FIRS HOUSE - FIRE REINSTATEMENT WORKS

Approved Executive 1 paper

Cabinet Member Signing approved this item on Tuesday 30 March 2021. Below is the council's own wording, with the papers it was decided on.

Item4

Resolved

RESOLVED 1. Pursuant to the Council’s Contract Standing Order (CSO) 16.02, to approve the award of a contract to the preferred contractor identified in exempt Appendix A for the replacement of the main roof structure. The works include new flat roof covering to the communal staircase area, rainwater good, fascia boards and soffits, external brickwork and concrete repairs, external decoration and replacement of fire damaged windows. The work to fourteen flats includes the replacement of FD30S flat entrance doors, plastering, rewiring, new internal doors and joinery, kitchens, bathrooms, boilers and plumbing works, internal decorations and floor coverings. The roof structure to the east wing of the block was not damaged by the fire. However compartmentation works will be carried out to protect the integrity of the roof and will ensure that it meets current building regulations. This will be for the sum of £999,623. 2. To approve the issue of a letter of intent for an amount of up to, but not exceeding £99,962, which represents 10% of the contract sum. 3. To approve the total professional fees of £85,880 which represents 8.6% of the contract sum. 4. To note the total project costs of £1,085,503. 5. To waive the costs to leaseholders for the compartmentation works due to the nature and urgency of the works. 6. To note that the fire reinstatement works scheme for the main structure, communal areas and tenanted flats will be fully funded by the Council’s Building Insurance. 7. T o note that the internal works to Leaseholder’s flats will be funded by Ocaso under their Buildings Insurance Policy. Reasons for decision Homes for Haringey requires the Cabinet Member’s approval to award the contract for the rebuild of the main roof structure including fire compartmentation works to the entire roof, new flat roof covering to the communal staircase area, rainwater goods, fascia boards and soffits, external brickwork and concrete repairs, external decoration and replacement of windows damaged by the fire. Replacement of FD30 ... view the full minutes text for item 4.
Word for word from the decision Haringey published for this meeting. Source: www.minutes.haringey.gov.uk

Follow this further

Built from Haringey's papers

What the report saysPro

Report to Cabinet Member Signing

Recommendations

3.1Pursuant to the Council’s Contract Standing Order (CSO) 16.02, for the Cabinet Member for Housing and Estate Renewal to approve the award of a contract to the preferred contractor identified in exempt Appendix A for the replacement of the main roof structure. The works include new flat roof covering to the communal staircase area, rainwater good, fascia boards and soffits, external brickwork and concrete repairs, external decoration and replacement of fire damaged windows. The work to fourteen flats includes the replacement of FD30S flat entrance doors, plastering, rewiring, new internal doors and joinery, kitchens, bathrooms, boilers and plumbing works, internal decorations and floor coverings. The roof structure to the east wing of the block was not damaged by the fire. However compartmentation works

Page 1 of 8 will be carried out to protect the integrity of the roof and will ensure that it meets current building regulations. This will be for the sum of £999,623.

3.2For the Cabinet Member for Housing and Estate Renewal to approve the issue of a letter of intent for an amount of up to, but not exceeding £99,962, which represents 10% of the contract sum.

3.3For the Cabinet Member for Housing and Estate Renewal to approve the total professional fees of £85,880 which represents 8.6% of the contract sum.

3.4For the Cabinet Member for Housing and Estate Renewal to note the total project costs of £1,085,503.

3.5It is recommended that the costs to leaseholders for the compartmentation works are waived due to the nature and urgency of the works.

3.6For the Cabinet Member for Housing and Estate Renewal to note that the fire reinstatement works scheme for the main structure, communal areas and tenanted flats will be fully funded by the Council’s Building Insurance.

3.7For the Cabinet Member to note that the internal works to Leaseholder’s flats will be funded by Ocaso under their Buildings Insurance Policy.

Reasons for decision

4.1Homes for Haringey requires the Cabinet Member’s approval to award the contract for the rebuild of the main roof structure including fire compartmentation works to the entire roof, new flat roof covering to the communal staircase area, rainwater goods, fascia boards and soffits, external brickwork and concrete repairs, external decoration and replacement of windows damaged by the fire. Replacement of FD30’s flat entrance doors, plastering works, rewiring, new internal doors and joinery, kitchens, bathrooms, boilers and plumbing works, internal decoration and floor coverings. The contract which the report relates to has been procured through the Council’s Dynamic Purchasing System.

Alternative options considered

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
FIRS HOUSE: FIRE REINSTATEMENT WORKSMinutes 260 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

2 of 4 attended
JE
Councillor Joseph EjioforCommittee Member, present
EI
Councillor Emine IbrahimCommittee Member, apologies, sent representative
FR
Fiona RaeSecretary, in attendance
PS
Philip SlawtherSecretary, expected

On this subject at Haringey

Search all
  1. FIRS HOUSE - FIRE REINSTATEMENT WORKSThis decision
  2. Additional Cost Report for Firs House Fire Reinstatement WorksApproved

More from Haringey Cabinet Member Signing

All decisions
MeetingDecisionOutcome
2 Nov 2026 Deaf Outreach Services ContractDECLARATIONS FOR THIS ITEM: NONE Decided Open
28 Oct 2026 Administrative amendment to Merchant Acquirer Re-ProcurementRESOLVED 1. To note the administrative error in the original report referring to Global Pay and Global Payments; 2. T... Noted Open
20 Oct 2026 Approval of Additional Expenditure and Final Payment to Accora Limited reportDECLARATIONS FOR THIS ITEM: NONE RESOLVED The Cabinet Member for Adults and Health: 1. Approved the variation of cont... Approved Open
16 Oct 2026 Approve Funding from Arts Council England to Haringey Music Service for the North London Music HubDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
13 Oct 2026 Filming at meetingsThe notice of filming at meetings was noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies