Additional contract costs for the Homes for Haringey external capital investment programme for year 2 (2019/20)

Approved Executive 1 paper

Cabinet approved this item on Tuesday 16 March 2021. Below is the council's own wording, with the papers it was decided on.

Item497

Resolved

RESOLVED 1. T hat pursuant to Contract Standing Order CSO 9.07.1(d) Cabinet approves additional costs and variations to Programme A, B and C within the Major Works year 2 project. This is set out in paragraph 6.17 of the report. 2. To approve the additional professional fees of £373,965 that represents 7.55% of the contract sum. This is in line with agreed terms in the contract. These fees are highlighted in the table referenced in paragraph 6.17. 3. To note that the original total contract sums for the project approved to date is £17,853,402. 4. To note that the total revised contract sums for the project will be £23,180,545. Reasons for decision The year 2 major works project is part of Homes for Haringey’s investment into the homes of the residents of Haringey Council to improve the living conditions across the borough and increase decency in the housing stock. Cabinet agreed in February 2018 to appoint Ridge and Partners LLP as Homes for Haringey’s multidisciplinary construction related consultant. Future projects under consideration will be project managed, designed and cost managed by Homes for Haringey and Ridge. The year 2 major works were approved by Cabinet in October 2019 and mobilised in January 2020. Due to Covid-19, Homes for Haringey closed all non-essential works between March and July 2020. Following the remobilisation, Ridge identified additional works across the programme. Homes for Haringey requested a full survey take place across the year 2 projects and the creation of a full cost report. A review of the works included within the programme, showed a failure to identify all elements of the work upfront in order to achieve a holistic delivery and to complete all the works required to each property. Ridge submitted the additional cost report in November 2020, identifying that a further £5m would be required to holistically deliver the year 2 project. In addition to the above, Homes for Haringey carried out the annual fire risk assessments within communal areas. As a result of these, further works were identified to reduce the risk of ... view the full minutes text for item 497.
Word for word from the decision Haringey published for this meeting. Source: www.minutes.haringey.gov.uk

Follow this further

Built from Haringey's papers

What the report saysPro

Report to Cabinet

Report for: Cabinet 16 March 2021

Title: Additional contract costs for the Homes for Haringey major works year 2 project.

Report authorised by: David Joyce, Director of Housing, Regeneration and Planning

Lead Officer: Lee Whitby, Head of Capital Works, Homes for Haringey

Ward(s) affected: Alexandra, Bounds Green, Fortis Green, Noel Park, Woodside, Highgate, Hornsey, Stroud Green, Crouch End, Muswell Hill, West green, Harringay, Seven Sisters, St Anns, Tottenham Green, White Hart Lane, Woodside, Bruce Grove, Northumberland Park, Tottenham Hale

Report for Key/ Non Key Decision: Key decision

1 Describe the issue under consideration.

1.1This report requests authorisation to proceed with additional works and variations under an existing building contract approved by Cabinet in October 2019.

1.2Following remobilisation due to the Covid-19 shutdown, new surveys were commissioned to ensure that the works being delivered aligned with the current asset and energy strategies. This led to additional works being identified that will ensure 1393 homes meet the Decent Homes Standard.

1.3In conjunction with this, to reduce the impact on residents and to deliver works in this most efficient and cost effect way, it was decided to amend the contract to include all relevant works identified in fire risk assessments.

1.4This includes the full value of a claim which has been made by the two contractors for delays and additional expenditure resulting from Covid-19. This claim is being assessed and the full amount is unlikely to be agreed.

1.5The additional works highlighted requires Cabinet authorisation. This is for an additional contract spend of £5,327,143 including fees to enable the improvement works to be carried out.

2 Cabinet Member introduction

2.1The year 2 external project was authorised in October 2019. This incorporated an award of contract being issued to two contractors to deliver works valued at £17,853,402.

2.2Further detailed surveys were commissioned after the initial contract award to meet additional requirements such as energy, safety and asset management criteria. The total highlighted for these works is £5,327,143.

Page 1 of 14 2.3 The approval of these additional works and variations will allow Homes for Haringey to progress with the major works year 2 project. This will enable external works such as the renewal of roofs, windows, doors, external brickwork repairs and improvements to communal areas and redecorations to proceed. This will improve the decency standard within our residents’ homes.

2.4The overall project will contribute to achieving the Borough Plan objectives for housing, which incorporates an objective to improve the quality of Haringey’s Council housing. The additional works are required to meet priorities such as bringing all the Council’s housing stock up to the Decent Homes Standard by March 2025 and targets related to energy efficiency and carbon reduction.

2.5This project pre-dates the Lowenberg Review, an independent report, which was commissioned by Homes for Haringey in December 2019 to improve the delivery of planned works. The upfront scoping of projects in advance of contract award is an area which was identified for improvement to reduce significant contract variations after award. The action plan resulting from this report is being monitored by Homes for Haringey’s Board. Following historic delivery issues, reviews have taken place to identify why delivery failures have occurred. Studies such as external reviews and internal lessons learned exercises have been conducted leading to several recommendations which are currently being implemented.

2.6The in depth reviews have included scrutinising the programmes failings and analysing in detail, the current Gateway process to identify the exact point of when a failure occurs with projects within the capital programme.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Additional contract costs for the Homes for Haringey external capital investment programme for year 2 (2019/20)Minutes 567 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 23 attended
JJ
John JonesCouncil Staff, expected
JE
Councillor Joseph EjioforChair, present
KA
Councillor Kaushika AminDeputy Chair, present
CA
Councillor Charles AdjeCommittee Member, present
MB
Councillor Mark BlakeCommittee Member, present
GB
Councillor Gideon BullCommittee Member, present
SC
Councillor Seema ChandwaniCommittee Member, present
KH
Councillor Kirsten HearnCommittee Member, present
EI
Councillor Emine IbrahimCommittee Member, present
SJ
Councillor Sarah JamesCommittee Member, present
MW
Councillor Matt WhiteCommittee Member, present
AS
Ayshe SimsekSecretary, expected

All 23 on the meeting page

On this subject at Haringey

Search all
  1. Additional contract costs for the Homes for Haringey external capital investment programme for year 2 (2019/20)This decision
  2. Request to accept additional funding for stop smoking service from department of health and social care (dhsc) and vary the existing contract for integrated lifestyle change programme to enhance the level of haringey smoking cessation services for 2025/26.Approved
  3. Approval for the additional funding for cycle confident until the end of the contract in february 2024Approved
  4. Provision of gas and additional services contractApproved
  5. Consultants for Construction Works Framework Agreement (Additional Services) - Award of ContractApproved

More from Haringey Cabinet

All decisions
MeetingDecisionOutcome
10 Nov 2026 Corporate Delivery Plan 2026-2028DECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
10 Nov 2026 Draft 2027-28 Budget and 2027-2032 Medium Term Financial Strategy ReportDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
10 Nov 2026 Regulation 19 consultation on Proposed Submission version of Haringey Local Plan 2027-2042 and submission to Secretary of StateDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
10 Nov 2026 Admission to Schools - Proposed Admission Arrangements for 2028/29DECLARATIONS OF INTEREST FOR THIS ITEM: None Decided Open
10 Nov 2026 Approval to extend current Highways and Street Lighting Contracts and approval of the procurement strategy for a future combined Highways and Street Lighting ContractDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies