment has been given that all five recommendations will be addressed by the end of July 2013. A summary of progress to date is given below.
Recommendation 1: Updating financial procedures
The following items are being reported in detail to the Finance Resources and Audit Committee on 9 July: • Procurement procedures for both APPCT and APTL have been updated in the light of current public sector procurement rules and LBH requirements. • A budgetary framework with clearly identified budget holders and supporting management reporting is in place for both APPCT and APTL. • A system of delegated authority and authorisation limits for individual purchase transactions is in place and maintained within the Exchequer accounting system. • Detailed manuals for the use of the new Exchequer system are in the process of being finalised. They will be completed by the end of July 2013.
APPCT and LBH are still in discussion about Service Level Agreements for LBH services such as procurement at the time of writing. An oral update will be given at the meeting.
The conclusions of the FRAC discussion will be reported orally at the Board meeting.
Recommendation 2: Clear identification of key roles
The internal audit report focusses on the importance of clear identification of a “Programme (Project) Sponsor” and a “Senior Responsible Officer (SRO)”.
Definitions are as follows:
(i) From the governance review:
“The Project Sponsor is ultimately responsible and will: (i) Show active commitment by leading from the front (ii) Review and approve project documentation (iii) Receive project highlight reports and review progress against the plan and business case (iv) Resolve project risks and issues (v) Provide overall direction to the project manager (vi) Monitor and manage cost and (vii) Report to the Management Team on progress”
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
.1 Alexandra Palace: Regeneration Programme Governance Arrangements: Final IA Report 2012-13Appendix 10 | 304 KB | Download |
PDF |
Governance Review and responseMinutes | 231 KB | DownloadRead as text |
Follow Alexandra Park and Palace Board at Haringey and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 29 Oct 2026 | Charitable Trust Progress ReportThe Committee noted the report. | Noted | Open |
| 29 Oct 2026 | FRRAC Chair's Report (Verbal update)The Committee noted the report. | Noted | Open |
| 29 Oct 2026 | Finance ReportThe Committee noted the 2026/27 forecast against revised budget. | Noted | Open |
| 29 Oct 2026 | Panorama Room ReportThe Committee noted the report. | Noted | Open |
| 29 Oct 2026 | Environmental Sustainability UpdateThe Committee noted the contents of this report and approve the Carbon Reduction Plan at Appendix 1. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.