London Borough of Haringey
Urgent Decisions, Tuesday 7 April 2020 at 11.00am

Transfer of 'Hard' Facilities Management (FM) Services to Homes for Haringey (HfH)

Approved Committee 2 papers

Urgent Decisions approved this item on Tuesday 7 April 2020. Below is the council's own wording, with the papers it was decided on.

Item28

Resolved

RESOLVED 1. To approve the Interim Agreement for the provision of ‘hard’ FM services for a period of up to 12 months to 31 st March 2021, whilst the longer term detailed contractual agreement can be put in place. 2. To approve delegated and insofar as is necessary retrospective authority to the Director of Housing, Regeneration and Planning to commission ‘hard’ FM services from Homes for Haringey within the forecast 2020-21 budget envelope of £1,650,000 as agreed by Cabinet in the FM Commissioning Strategy 2019. Reasons for decision Following the Cabinet decision on 9 th July 2019, joint mobilisation planning for the FM insource was undertaken between the Council and HfH to prepare for the transfer of all FM functions coming back in-house. HfH has mobilised to take-on Hard FM Services and temporary management arrangements are required to manage transferring staff while the confirmation of an Interim FM Manager is finalised. The Interim Agreement provides the authority for HfH to deliver ‘hard’ FM services from 1 st April 2020 while the detailed FM specification and delivery plan are developed jointly between both organisations. There is currently a lack of detail relating to the condition of the Council’s estate to enable the Council to draft a service specification and delivery plan that would enable HfH to understand the cost implications. The Covid-19 crisis has impacted on the ability of the project team to develop the service specification and delivery plan and it is unknown how long this crisis will prevail. Therefore, adopting an interim agreement whilst the Council and HfH manages the Covid -19 crisis and understand the condition of the Council’s assets in more detail would enable sufficient time to develop the specification, delivery plan and cost model acceptable to both HfH and the Council. The above approach underpins the principles of an open and collaborative / trusted relationship between the Council and HfH with ... view the full minutes text for item 28.
Word for word from the decision Haringey published for this meeting. Source: www.minutes.haringey.gov.uk

Follow this further

Built from Haringey's papers

What the report saysPro

Report to Urgent Decisions

Dan Hawthorn Director of Housing, Regeneration and Planning

Homes for Haringey 48 Station Road Wood Green London N22 7 TY Date: 31st March 2020

To: Homes for Haringey (You, Your)

Dear Sirs

Repairs and maintenance of General Fund estate

I write to confirm the basis of Your appointment, pursuant to Regulation 12(1) of the Public Contracts Regulations 2015 (Award of contracts to controlled persons) ) to manage certain commercial and other premises and which are accounted for in the Council's general fund on and from 1 April 2020 (the Commencement Date) for a term of 12 months (the Term) and where such services are currently being provided to Us by Amey (the Amey Services)

These premises are more particularly listed at Schedule 1 to this letter (the Premises) and include

· Corporate buildings, including offices and civic buildings · Operational estates, including depots, mortuary, coroners court, · Schools and children’s centres and other educational/youth provision · Adult services buildings such as day centres and care homes · Commercial property, including industrial estates, shops and offices.

We have agreed that the it is the intention that the terms of the Agreement for the delivery of housing management and other services dated 16th July 2018 (the Management Agreement) shall apply in due course to the provision of the Amey Services, covering statutory testing, planned maintenance and reactive repairs but that the Services, Management Fee and the Specification for the repair and maintenance of the Premises shall be agreed between us before 31 March 2021 and that once agreed the Services, Management Fee and Specification (as such terms are defined in the Management Agreement) will be incorporated into the Management Agreement by way of a deed of variation (it being agreed that the terms of such variation will not require the consent of the Secretary of State pursuant to s27 of the Housing Act 1985).

We have agreed that the following terms will apply to the delivery by You of the Amey Services and between Us in the agreement of the Services, Management Fee and the Specification for the repair and maintenance of the Premises

1.1The negotiations shall be undertaken in good faith and in a timely manner and each party shall use their best endeavours to ensure the Management Agreement is varied before 31 March 2021 1.2 A full-service specification will be produced by the Councils Corporate Landlord Team and a Delivery Plan will be produced by You along with other baselining and review of the Amey Services

1.3That the Management Fee shall be revised to enable You to fully recover Your costs in delivering the Services and Specification as agreed between Us

1.4That the Parties are both committed to the principles of equality of opportunity, fairness and quality of life for all, both in terms of how we work with the community and in our role as an employer.

2 For the period prior to the variation of the Management Agreement it is agreed as follows:

2.1We agree that You will not be responsible for, nor liable for, any disrepair of any of the Premises prior to this appointment.

2.2Within twelve months of You accepting this appointment, You will prepare a schedule of condition for each of the Premises and within 28 days agree with the Council (acting reasonably) a provisional works programme (and capital funding for) for the making good of any disrepair identified in that schedule.

2.3You agree to provide the Amey Services to a good industry standard (and in a manner (broadly similar to the contracted service that was required to be provided by Amey prior to Your appointment)

2.4We agree to pay You Your direct costs (labour and material) in providing the Amey Services within the context of an overall budget of £1,650,000 during the financial year 2020/21 and subject to the agreement of the works programme described in paragraph 2.2 above

I would be grateful if you could sign and return a copy of this letter to me to confirm Your appointment on the terms set out in this letter.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
200331 HfH Facility Management Appointment Letter SignedMinutes 241 KB DownloadRead as text
PDF
Transfer of 'Hard' Facilities Management (FM) Services to Homes for Haringey (HfH)Minutes 585 KB Download

At this meeting

Whole meeting
28Transfer of 'Hard' Facilities Management (FM) Services to Homes for Haringey (HfH)This decision

Who was there

1 of 1 attended
JE
Councillor Joseph EjioforCommittee Member, present

More from Haringey Urgent Decisions

All decisions
MeetingDecisionOutcome
17 Oct 2023 Household Support Fund in HaringeyRESOLVED 1. To note the Household Support Fund allocation from the government of £4,813,343.44 for the period 1st Apr... Noted Open
12 Sep 2023 Request to approve to vary the and extend the contract with D Shelton Hotel Limited, for Interim night shelter accommodationRESOLVED to: i. approve to vary and extend the contract under the procedures enlisted in Contract Standing Order (CSO... Approved Open
17 Jul 2023 Variation of current electrical inspection report programmeRESOLVED 1. To approve a variation of the two existing contracts with Contractor N and Contractor A, for the provisio... Approved Open
15 Jun 2023 Microsoft Enterprise Agreement - Contract Variation and Extension - for the Provision of Microsoft License Subscriptions, to include E5RESOLVED to 1. Approve, under Contract Standing Order 10.02.1b), an extension to the Council’s Microsoft Agreement wi... Approved Open
22 May 2023 Household Support Fund in Haringey Phase 2: May 2023RESOLVED to 1. Approves the Household Support Fund Scheme Policy: May 2023 Phase 2, which sets out the Council’s arra... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies