Award of Housing Asset Management Partnering Contracts

Approved Executive 2 papers

AI summaryHaringey Cabinet Member for Housing and Planning approves award of four long-term housing major works partnering contracts across four geographical lots, each for five years with a possible five-year extension.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedOne contractor per geographical lot, five years plus option for five more
MoneyNot stated in public papersFunded from HRA capital budget; values in Part B Exempt
What happens nextLeaseholder consultation requiredContract awards conditional on Section 20 consultation outcome
Who it affectsCouncil tenants and leaseholders in HaringeyAll homes owned and managed by the council, borough-wide

What was decided

The Cabinet Member for Housing and Planning (Deputy Leader) approved the award of four partnering contracts, one per geographical Lot, to four separate successful bidders named in the Part B Exempt report, for five years with an option to extend a further five years, conditional on leaseholder consultation. Report 3.2, P3

The Cabinet Member also confirmed delegated authority, given by Cabinet in June 2025, for the Director of Housing, in consultation with the Corporate Director of Finance and Resources, to issue works orders under the contracts in line with the annual Cabinet-approved Housing Revenue Account Housing Capital Programme. Report 3.3

Why

The contracts deliver the strategy approved by Cabinet in July 2022 for housing major works, taking a holistic approach to refurbishing tenanted and leasehold properties and blocks, and maximising social value from the council's investment. Report 4.1, P6

Key objectives are meeting the Decent Homes Standard, raising all council homes to at least EPC B by 2035, maintaining statutory safety standards, and providing employment, training and SME supply chain opportunities. Report 4.1, P6, 6.1, P45

The scope includes decent homes works, building and fire safety, block refurbishment, mechanical and electrical works, decarbonisation, neighbourhood and estate improvements, and internal and external cyclical works. Report 4.3, P8

What happens next

Contracts will be awarded to Bidder 3 (Lot 1 West), Bidder 9 (Lot 2 Central), Bidder 2 (Lot 3 East North) and Bidder 14 (Lot 4 East South), subject to leaseholder consultation. Report 4.16, P25, 4.17, P28, 4.18, P31, 4.19, P34

Works orders will be issued by the Director of Housing within the HRA capital programme approved annually by Cabinet. Report 3.3, P50

A separate dispensation related to the use of the LCP framework will be requested in addition to the completed Section 20 consultation. Report 4.9, P14

Options considered

  • Chosen: Award four partnering contracts to the recommended bidders. Supports the 2022 Partnering Contracts Strategy; best way to address decency issues holistically and maximise social value Report 4.1, P6, 3.2, P3
  • Rejected: Alternative options. The report records 'Alternative options considered: None'

Implications

  • Financial: Works will be paid for from the HRA capital programme, with risk of cost escalation that could reduce the benefit-cost ratio; close monitoring and enhanced reporting required. Report P50
  • Legal: Procurement followed the London Construction Programme Housing Framework Lot 2.3 under CSO 7.02 and PCR 2015 Regulation 33(8)(b)(ii); award is within the powers set by CSO 2.01(c) for contracts of £500,000 or more, taken by Cabinet Member under CSO 0.08 with Leader agreement. Report P47, P48, P54, P55
  • Equalities: The Public Sector Equality Duty under the Equality Act 2010 has been considered; works affect all residents and aim to address fuel poverty for over 15,000 households in the borough. Report P59, 5.2, P41
  • Climate: Contracts support the climate emergency action plan by delivering decarbonisation works and a minimum EPC B rating for all council homes by 2035, aligned with the borough's net zero target by 2041. Report 6.1, P45, 5.1, P39
  • Other: Social value carries 16% of the total marks (4.8% quantitative, 5.6% qualitative, 5.6% delivery plan), supporting employment, training and SME supply chain benefits. Report 4.11, P18

Who and where

  • Council tenants and leaseholders across all four geographical areas of the borough Report 4.3, P8, 4.1, P6
  • SME suppliers and local construction workforce in Haringey Report 4.1, P6
  • Residents experiencing fuel poverty in the borough (over 15,000 households) Report 5.2, P41

Timeline

  • July 2022: Cabinet approved the Partnering Contracts Strategy for Housing Major Works Report 4.1, P6
  • June 2025: Cabinet approved initial award of the four contracts and delegated authority to the Director of Housing to issue works orders Report 3.3, 4.5, P10
  • By 2028: All council homes to meet the Decent Homes Standard Report 5.1, P39, 5.3, P43
  • By 2035: All council homes to reach a minimum of EPC B Report 4.1, P6, 6.1, P45
  • By 2041: Borough net zero target to be met Report 5.1, P39
  • 2026-02-09: Cabinet Member for Housing and Planning approves award of the four contracts

Plain English for the jargon

  • Lot: A geographical area of the borough used to split the housing stock into four separate contract areas: West, Central, East North and East South
  • Decent Homes Standard: A government standard setting minimum conditions for social housing, which all council homes must meet by 2028
  • EPC B: Energy Performance Certificate rating of B or better, a measure of a home's energy efficiency
  • HRA: Housing Revenue Account, the ring-fenced account that funds council housing, including its capital works programme
  • LCP Housing Framework: London Construction Programme Housing Framework, a pre-approved procurement framework used to run a mini competition for these contracts
  • Section 20 consultation: A formal consultation process with leaseholders under the Landlords and Tenants Act 1985 before qualifying works are carried out
  • CSO: Contract Standing Order, the council's rules on how contracts must be procured and awarded
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7

Resolved

DECLARATIONS OF INTEREST MADE FOR THIS ITEM: None RESOLVED The Cabinet Member for Housing and Planning (Deputy Leader): Approved the award of the four partnering contracts across four geographical Lots, to four separate successful bidders stated in the Part B Exempt report for a period five years with an option to extend a further five years, in accordance with CSO2.01 (C), conditional on leaseholder consultation. Pursuant to Cabinet approval in June 2025 delegated authority for the Director of Housing, in consultation with the Corporate Director of Finance and Resources, to issue works orders under the contract in line with the annual Cabinet approved, Housing Revenue Account Housing Capital Programme. Reasons for decision The award of the four contracts supports the strategy approved by Cabinet in July 2022 ‘Partnering Contracts Strategy for Housing Major Works’ and established four long-term partnering contracts which were identified as the best way to address decency issues which adopted a holistic approach to refurbishing properties and blocks (both tenanted properties and leasehold) and maximizes the social value benefits of the Council’s investment. Key objectives of these contracts will include:  Ensuring that all stock met the Decent Homes Standard, and this would be maintained going forward.  Ensuring that all Council owned homes had a minimum of an EPC B by 2035.  Ensuring that statutory safety standards were maintained in all blocks.  Providing employment and training opportunities; supporting and enabling SME supply chain in the borough to benefit from the investment and involving our residents at all stages in the procurement and delivery process. The Partnering Contracts would deliver Housing capital investments works to properties owned and managed by the Council and included but not restricted to:  Decent Homes Related Works  Building Safety & Fire Safety Related Works  Block Refurbishment Works  Mechanical & Electrical Works  Decarbonisation Related Works  Neighbourhood & Estate Improvement Works  Internal and External Cyclical Works Alternative options considered None.
Word for word from the decision Haringey published for this meeting. Source: www.minutes.haringey.gov.uk

Follow this further

Built from Haringey's papers

What the report saysPro

Report to Cabinet Member Signing

Recommendations

3.1It is recommended that the Cabinet Member for Housing and Planning (Deputy Leader):

3.2Approve the award of the four partnering contracts across four geographical Lots, to four separate successful bidders stated in the Part B Exempt report for a period five

Page 1 of 8 years with an option to extend a further five years, in accordance with CSO2.01 (C), conditional on leaseholder consultation.

3.3Pursuant to Cabinet approval in June 2025 to delegated authority for the Director of Housing, in consultation with the Corporate Director of Finance and Resources, to issue works orders under the contract in line with the annual Cabinet approved, Housing Revenue Account Housing Capital Programme.

Reasons for decision

4.1The award of the four contracts supports the strategy approved by Cabinet in July 2022 ‘Partnering Contracts Strategy for Housing Major Works’ and establishes four long-term partnering contracts which were identified as the best way to address decency issues which adopts a holistic approach to refurbishing properties and blocks (both tenanted properties and leasehold) and maximizes the social value benefits of the Council’s investment. Key objectives of these contracts will include:

 Ensuring that all stock meets the Decent Homes Standard, and this is maintained going forward.  Ensuring that all Council owned homes have a minimum of an EPC B by 2035.  Ensuring that statutory safety standards are maintained in all blocks.  Providing employment and training opportunities; supporting and enabling SME supply chain in the borough to benefit from the investment and involving our residents at all stages in the procurement and delivery process.

4.3The Partnering Contracts will deliver Housing capital investments works to properties owned and managed by the Council and includes but not restricted to:

 Decent Homes Related Works  Building Safety & Fire Safety Related Works  Block Refurbishment Works  Mechanical & Electrical Works  Decarbonisation Related Works  Neighbourhood & Estate Improvement Works  Internal and External Cyclical Works

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Summary of Leaseholder Observations 08 12 25Appendix A 64 KB Download
PDF
Award of Housing Asset Management Partnering ContractsMinutes 553 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

1 of 1 attended
SW
Councillor Sarah WilliamsCommittee Member, present

On this subject at Haringey

Search all
  1. Award of Housing Asset Management Partnering ContractsThis decision
  2. Veolia Waste Contract award for 2027 for Housing EstatesApproved
  3. Award print/post services contract to support Revenues and Benefits, Housing, Planning and PensionsDecided
  4. Award of Contracts for the provision of Housing Related Support -Young People Supported Housing PathwayApproved
  5. Award of Housing Asset Management Partnering ContractsApproved
  6. Award of contract for Employers Agent services for Phase 1 (Selby Centre + Sports Facilities) and Phase 2 (Housing of the Selby Urban Village ProjectApproved

More from Haringey Cabinet Member Signing

All decisions
MeetingDecisionOutcome
2 Nov 2026 Deaf Outreach Services ContractDECLARATIONS FOR THIS ITEM: NONE Decided Open
28 Oct 2026 Administrative amendment to Merchant Acquirer Re-ProcurementRESOLVED 1. To note the administrative error in the original report referring to Global Pay and Global Payments; 2. T... Noted Open
20 Oct 2026 Approval of Additional Expenditure and Final Payment to Accora Limited reportDECLARATIONS FOR THIS ITEM: NONE RESOLVED The Cabinet Member for Adults and Health: 1. Approved the variation of cont... Approved Open
16 Oct 2026 Approve Funding from Arts Council England to Haringey Music Service for the North London Music HubDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
13 Oct 2026 Filming at meetingsThe notice of filming at meetings was noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies