Resolved
RESOLVED that the performance of the Trust be noted.
Alexandra Park and Palace Board noted this item on Tuesday 16 February 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the performance of the Trust be noted.
The Board is asked to note the performance of the Trust.
Report Authorised by: Louise Stewart, Chief Executive Officer, Alexandra Park and Palace
Contact Officer: Contact Officer: Natalie Layton, Executive Assistant, Alexandra Park and Palace, Email: [email removed], Telephone: 020 8365 4335
3. Reasons for any change in policy or for new policy development (if applicable) N/A
4. Local Government (Access to Information) Act 1985 N/A
5. Table 1. Incoming Resources – Unrestricted Funds
The Trust funds its unrestricted activities from the London Borough of Haringey (LBH) operating grant and in 2015-16 this grant is £1,900k. It also funds its activities from income received from the Park and Palace tenants of £180k and this income is on target to be achieved. The Trading company pays an annual licence fee for using the Park and Palace which as per current Licence Agreement is £190k pa (Agreement to be renewed in 2016). The Trading company gift aid target has been revised to £1,633k (£537k up on budget) due to exceptional performance of trading activities, in particular because of additional income from Events and associated catering offer.
The forecast of unrestricted incoming resources for 2015/16 is £3.9m (budgeted at £3.4m).
6. Table 1. Overheads
YTD the majority of budgeted expenditure is on target. Under-spending on Legal and Professional fees is attributable to the hotel project. Maintenance of Park and Palace is likely to be spent on ongoing minor repairs. The Marketing, Advertising and Design budget has been underspent due to a lack of human resource in the Trust and the expenditure has been partly borne by the Trading company; this will be subject to appropriate internal recharge of costs at the year end.
7. Table 2. Designated Funds (Fixed Assets)
The Capital Grant from LBH for 2015-16 is £400k and in addition there is an agreed balance carried forward from 2014-15 of £116k making a total available of £516k. YTD spending and committed projects are on target to expend in 2015-16 – refer to Table 2 for details.
The Trust has been advanced a SIF loan from LBH of £278k for a replacement of lighting in the Great Hall. The loan is repayable over 7 years with 1 st repayment of £44,417 due on 1st April 2016. The project is now completed and a new LED lighting will enable annual savings in maintenance and energy usage.
8. Table 3. Restoration Project (Restricted Funds)
The current forecast of incoming resources for the Project in 2015-16 is £1,735k being £500k from LBH and £1,235k from the HLF (as per The HLF Agreement 70% of the Project’s expenditure is funded by HLF and 30% by LBH and fundraising).
Since the start of Phase 2, two Claims for funding to HLF have been submitted and payment received. Table 3 provides details of forecast expenditure for the Project in 2015-16, this is subject to revisions as advised by the Project manager Mott MacDonald – we are currently awaiting a revised 2016-2018 Cash Flow Projection and in the new financial year we will report on the income and expenditure over a duration of the Project to enable a meaningful monitoring of its progress
9. Table 4. Consolidated position of the Trust (for information only) Table 1: APPCT Unrestricted Funds
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
ALEXANDRA PARK AND PALACE TRUST FINANCIAL RESULTS FOR PERIOD 30 NOVEMBER 2015 AND ANNUAL FORECASTMinutes | 397 KB | DownloadRead as text |
Follow Alexandra Park and Palace Board at Haringey and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 29 Oct 2026 | Charitable Trust Progress ReportThe Committee noted the report. | Noted | Open |
| 29 Oct 2026 | FRRAC Chair's Report (Verbal update)The Committee noted the report. | Noted | Open |
| 29 Oct 2026 | Finance ReportThe Committee noted the 2026/27 forecast against revised budget. | Noted | Open |
| 29 Oct 2026 | Panorama Room ReportThe Committee noted the report. | Noted | Open |
| 29 Oct 2026 | Environmental Sustainability UpdateThe Committee noted the contents of this report and approve the Carbon Reduction Plan at Appendix 1. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.