Resolved
RESOLVED That the contents of the report be noted.
Alexandra Park and Palace Board noted this item on Tuesday 29 October 2013. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED That the contents of the report be noted.
Agenda item:
Alexandra Palace & Park Board 29 October 2013
Report Title: Report of the Director of Property & Regeneration, Alexandra Park and Palace
Report of: Kerri Farnsworth, Director of Property & Regeneration, Alexandra Park and Palace
1. Purpose 1.1 To update the Board on recent developments and activities, in particular:-
i) Fabric Conservation (incl Theatre) ii) HLF Project Progress iii) Commercial Development Opportunities iv) Regeneration Programme governance & team restructure v) Forward 12-mth Programme for Property & Regeneration
2. Recommendations 2.1 That the Board notes the contents of the report and expresses its views as appropriate.
Report Authorised by: Duncan Wilson, Chief Executive Alexandra Palace and Park
Contact Officer: Kerri Farnsworth, Director of Property & Regeneration, Alexandra Park and Palace, Alexandra Palace Way, London N22 7AY Tel: 0208 465 4316
3. Executive Summary 3.1 Fabric Conservation & Facilities Maintenance 3.2 HLF Project Progress 3.3 Commercial Development 3.4 Regeneration Programme governance & team restructure 3.5 Forward 12-mth Programme for Property & Regeneration
4. Reasons for any change in policy or for new policy development (if applicable) 4.1 N/A
5. Local Government (Access to Information) Act 1985 5.1 N/A 6. Fabric Conservation & Facilities Maintenance
English Heritage Fabric Repair project
6.1Works to both the SE pavilion and the Southern Colonnade have now achieved practical completion in line with agreed programme and budget, with only minor site clearance remaining.
6.2English Heritage have been pleased with both the quality of the works carried out by the contractor and the management of the works by the Trust. They have indicated a willingness to work with APPCT again, subject to a longer-term fabric maintenance strategy being put in place (see item 6.6 below).
Interim repairs - Theatre and North Wall
6.3A decision was taken to undertake interim repairs to the Theatre auditorium ceiling roof in advance of the main HLF project. The reason for this was that by securing the ceiling and enabling public usage of the space, APPCT would have a ‘window’ of 12-18 months (dependent upon when the HLF works physically commence onsite) in which to test the programming and the actual in-house operations aspects of events in the Theatre auditorium - both of which are fundamental to its long-term success.
6.4After initial investigations it was discovered that the access arrangements from above the auditorium ceiling, which had been assumed to be in place to enable the repairs to be undertaken, were in need of improvement. Works are hence now underway to permanently improve above-ceiling access and then to carry out the ceiling repair works (consisting mainly of re-fixing and reinforcing previous interventions). These works will be completed by end of November 2013.
6.5Urgent repairs are also being carried out to the North Wall to secure and/or remove loose cement render and vegetation (ivy). These works should be complete by November 2013. To take advantage of the temporary access structures, a structural survey was also undertaken which has identified a number of potential additional remedial works.
Surveyor to the Fabric
6.6Following an external competitive tender process, the conservation architects Purcell have been invited to take up the role of Surveyor to the Fabric. Their first task will be to complete by the end of the year a ‘Fabric Maintenance Plan’ (FMP) which sets out a prioritised strategy for fabric repairs & maintenance for the Palace for the next 10 years.
Victorian Theatre Stage Machinery
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Report of the Director of Regeneration and PropertyMinutes | 267 KB | DownloadRead as text |
Follow Alexandra Park and Palace Board at Haringey and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 29 Oct 2026 | Charitable Trust Progress ReportThe Committee noted the report. | Noted | Open |
| 29 Oct 2026 | FRRAC Chair's Report (Verbal update)The Committee noted the report. | Noted | Open |
| 29 Oct 2026 | Finance ReportThe Committee noted the 2026/27 forecast against revised budget. | Noted | Open |
| 29 Oct 2026 | Panorama Room ReportThe Committee noted the report. | Noted | Open |
| 29 Oct 2026 | Environmental Sustainability UpdateThe Committee noted the contents of this report and approve the Carbon Reduction Plan at Appendix 1. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.