RESOLVED To approve the updated Asset Management Plan 2020-2025 (“AMP”) as included at Appendix 1 including the updated Acquisitions and Disposals Policy and the updated Commercial Property Portfolio Strategy. Reasons for decision The Council’s Asset Management Plan (AMP) sits alongside the Capital Strategy and is a key document in supporting the Council’s decision making about investment in its land and property assets to deliver Council priorities and services. CIPFA (Chartered Institute of Public Finance and Accountability) guidance advises Councils to agree an Asset Management Plan as part of their budget strategy from 2020/21. CIPFA’s guidance on asset management includes ensuring that Councils regularly review their need for property either operationally or strategically. The Council’s Asset Management Plan 2020-25 was agreed in February 2020. At the time Cabinet was advised that it would be updated after one year as their would-be significant progress and change over the course of the year to require an update. It is important that the plan is updated regularly to ensure it is useful in supporting capital investment decisions which will deliver the Council’s Borough Plan and MTFS priorities. Alternative Options The Council’s Asset Management Plan lasts for five years and can be refreshed periodically. If this does not happen, the plan will not reflect the most recent changes and the plan will not be as helpful in development the Council’s budget strategy.
Word for word from the decision Haringey published for this meeting.Source: www.minutes.haringey.gov.uk
Report authorised by : David Joyce, Director of Housing, Regeneration & Planning
Lead Officer: Christine Addison, Assistant Director for Capital Projects & Property (interim)
Ward(s) affected: All
Report for Key/ Key Non-Key Decision:
1. Describe the issue under consideration
1.1This report presents the Council’s 2021 update of the Asset Management Plan for the period 2020-25 and recommends its adoption.
1.2The Asset Management Plan was agreed in February 2020 and it was agreed at the time that there would be an update after one year in February 2021. The Asset Management Plan sets out an overarching strategy for the use of Council property and land to support the delivery of the Council’s Borough Plan and Council services. It provides a baseline on property and land matters and supports capital investment decisions identified in the capital strategy / Medium Term Financial Strategy (MTFS). It sits alongside the Council’s Capital Strategy and Capital Programme for 2021/22 – 2025/26. This update sets out some of the achievements over the course of the last year and updates the plan proposals in a number of areas for 2021/22 onwards.
1.3Achievements over the year include:
a number of important property acquisitions which will help deliver Borough Plan targets on housing, enhance support for homeless people and support economic growth;
the Council’s use of property during the Covid 19 pandemic,
great steps forward in compliance in schools and an expanded schools capital programme to deal with a backlog of condition issues.
1.4New action which will be taken forward this coming year includes the major refurbishment of the Civic Centre to create a new Civic and Council Headquarter for Haringey over the course of this plan and a start on site of new Canning Crescent mental health facilities.
1.5The update shows the success of the shift in emphasis in managing assets to ensure they are used to support the Council’s Borough Plan objectives including considering use of land for the council housing growth programme and ensuring
Page 1 of 7 council assets are used to support economic growth, regeneration and community well-being.
2. Cabinet Member Introduction
2.1Last year Cabinet agreed to the Council’s first Asset Management Plan since 2008. The Asset Management Plan is an important tool in achieving the Council’s Borough Plan ambitions. It is part of the capital strategy and is the context for capital investment decisions, setting out major initiatives and priorities for capital investment, as well as investment required for compliance and carbon management planning. The plan includes our Acquisitions and Disposals Policy which is guiding our decision making in this area and this is updated this year.
2.2This updated plan sets out our many achievements on property over the year including:-
The decision to invest in the Civic Centre, protecting its heritage and creating something all residents in the borough will be proud of.
The most ambitious acquisitions programmes in its recent history with some major acquisitions to support the housing programme - including at the Chocolate Factory, 1a Ashley Gardens (to be Rosa Luxembourg House) and the IBSA flats which are now housing homeless families.
We’ve increased spending on the schools estate to help meet health and safety standards and deal with a backlog of poor condition.
During the Covid-19 pandemic we have acted very quickly to use our property differently to support the management of the pandemic.
We have completed the refurbishment of Hornsey Library, with other library improvements taking place or planned over the coming year. We’re making a start this coming year on providing better facilities for adults at Burgoyne Road, Canning Crescent and Osbourne Road. We will also complete the new depot at Marsh Lane this year which frees up the existing site for Housing where we will be on site building new Council homes by March 2022.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.