Tangmere and Northolt Compulsory Purchase Order

Agreed Executive 4 papers

Cabinet agreed this item on Tuesday 13 October 2020. Below is the council's own wording, with the papers it was decided on.

Item317

Resolved

RESOLVED 1. To authorise the making of the Order to acquire all land and rights within the land edged red on (Appendix 2(b)) for housing purposes pursuant to the powers contained in section 17 of the Housing Act 1985, to enable the Council demolition of the Tangmere and Northolt blocks and the erection of new housing accommodation on the site so as to achieve a future qualitative gain following confirmation of the Order. 2. To delegate authority to the Director of Housing, Regeneration and Planning in consultation with the Assistant Director of Corporate Governance as follows: (a) To make all necessary changes, as appropriate to the draft Statement of Reasons (and any adjustment to the Order Schedule and Order Map) and take all necessary steps to make, serve and implement the Order, to pursue its confirmation by the Inspector, Secretary of State (or the Council) and to implement the Order as may be necessary (these steps are set out in section 6.59-6.74 of this report); (b) To make General Vesting Declarations (GVDs) under the Compulsory Purchase (Vesting Declarations) Act 1981 and/or to serve notices to treat and notices of entry (if required) following confirmation of the Order. (c) To issue and serve any warrants to obtain possession of property acquired by the Council following the execution of a GVD or service of a notice of entry relating to the Order if it is considered appropriate and necessary to do so. (d) To acquire third party interests in the land within the Order either by agreement or compulsorily; and (e) To finalise and confirm the Order documents prior to making the Order. Reasons for decision Proceeding with a CPO and making the Order is necessary due to the extensive timescale and resources expended in acquiring all of the ... view the full minutes text for item 317.
Word for word from the decision Haringey published for this meeting. Source: www.minutes.haringey.gov.uk

Follow this further

Built from Haringey's papers

What the report saysPro

Report to Cabinet, 22 pages

Report for: Cabinet – 13th October 2020

Title: Tangmere and Northolt CPO

Report authorised by: David Joyce

Lead Officer: David Sherrington, Director of Broadwater Farm and Christine Addison, Assistant Director for Capital Projects & Property

Ward(s) affected: West Green Ward

Report for Key/ Non-Key Decision: Key decision

1. Describe the issue under consideration

1.1On 13th November 2018, following detailed consultation with residents, Cabinet agreed the demolition of Tangmere and Northolt blocks and to build new Council homes on the Broadwater Farm estate. Cabinet also agreed a Rehousing and Payments Policy specific to Broadwater farm residents to support the rehousing process. Previously, in June 2018, the Tangmere Rehousing Priority Scheme was adopted as a matter of urgency due to the need to remove piped gas from the building as soon as possible to reduce potential danger.

1.2The Council began negotiating the buyback of properties with leaseholders in Tangmere in June 2018 and with Northolt leaseholders in February 2019. As of 29th September 2020, 18 of the leasehold properties have been acquired and 5 secure tenants remain.

1.3However, despite ongoing negotiations, there are 13 leaseholders in Northolt and 6 leaseholders in Tangmere whose interests have not yet been acquired (19 in total). As of 29th September 2020, 10 of the leaseholders remaining have reached agreement to sell to the Council by private treaty, with these sales to be finalised. Therefore, negotiations with 9 leaseholders have yet to reach agreement.

1.4On 14th July 2020, Cabinet approved an updated Acquisition Strategy for the remaining leaseholders in Tangmere and Northolt. This strategy was agreed to enhance the prospects of acquiring the remaining interests by agreement as far as possible. The decision to proceed to make a Compulsory Purchase Order ‘CPO’ is being made in parallel to ongoing negotiations to acquire all remaining interests where acquisition by agreement cannot be reached.

1.5This Report therefore seeks authority for the Council to use its compulsory purchase powers to make ‘The London Borough of Haringey (Tangmere and Northolt) Compulsory Purchase Order 2020’ (“the Order”) in respect to Tangmere and Northolt site (shown edged red on the attached plan) and to acquire all outstanding property interests and any additional rights that may be required. This

Page 1 of 22 will ensure vacant possession should the Council fail to reach a negotiated settlement for the purchase of the outstanding third-party land and property interests.

1.6The possibility of using compulsory purchase powers was identified in the Cabinet report of the 13th November 2018 which noted that ‘should the Council and any leaseholders not reach an agreement in a reasonable period, it may be necessary, as a last resort, for the Council to consider using its compulsory purchase powers.’

1.7This report also sets out a number of decisions required by the Council in order to progress with the preparation and making of the Order.

2 Cabinet Member Introduction

Cllr Ibrahim, lead member for Housing:

2.1In 2018, it became apparent that the Tangmere and Northolt blocks on the Broadwater Farm estate were unsafe and would need to be extensively refurbished or demolished and replaced. Following a positive consultation with residents in both blocks, the decision was taken in November 2018 that demolition was the most suitable option – enabling for the delivery of new, safe and high-quality Council homes on the estate.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
CPO EQIA v3Appendix Three 18 pages Download
PDF
Northolt & Tangmere SOR Draft FINALAppendix one 30 pages Download
PDF
(b): Haringey Broadwater Scheme: CPO Map v2.1Appendix two 1 pages Download
PDF
Tangmere and Northolt Compulsory Purchase OrderMinutes 22 pages DownloadRead as text

More from Haringey Cabinet

All decisions
MeetingDecisionOutcome
10 Nov 2026 Corporate Delivery Plan 2026-2028DECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
10 Nov 2026 Draft 2027-28 Budget and 2027-2032 Medium Term Financial Strategy ReportDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
10 Nov 2026 Regulation 19 consultation on Proposed Submission version of Haringey Local Plan 2027-2042 and submission to Secretary of StateDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
10 Nov 2026 Admission to Schools - Proposed Admission Arrangements for 2028/29DECLARATIONS OF INTEREST FOR THIS ITEM: None Decided Open
10 Nov 2026 Approval to extend current Highways and Street Lighting Contracts and approval of the procurement strategy for a future combined Highways and Street Lighting ContractDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies