Resolved
RESOLVED that the report be noted.
Regulatory Committee noted this item on Monday 21 January 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the report be noted.
Report for: Regulatory Committee
Title: Planning Services 2018/19 (April – December) update
Report authorised by : Emma Williamson, Assistant Director, Planning
Lead Officer: Dean Hermitage, Matthew Patterson, Neil Goldberg, Fortune Gumbo, Bob McIver
Ward(s) affected: N/A
Report for Key/ Non Key Decision: for information
1. Describe the issue under consideration A report on the work of the Planning Service in the financial year 2018/19 (April – December) to date.
2. Recommendations a) That this report be noted
3. Reasons for decision Not applicable
4. Alternative options considered This report is for noting and as such no alternative options were considered.
5. 2018/19 (April – December) work report
Development Management
Applications during 2018/19: 2663 Applications in same period 2017/2018: 2517 Number of cases on-hand end December 2018: 468 Appeals during 2018/19: 71 Appeals dismissed (won) during 2018/19: 48 Cumulative performance (applications in time) during 2018/19: o Majors : 100% o Minors : 98% o Others : 98% o PSO : 90% o Validation: 12 working days
As requested at the July Regulatory Committee Appendix One explains the categories of applications.
Page 1 of 10 Performance overview
5.1Performance is at 100% for ‘Majors’ Applications and remains at the top quartile in London. Our performance for ‘Minor’ applications has improved and also remains at the top quartile in London at 98%. ‘Other’ applications are also maintained at top quartile in London at 98%. Performance has continued to improve and we expect to continue to be top quartile in all categories for the whole of this year.
5.2In 2018/19 we have decided a total of 20 major applications compared to 25 decided during the same period in 2017/18. The average time of decision has increased from 214 to 250 days between these time periods, however all of these have been subject to planning performance agreements / extensions of time which are mutually agreed with applicants and encouraged in national guidance. The level of major applications submitted in the latter part of this year has reduced over previous years. The Government has three measures of performance which the Council must remain within thresholds for. If we breach these thresholds we will be designated as a poorly performing planning authority and developers will then have the option of applying directly to the Planning Inspectorate for Planning permission. This would mean that we don’t get the fee income for that application but we are still required to undertake the consultation. In addition we lose the democratic right to determine the application. The first of these measure is our performance on a two year rolling period for determination of major applications. We are at 100% for this measure (the threshold is 50%)
5.3In 2018/19 we have decided 393 ‘Minor’ applications compared to the 445 ‘Minor’ applications decided during the same period in 2017/18. There is an increase in average decision time from 68 days to 78 days. During 2018/19 we have decided 915 ‘Other’ applications compared to the 922 ‘Other’ applications decided during the same period in 2017/18. The cumulative average decision time has slightly increased from 58 days to 60 days. Officers are currently addressing the reasons for these rises in average decision time and implementing measures to address this. The second of the government thresholds relates to performance on minor and other applications over a two year period. We are at 97% on this measure (the threshold is 70%). The third of the government thresholds relates to overturns of refusals of applications on appeal and relates to minor and other applications. We are at 2.5% on this measure (the threshold is to remain below 5%).
5.4The length of time taken to validate an application has increased from an average of 10 to 12 days, however this is a product of the Systems thinking approach where there is a delay before validation rather than before decision.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Planning Services 2018/19 (April: December) updateMinutes | 294 KB | DownloadRead as text |
Follow Regulatory Committee at Haringey and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 14 Jan 2021 | Urgent businessRESOLVED 1. To a gree the appointment of Councillor Sheila Peacock to the Planning Sub-Committee , replacing Councill... | Agreed | Open |
| 5 Oct 2020 | Recent Government Announcements on PlanningRESOLVED that: A) The response to the changes to the current planning system consultation, which was submitted on 1 O... | Noted | Open |
| 2 Oct 2020 | Establishment of Planning and Licensing Sub Committees 2020/21RESOLVED that: 1. The terms of reference of the Regulatory Committee as set out within the Council’s Constitution, at... | Noted | Open |
| 31 Jul 2020 | Business and Planning Act 2020 - Pavement Licence conditions and fees as part of the Covid 19 recovery measuresRESOLVED to i. Agree the p avement licence conditions as outlined in Appendix A which will be the Council’s published... | Agreed | Open |
| 14 Jul 2020 | Amendment to Committee MembershipsRESOLVED that i. Councillor Sarah Williams be appointed as Chair of the Planning Sub Committee, and Licensing Sub Com... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.