Osborne Grove Nursing Home Redevelopment – Award of Contract for Architect led Multi-Disciplinary Design Services

Approved Executive 1 paper

Cabinet approved this item on Tuesday 16 March 2021. Below is the council's own wording, with the papers it was decided on.

Item499

Resolved

RESOLVED to 1. Approve an award of contract to Ingleton Wood LLP up to £2,185,257.25 (inclusive of surveys and contingency). This is based on delivering Multi-Disciplinary Services from RIBA Stage 2 to 6. Refer to Part B of this report for exempt information. Reasons for decision In July 2019 Cabinet approved a scheme that included the demolition of the existing buildings on site and the construction of a 70-bed nursing home. The minutes of this meeting included reference to the desire by Cabinet to also seek to maximise the use of the site. A further feasibility study completed in March 2020 demonstrated that the land where the existing facility is provided, offered significant opportunity for development to not only meet the recognised demand for nursing care but also additional housing demand across the Borough. There is not the skills or resources available in-house to deliver these works hence the requirement to appoint an external consultant for these services. Alternative Options Considered In-house – delivering the role in-house was considered, however there is currently no resource within the Council that has the capacity along with the necessary experience, qualifications, and expertise to deliver this service. The Dynamic Purchasing System was chosen to invite tenders above £160k as recommended by Strategic Procurement. Do nothing – The option to retain a 32-bed dual registration residential/nursing home on the site was considered but rejected, primarily because it would not increase the registered nursing capacity within the borough and because it would not address a number of fundamental design issues with the current building which prevent it functioning effectively as a nursing home and which could not be fully addressed due to structural limitations of the building. A review of activity and demand in Haringey confirmed the need for increased nursing bed capacity in the area. There are currently 175 Haringey service users in receipt of nursing care and this figure is projected to grow to around 250 by 2022/23. On the supply side, there is only one nursing home in Haringey. It has not, therefore, been possible for local demand for nursing care to be ... view the full minutes text for item 499.
Word for word from the decision Haringey published for this meeting. Source: www.minutes.haringey.gov.uk

Follow this further

Built from Haringey's papers

What the report saysPro

Report to Cabinet

Recommendations

3.1For Cabinet to approve an award of contract to Ingleton Wood LLP up to £2,185,257.25 (inclusive of surveys and contingency). This is based on delivering

Page 1 Multi-Disciplinary Services from RIBA Stage 2 to 6. Refer to Part B of this report for exempt information.

Reasons for decision

4.1In July 2019 Cabinet approved a scheme that included the demolition of the existing buildings on site and the construction of a 70-bed nursing home. The minutes of this meeting included reference to the desire by Cabinet to also seek to maximise the use of the site.

4.2A further feasibility study completed in March 2020 demonstrated that the land where the existing facility is provided, offered significant opportunity for development to not only meet the recognised demand for nursing care but also additional housing demand across the Borough.

4.3There is not the skills or resources available in-house to deliver these works hence the requirement to appoint an external consultant for these services.

Alternative options considered

5.1In-house – delivering the role in-house was considered, however there is currently no resource within the Council that has the capacity along with the necessary experience, qualifications, and expertise to deliver this service.

5.2The Dynamic Purchasing System was chosen to invite tenders above £160k as recommended by Strategic Procurement.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Osborne Grove Nursing Home Redevelopment: Award of Contract for Architect led Multi-Disciplinary Design ServicesMinutes 199 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 23 attended
JJ
John JonesCouncil Staff, expected
JE
Councillor Joseph EjioforChair, present
KA
Councillor Kaushika AminDeputy Chair, present
CA
Councillor Charles AdjeCommittee Member, present
MB
Councillor Mark BlakeCommittee Member, present
GB
Councillor Gideon BullCommittee Member, present
SC
Councillor Seema ChandwaniCommittee Member, present
KH
Councillor Kirsten HearnCommittee Member, present
EI
Councillor Emine IbrahimCommittee Member, present
SJ
Councillor Sarah JamesCommittee Member, present
MW
Councillor Matt WhiteCommittee Member, present
AS
Ayshe SimsekSecretary, expected

All 23 on the meeting page

On this subject at Haringey

Search all
  1. Osborne Grove Nursing Home Redevelopment – Award of Contract for Architect led Multi-Disciplinary Design ServicesThis decision
  2. Osborne groveApproved
  3. Approval for meanwhile use of the Osborne Grove Nursing Home building as the venue for the Rough Sleeper Night Shelter and insourcing the Rough Sleeping Night Shelter support provisionApproved
  4. Closure of Osborne Grove Nursing Home pending redevelopmentAgreed
  5. Mandate to consult on Osborne Grove Nursing Home ClosureApproved
  6. Osborne Grove Nursing Home Feasibility StudyNoted

More from Haringey Cabinet

All decisions
MeetingDecisionOutcome
10 Nov 2026 Corporate Delivery Plan 2026-2028DECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
10 Nov 2026 Draft 2027-28 Budget and 2027-2032 Medium Term Financial Strategy ReportDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
10 Nov 2026 Regulation 19 consultation on Proposed Submission version of Haringey Local Plan 2027-2042 and submission to Secretary of StateDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
10 Nov 2026 Admission to Schools - Proposed Admission Arrangements for 2028/29DECLARATIONS OF INTEREST FOR THIS ITEM: None Decided Open
10 Nov 2026 Approval to extend current Highways and Street Lighting Contracts and approval of the procurement strategy for a future combined Highways and Street Lighting ContractDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies