RESOLVED to i) Note the updates on regeneration of Alexandra Palace, including HLF project and commercial development opportunities, plus the forward work programme for 2014. ii) Note the progress on fabric maintenance, facilities management service provision and commercial leases/licences. iii) Agree the variation to the existing Grounds Maintenance Contract held with John O’Connor to allow for the maintenance of beds in the Palm Court at a monthly cost of £625+ VAT; and authorise Officers to finalise discussions with the Contractor, and LB Haringey’s Assistant Director of Corporate Governance to seal the finalised contract variation. iv) Note the progress on the Campsbourne Play Centre and authorise Officers to enter lease negotiations with the sitting tenant.
Word for word from the decision Haringey published for this meeting.Source: www.minutes.haringey.gov.uk
2.2Notes the updates on regeneration of Alexandra Palace, including HLF project and commercial development opportunities, plus the forward work programme for 2014. 2.3 notes progress on fabric maintenance, facilities management service provision and commercial leases/licences 2.4 agrees a variation to the existing Grounds Maintenance Contract held with John O’Connor to allow for the maintenance of beds in the Palm Court at a monthly cost of £625 + VAT; and authorises Officers to finalise discussions with the Contractor, and LB Haringey’s Assistant Director of Corporate Governance to seal the finalised contract variation 2.5 notes the progress on the Campsbourne Play Centre and authorises Officers to enter lease negotiations with the sitting tenant
Report Authorised by: Duncan Wilson, Chief Executive Alexandra Palace and Park
3. Contact Officer: Duncan Wilson, Chief Executive Alexandra Palace and Park
4. Executive Summary 4.1 Updates within the regeneration and property programme include - HLF ‘Restoring the People’s Palace’ project progress - Facilities Management - Fabric Conservation - Commercial Development; and - key milestones within the forward programme for 2014 - Park Dog Control Orders - Park Grounds Maintenance Contract; and - planning applications affecting the Palace and/or Park. 5. Reasons for any change in policy or for new policy development (if applicable) 5.1 N/A
6. Local Government (Access to Information) Act 1985 6.1 N/A
7. Regeneration Programme
HLF professional team procurement
7.1The Activity Planning element of the HLF project has now been procured, with award- winning specialists Tricolor appointed to work alongside Barker Langham.
7.2The procurement of the final major specialist team member on Collections Management is underway and should be concluded by the end of May.
HLF Project Progress
7.3The design team are now fully-engaged in developing concept designs for the HLF project. Presentations on both the design and interpretation were made at the Regeneration Strategy Group workshop and at the SAC-CC in April, and have been warmly welcomed to date. Members of the design team were also present at the Theatre awareness-raising event in April to talk through their work with guests, with feedback being again very positive.
7.4A number of surveys and investigative works have been procured, completed and/or are underway. These surveys and investigations have been designed to fill gaps in existing available data and knowledge, and will provide a sound benchmark for the design development and associated cost testing over the next few months.
7.5The team’s Stage 1 work took slightly longer than anticipated, largely due to the recognition of the need for more detailed and specific investigations to test assumptions, plus the need to ensure that the project’s ambitious scope and aspirations are achievable within the available budget.
7.6In order to achieve the current cost budget there have had to be in-depth testing of the scope of the project and design, as well as a considerable amount of ‘value engineering’ ie. testing of design options against a set of cost/benefit parameters, including conservation considerations, community benefit, commercial impact and aesthetics. Key stakeholders such as English Heritage and LB Haringey Conservation have been actively engaged throughout this process to establish their support for the evolving scheme scope and design concepts.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.