RESOLVED to approve the proposed programme of priority works and delivery programme for 2015/16, with the proposed Fabric Maintenance Plan work packages to be deferred into future years, and, to note the update on the Fabric Maintenance Plan and services.
Word for word from the decision Haringey published for this meeting.Source: www.minutes.haringey.gov.uk
Report of: Emma L Dagnes, Interim Chief Executive, Alexandra Park and Palace
1. Purpose 1.1 To seek approval for a proposed programme of priority works and delivery programme for 2015/16 with the proposed Fabric Maintenance Plan work packages to be deferred into future years and to provide an update on the Fabric Maintenance Plan and services.
2. Recommendations 2.1 That the Board approves the proposed programme of priority works and delivery programme for 2015/16 and the proposed Fabric Maintenance Plan work packages to be deferred into future years and notes the contents of this report.
Report Authorised by: Emma L Dagnes, Interim Chief Executive Alexandra Palace and Park
Contact Officer: Emma L Dagnes, Interim Chief Executive, Alexandra Palace Way, Wood Green N22 7AY Tel No. 020 8365 4335
3. Executive Summary 3.1 The Board is asked to approve the work packages as detailed within the report 3.2 The Board is asked to note the content of this report
4. Reasons for any change in policy or for new policy development (if applicable) 4.1 N/A
5. Local Government (Access to Information) Act 1985 5.1 N/A 6. Fabric Maintenance Plan
6.1The Fabric Maintenance Plan, prepared by the Surveyor to the Fabric, Purcell, recommended Work packages in the region of £387,700 for Year 2 of the ten year plan, for the financial year 2015/16, which included a carry-over of £58,000 from 2014/15 on the proposed Roof Repair Package. The Roof Repair Package having been delayed to carry out a specialist leak detection survey will focus on the causes of the defects and reduce the extent of the repairs to the vast roofs.
The budget available for repairs and renewals to the fabric of the buildings is in the region of £100,000 for 2015/16 plus any permitted carry over from 2014/15. We have therefore carried out a thorough review of the repair priorities, and the Trust will be concentrating on making the external envelope weather-tight and safe to access. This should minimise any further deterioration and unnecessary expense, and avoid any adverse impact on event operations and to the general public.
The priority works packages are as follows:-
Roof Repair Package Urgent glazing repairs to Palm Court Repair of leaking roofs, glazing and abutments to: West Corridor roof; Great Hall east gutter; Area 7 roof/external wall; East Court gutters, drainage and glazing
Permanent Roof Access Provision of handrails to Great Hall gutters, to provide safe access to existing latch-wire access and additional latch-wires on corner flat roofs to allow access and maintenance Recommissioning of existing latch-wire access to Great Hall, and adding walkways to missing sections, to facilitate safe inspection of whole roof and further identify defects to glazing Provision of latch-wire and straps to West Yard Service Building, to provide safe access to smoke vents and edge protection to north wall
Joinery repairs and redecoration Extensive repairs to rotten timber doors, overhaul of windows, renewal of draught-proofing, and redecoration throughout to Palm Court, Londesborough Room, and Bar & Kitchen
Great Hall – Clean fabric linings and walkways Dry cleaning of canopy fabric linings and ducting/walkways to remove excessive dust build up to improve appearance and reduce potential fire risk, and minimise potential disturbance to installation of new amenity lighting under the SIF project Interim Repairs to North Wall Inspections and holding repairs to interior and external face of free standing large brick wall, pending a more major restoration project, to ensure the safety of the wall and to users of the North Yard, West Yard and The Lab car-park
South Elevation/Traitor’s Gate - Brick and render repairs Consolidation of spalling and missing brickwork to main corner piers and repairs to render plinths, to make safe and presentable to the public, subject to budget availability
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.