Resolved
RESOLVED that i) The performance of the Trust and the attached timetable for submitting the annual accounts be noted; and ii) A salary increase of 2% for all Trust employees effective from 1 st April 2016 be approved.
Alexandra Park and Palace Board noted this item on Tuesday 12 April 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that i) The performance of the Trust and the attached timetable for submitting the annual accounts be noted; and ii) A salary increase of 2% for all Trust employees effective from 1 st April 2016 be approved.
2.1To note the performance of the Trust and the attached timetable for submitting the annual accounts.
2.2To approve a salary increase of 2% for all Trust employees effective from 1st April 2016.
Report Authorised by: Louise Stewart, Chief Executive Officer, Alexandra Park and Palace
Contact Officer: Natalie Layton, Executive Assistant, Alexandra Park and Palace Email: [email removed] , Telephone: 020 8365 4335
3.2The report provides the financial results for the period ending 29 th February. Variations since the figures were presented to the Board in February, include:
An increase of £615k Gift Aid from Alexandra Palace Trading Limited, which will increase a balance of unrestricted reserves carried forward to 2016-17; £516k capital grant funds carried forward from 2014-15 and 2016-17 spent as planned on capital projects; Re-allocation of HLF project costs of 250k from 2015-16 to 2016-17 to allow for removal of asbestos before the works can continue.
3.3The report recommends a 2% staff salary increase in accordance with the salary increase agreed by APTL in February for Trading Company staff. Staff salaries have not increased since October 2014. 4. Reasons for any change in policy or for new policy development (if applicable) N/A
5. Local Government (Access to Information) Act 1985 N/A
6. Table 1 – Incoming Resources
6.1All sources of unrestricted income are shown in Table 1 below. The main source of income is the LBH’s (London Borough of Haringey) operating grant of £1,900k.
6.2£180k of income from Park and Palace leases is on target to be achieved. Income from Park Leases shows additional £48k income which represents the cost of maintenance and repairs recharged to tenants (see corresponding over-spending in maintenance expenditure).
6.3APTL (Alexandra Palace Trading Limited, ‘the Trading Company”) is charged £190k for the use of the Palace premises. The Licence Agreement is due for a renewal in 2016-17 and an increased licence fee is being considered to reflect 1) use of the Palace premises as well as the Park for commercial activities and 2) increased commercial benefit (turnover) generated by APTL .
6.4The Trading Company Gift Aid target has been revised to £1,712k (£615k up on budget) due to the exceptional performance of all trading activities, in particular because of additional income from events and associated catering offers.
7. Table 1 – Overheads
7.1For the year-to-date most budgeted expenditure is on target. Under-spending on Legal and Professional fees is attributable to the hotel project as well as a Governance Review project and a Strategic Vision review – both were provisionally booked to start by the end of 2015-16 but have been delayed until 2016-17 (hence funds will be carried forward in reserves).
7.2The Marketing, Advertising and Design budget has been under-spent due to a lack of resource in the Trust and the expenditure has been partly borne by the Trading Company.
8. Table 2 – Designated Funds (Fixed Assets)
8.1Capital Grant funding from LBH for 2015-16 was £400k and in addition there was an agreed balance carried forward from 2014-15 of £116k making a total of £516k available. To date spending and committed projects are on target to expend this budget in 2015-16 – refer to Table 2 below for details. 9. Table 3. Restoration Project (Restricted Funds)
9.1The current forecast of incoming resources for the Heritage Lottery Fund (HLF) sponsored project in 2015-16 is £1,570k. In accordance with the HLF Agreement 70% of the Project’s expenditure is funded by HLF and 30% by LBH and fundraising - £500k from LBH and £1,070k from the HLF.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
TRUST FINANCIAL REPORT (AND ANNUAL ACCOUNTS TIMETABLE)Minutes | 260 KB | DownloadRead as text |
Follow Alexandra Park and Palace Board at Haringey and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 29 Oct 2026 | Charitable Trust Progress ReportThe Committee noted the report. | Noted | Open |
| 29 Oct 2026 | FRRAC Chair's Report (Verbal update)The Committee noted the report. | Noted | Open |
| 29 Oct 2026 | Finance ReportThe Committee noted the 2026/27 forecast against revised budget. | Noted | Open |
| 29 Oct 2026 | Panorama Room ReportThe Committee noted the report. | Noted | Open |
| 29 Oct 2026 | Environmental Sustainability UpdateThe Committee noted the contents of this report and approve the Carbon Reduction Plan at Appendix 1. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.