Cabinet, Tuesday 12 November 2019 at 6.30pm

The need for additional Housing Revenue Account spend on new build properties and Temporary Accommodation acquisitions

Approved Executive 1 paper

Cabinet approved this item on Tuesday 12 November 2019. Below is the council's own wording, with the papers it was decided on.

Item73

Resolved

RESOLVED To recommend to Full Council that it approves additions to the 2019/20 HRA capital programme of £70.4m to finance: the construction of new build properties (£4.1m); the acquisition of new build properties for affordable housing (£8.7m) and the acquisition of existing properties to house homeless households (£57.6m). Reasons for decision On 10 September 2019, Cabinet approved a re-profiled HRA capital budget of £77.8m, for 2019/20. This included £62.8m for existing stock, £2.9m for the Council housing delivery ... view the full minutes text for item 73.
Word for word from the decision Haringey published for this meeting. Source: www.minutes.haringey.gov.uk

Follow this further

Built from Haringey's papers

What the report saysPro

Report to Cabinet, 7 pages

Recommendations

3.1That Cabinet recommends Full Council approves additions to the 2019/20 HRA capital programme of £70.4m to finance: the construction of new build properties (£4.1m); the acquisition of new build properties for affordable housing (£8.7m) and the acquisition of existing properties to house homeless households (£57.6m).

Reasons for decision

4.1On 10 September 2019, Cabinet approved a reprofiled HRA capital budget of £77.8m, for 2019/20. This included £62.8m for existing stock, £2.9m for the Council housing delivery programme and £12m for new homes acquisition. There is also a £41.4m in the General Fund capital budget to acquire existing properties to be used to house homeless households.

4.2The construction of new build properties is now moving at a faster pace than anticipated in February 2019. The current budget provision of £2.9m for new build properties as outlined in the quarter 1 (period 3) budget monitoring report for 2019/20 to Cabinet dated 10 September 2019, has become insufficient to cover the cost of the accelerated works in this year.

4.3Hence the need for an increase of £4.1m within the 2019/20 HRA budget for the construction of new build properties by the Council. This is following a re- assessment of the budget required given the faster speed and greater progress on these projects by the Council than projected in February 2019.

4.4New opportunities have come forward to acquire properties under development by other organisations, that were not previously foreseen. Thus, the need for an increase of £8.7m within the 2019/20 HRA budget, for the acquisition of new homes.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
The need for additional Housing Revenue Account spend on new build properties and Temporary Accommodation acquisitionsMinutes 7 pages DownloadRead as text

At this meeting

Whole meeting
70MinutesOn the agenda
73The need for additional Housing Revenue Account spend on new build properties and Temporary Accommodation acquisitionsThis decision
74Amendments to the Community Benefit SocietyApproved 75Admission to Schools – Proposed Admission Arrangements for 2021/22Agreed 76Options for the future of Stamford Hill Primary SchoolNoted 77Childcare Sufficiency StrategyApproved 78Charging for Managed Accounts 2018/19 MTFS Proposal: Consultation findings and feedback report.Approved 79Community Infrastructure Levy (CIL) Partial Review: Draft Charging Schedule (DCS) consultationNoted 80Update of the Haringey Local Development Scheme (LDS) 2016 - 2019Approved 81London Borough of Haringey Air Quality Action Plan 2018-22 Public and enforcement of Anti-Idling RegulationsApproved 82Affordable Energy Strategy and agreement to proceed with public consultationAgreed 83Council Energy Contract AwardApproved 84Improvements to high-speed broadband infrastructure and connectivity in the boroughAgreed 85Agreement to award of Contract for Ferry Lane Public Realm SchemeApproved 86Novation of Contract for provision of SAP Managed ServiceApproved 87Regulation of Investigatory Powers Act (RIPA) 2000: Use within the Council 2018/19 and review of to the Council's investigatory powers policies under RIPA 2000 and Investigatory Powers Act 2016Noted 88Supply of Goods and Services for Cameras Refresh, Upgrade and Network Extension – Contract AwardApproved 89North Hill Retaining Wall WorksApproved 91Exclusion of the Press and PublicDecided 97Exempt Cabinet MinutesPrivate

More from Haringey Cabinet

All decisions
MeetingDecisionOutcome
10 Nov 2026 Corporate Delivery Plan 2026-2028DECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
10 Nov 2026 Draft 2027-28 Budget and 2027-2032 Medium Term Financial Strategy ReportDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
10 Nov 2026 Regulation 19 consultation on Proposed Submission version of Haringey Local Plan 2027-2042 and submission to Secretary of StateDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
10 Nov 2026 Admission to Schools - Proposed Admission Arrangements for 2028/29DECLARATIONS OF INTEREST FOR THIS ITEM: None Decided Open
10 Nov 2026 Approval to extend current Highways and Street Lighting Contracts and approval of the procurement strategy for a future combined Highways and Street Lighting ContractDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies