VARIATION OF CURRENT ELECTRICAL INSPECTION REPORT PROGRAMME

Approved Committee 1 paper

Urgent Decisions approved this item on Monday 17 July 2023. Below is the council's own wording, with the papers it was decided on.

Item3

Resolved

RESOLVED 1. To approve a variation of the two existing contracts with Contractor N and Contractor A, for the provision of Electrical Inspection Services to the Council by increasing the maximum contract values by an additional £1,474,825.00 for Contractor N and £1,413,050.00 for Contractor A (£2,887,875.00 in total) taking the total maximum value for both contracts, to £8,663,625 over the maximum contracts period of 18 months (of which 10 months currently remain). Reasons for decision In order to deliver the Electrical Inspection programmes, which includes completing urgent and high-risk actions and upgrading of smoke and heat alarms within properties, Haringey Council requires the support of specialist electrical contractors. The existing arrangements for this work have been in place since October 2022 and were procured as a direct award under the South East Consortium’s (SEC) Electrical Renewal’s Framework. Working with our Strategic Procurement business partners and the SEC, we were able to identify that Contractors N and A, were able to take on and support our service requirements. The contractors are and have since been successfully delivering the programmes of inspections and associated works, critical to the safety of residents. This service is currently relied upon whilst we recruit to existing vacancies within our in-house electrical team, who will, in the longer term deliver the core elements of this work. However, due to current priorities around damp and mould, voids and focus on improving the repairs service as well as market pressures and a shortage of suitably competent persons this is taking longer than originally anticipated and we will need to implement a further contract prior to fully in-souring the service again. Even when the team is fully resourced, there will always be a need to rely upon additional contracting services to support the in-house team through peaks in workload and gaps in resources. The procurement of a longer-term support arrangement is the subject of a separate and new procurement project will be progressed, to take over this provision once this extension is exhausted. As we continue delivering electrical safety programmes, the variation of these contracts offers continuity and the necessary resources to deliver on this key commitment to the Regulator and essential life-safety programmes. The variation supports the ongoing delivery of the electrical safety inspection and works programmes to comply with the Electrical Safety Regulations and the Fire Safety Act. Alternative options considered. Do nothing . This would mean that the current contract would not be sufficient to complete the programme. It would also mean that we cannot meet our commitment to the Regulator to complete the EICR programme by the December 2023. Furthermore, it would leave the residents subject to living in buildings where there could be electrical safety issues that go ... view the full minutes text for item 3.
Word for word from the decision Haringey published for this meeting. Source: www.minutes.haringey.gov.uk

Follow this further

Built from Haringey's papers

What the report saysPro

Report to Urgent Decisions, 6 pages

Recommendations

The Cabinet Member for Housing Services, Private Renters, and Planning is asked:

3.1To approve a variation of the two existing contracts with Contractor N and Contractor A, for the provision of Electrical Inspection Services to the Council by increasing the maximum contract values by an additional £1,474,825.00 for Contractor N and £1,413,050.00 for Contractor A (£2,887,875.00 in total) taking the total maximum value for both contracts, to £8,663,625 over the maximum contracts period of 18 months (of which 10 months currently remain).

Reasons for decision

4.1In order to deliver the Electrical Inspection programmes, which includes completing urgent and high-risk actions and upgrading of smoke and heat alarms within properties, Haringey Council requires the support of specialist electrical contractors.

4.2The existing arrangements for this work have been in place since October 2022 and were procured as a direct award under the South East Consortium’s (SEC)

Page 1 of 6 Electrical Renewal’s Framework. Working with our Strategic Procurement business partners and the SEC, we were able to identify that Contractors N and A, were able to take on and support our service requirements.

4.3The contractors are and have since been successfully delivering the programmes of inspections and associated works, critical to the safety of residents. This service is currently relied upon whilst we recruit to existing vacancies within our in-house electrical team, who will, in the longer term deliver the core elements of this work. However, due to current priorities around damp and mould, voids and focus on improving the repairs service as well as market pressures and a shortage of suitably competent persons this is taking longer than originally anticipated and we will need to implement a further contract prior to fully in- souring the service again.

4.3Even when the team is fully resourced, there will always be a need to rely upon additional contracting services to support the in-house team through peaks in workload and gaps in resources. The procurement of a longer-term support arrangement is the subject of a separate and new procurement project will be progressed, to take over this provision once this extension is exhausted.

4.3As we continue delivering electrical safety programmes, the variation of these contracts offers continuity and the necessary resources to deliver on this key commitment to the Regulator and essential life-safety programmes.

4.4The variation supports the ongoing delivery of the electrical safety inspection and works programmes to comply with the Electrical Safety Regulations and the Fire Safety Act.

5. Alternative options considered.

5.1Do nothing. This would mean that the current contract would not be sufficient to complete the programme. It would also mean that we cannot meet our commitment to the Regulator to complete the EICR programme by the December 2023. Furthermore, it would leave the residents subject to living in buildings where there could be electrical safety issues that go unrecorded and unremedied if we do not undertake electrical inspections and improvement works. In addition, the Council would not be compliant with the Electrical Regulations.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
VARIATION OF CURRENT ELECTRICAL INSPECTION REPORT PROGRAMMEMinutes 6 pages DownloadRead as text

At this meeting

Whole meeting
3VARIATION OF CURRENT ELECTRICAL INSPECTION REPORT PROGRAMMEThis decision

On this subject at Haringey

Search all
  1. VARIATION OF CURRENT ELECTRICAL INSPECTION REPORT PROGRAMMEThis decision
  2. Variation of current surveying contractDecided

More from Haringey Urgent Decisions

All decisions
MeetingDecisionOutcome
17 Oct 2023 Household Support Fund in HaringeyRESOLVED 1. To note the Household Support Fund allocation from the government of £4,813,343.44 for the period 1st Apr... Noted Open
12 Sep 2023 Request to approve to vary the and extend the contract with D Shelton Hotel Limited, for Interim night shelter accommodationRESOLVED to: i. approve to vary and extend the contract under the procedures enlisted in Contract Standing Order (CSO... Approved Open
15 Jun 2023 Microsoft Enterprise Agreement - Contract Variation and Extension - for the Provision of Microsoft License Subscriptions, to include E5RESOLVED to 1. Approve, under Contract Standing Order 10.02.1b), an extension to the Council’s Microsoft Agreement wi... Approved Open
22 May 2023 Household Support Fund in Haringey Phase 2: May 2023RESOLVED to 1. Approves the Household Support Fund Scheme Policy: May 2023 Phase 2, which sets out the Council’s arra... Approved Open
12 May 2023 Park View Secondary School - Contract award for the urgent provision of 11 temporary classroom unitsRESOLVED to: 1. Approve, pursuant to Contract Standing Order (CSO) 9.07.1d) and CSO 16.02, the award to Contractor A ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies