RESOLVED That pursuant to Contract Standing Order 9.07.1(d), to approve the award of contract for the supply of CCTV goods and services to the successful bidder named in the exempt report for a period of 4 years under a schedule of rates framework (detailed in the Contract – and Appendix A of the exempt report) up to a maximum spend of £2.1m. Reasons for decision The Council initiated a competitive exercise through the Official Journal of the EU (OJEU) and an OJEU notice was issued on 02 August 2019, to invite tenders with submissions due on 04 September 2019. The procurement process followed the Open Procedure in accordance with Regulation 27 of the Public Contract Regulations 2015. A total of seven providers registered interest and one provider submitted a bid for the contract. The tender procedure consisted of a single stage process, including ‘selection questions’ and six qualitative questions, assessing the bidders against the broad range of required experience, skills and capabilities as described in the specification. The submitted bid has been evaluated against price and quality to ensure that it delivers value for money. The successful bidder has demonstrated its ability and capability through responses to the tender requirements and questions, and it is therefore proposed to be the successful provider. Alternative options considered Doing nothing – continue as is, repairing the existing frail infrastructure that dates back to 2006.This option was not progressed as ultimately it risks infrastructure failure and loss of CCTV capability. Risks associated with failure include loss of public and key stakeholders’ confidence, increased crime and disorder, failures in traffic ... view the full minutes text for item 88.
Word for word from the decision Haringey published for this meeting.Source: www.minutes.haringey.gov.uk
Title: Supply of Goods and Services for Cameras Refresh, Upgrade and Network Extension – Contract Award Report authorised by : Stephen McDonnell, Director of Environment and Neighboourhoods
Lead Officer: Sarah Tullett, Client & Contract Manager, 020 8489 7001, [email protected]
Ward(s) affected: All
Report for Key/ Non Key Decision: Key Decision
1. Describe the issue under consideration
1.1This report is seeking approval from Cabinet for the award of contract under Contract Standing Order (CSO) 9.07.1 (d) which states that all contracts valued at £500,000 (five hundred thousand pounds) or more at the time of award may only be awarded, assigned, or novated by the Cabinet . The award is of the contract for installation of CCTV in the borough, including:
The design, supply and installation at site; Testing and completion of the works; Remedying of defects in the works.
1.2This contract will support the Council in delivering on the refresh and upgrade of the Council’s CCTV infrastructure and significantly increase the current number of cameras across the borough (increasing from 75 to estimated 150) in order to improve public confidence, detect and deter criminality as well as improve the flow of traffic across the borough.
1.3This is a new contract to be awarded for a period of 4 years at a maximum cost of £2.1M. The contract will be funded from the allocated capital of £4.1M for the provision of CCTV across the borough. The overall capital allocation is to procure new servers, cameras, and control room as below:
Digital infrastructure upgrade – servers at River Park House £700K Cameras refresh, upgrade and extension (this contract) £2.1M Construction - Core and shelling of 48 Station Road £700K Fit out of the new Control Room at 48 Station Road £600K Total £4.1M
Page 1 of 6 This is a significant investment to increase how safe and confident people who live work and play in Haringey feel.
2. Cabinet Member Introduction
2.1The need to provide a new CCTV Control Room followed the decision to decant from the Ashley Road depot where the current Control Room is based. Capital provision of £2.1m was made available for this. We took the opportunity to review the scale and ambition of our CCTV operation, considering both the need and opportunities for CCTV in Haringey. Consequently the Council increased the capital allocation for this to £4.2m in February 2019.
2.2We are replacing and increasing the capacity of our servers. Through this contract award we will double the size of our camera network. This report is for the award of the contract for replacement, refresh and extension of our camera network.
2.3As well as increasing the number of cameras we will take advantage of latest technology, providing high quality evidential footage to support any necessary enforcement and quality real time coverage to manage incidents dynamically. We will also increase coverage to enable us to better manage the road traffic network.
2.4We will increase our pool of redeployable cameras to increase the tools available to tackle crime and Anti-social behaviour (ASB) hotspots. This will increase flexibility and capacity, and having solved an issue in one location we can then lift and shift our capability to other areas.
2.5This will be followed by the fit out of a modern new control room, operated jointly with Homes for Haringey and the Metropolitan Police. The new control room will bring together all the key agencies in the borough able to provide a joined up seamless response to crime and ASB as it occurs.
2.6At the end of the programme we will have an expanded, modern CCTV capability joined up with partners, that enables us to provide a flexible and seamless response to incidents and issues in the borough. This will help deliver our Borough Plan commitments to create a safer borough and improving public confidence and deterring and detecting criminality.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.