RESOLVED 1. To approve, under Contract Standing Order (CSO) 10.02.1b), a variation to the contract with Support Revolution Ltd for SAP Hosting and Support in order to confirm an option for the Council to request consultancy services to support work on the Council’s ERP Improvement Programme between 01/10/2020 to (est.) 22 /12/2021 , at a value of a total of up to £272,000 (calculated based on pre-agreed rates) and to be ordered by issue from time to time of one or more purchase orders. 2. To approve, under Contract Standing Order (CSO) 10.02.1b) and pursuant to the variation referred to in the paragraph above, an initial order for a tranche of consultancy services valued at £130,000. Reasons for decision The Council is undergoing an ERP Improvement programme. ERP is a software platform at the core of Haringey’s Finance, HR and other complex processes. It allows those processes in separate functions of the organisations to share data – co-ordinating the organisation. It is provided by a company called SAP and supported by an SAP partner organisation called Support Revolution. The programme will deliver: · A platform for insourced permanent recruitment by April 2020; · Process, policies, and technology solution for strategic procurement activity; · Significant improvements to our HR, Finance and other functions of ERP so that users can work faster and easier; · Fundamental changes to Finance, HR and other reporting making it more easily accessed and more effective. The programme requires access to planned resources which are within the scope of both the contract with ... view the full minutes text for item 325.
Word for word from the decision Haringey published for this meeting.Source: www.minutes.haringey.gov.uk
1. Describe the issue under consideration This report seeks approval from Cabinet for the implementation of Contract Standing Order 10.02.1 b), which provides that variations to contracts valued at £500,000 (five hundred thousand pounds) or more may only be varied by the Cabinet.
2. Cabinet Member Introduction I concur with the recommendations of this report. This recommendation is based on cost efficiency and service delivery.
3. Recommendations 3.1. For Cabinet to approve, under Contract Standing Order (CSO) 10.02.1b), a variation to the contract with Support Revolution Ltd for SAP Hosting and Support in order to confirm an option for the Council to request consultancy services to support work on the Council’s ERP Improvement Programme between 01/10/2020 to (est.) 22/12/2021, at a value of a total of up to £272,000 (calculated based on pre-agreed rates) and to be ordered by issue from time to time of one or more purchase orders.
3.2For Cabinet to approve, under Contract Standing Order (CSO) 10.02.1b) and pursuant to the variation referred to in paragraph 3.1 above, an initial order for a tranche of consultancy services valued at £130,000.
4. Reasons for decision 4.1. The Council is undergoing an ERP Improvement programme. ERP is a software platform at the core of Haringey’s Finance, HR and other complex processes. It allows those processes in separate functions of the organisations to share data – co- ordinating the organisation. It is provided by a company called SAP and supported by an SAP partner organisation called Support Revolution.
4.2The programme will deliver: A platform for insourced permanent recruitment by April 2020
Page 1 of 6 Process, policies, and technology solution for strategic procurement activity Significant improvements to our HR, Finance and other functions of ERP so that users can work faster and easier Fundamental changes to Finance, HR and other reporting making it more easily accessed and more effective
4.3The programme requires access to planned resources which are within the scope of both the contract with our ERP support partner, Support Revolution, and the project scope and budget, to deliver.
4.4The programme will allow decision making at an appropriate level for minor increases to and requests under the contract.
5. Alternative options considered a. Do nothing – we will be unable to deliver the ERP Improvement Programme. b. Insourcing talent – It will not be possible to recruit an in-house expert SAP team and have them operational in time to deliver the project. c. Open market tender – rejected as would have to onboard a new SAP support partner which would involve purchasing support days from existing partner in any case and unlikely to lead to reduced price/unit.
6. Background information 6.1. Variations are provided for under the terms of the contract with the SAP support partner to allow for these instances where support for unexpected projects is required.
6.2The Cabinet decision taken on 8th October 2019 to award the SAP support contract to Support Revolution at a saving of £330k, securing a low-cost base of professional support for a key organisational platform. This award had two key goals:
Resourcing security i.e. advance notice of and availability of resources with a key partner. Stable cost base i.e. secure, costed expertise for assured delivery of the ERP Improvement Programme. 6.3. Furthermore, stability and security/availability of SAP platform is core to future savings activities that rely on large scale automation and data availability across the organisation.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.