Cabinet Member Signing, Friday 21 October 2022 at 10.00am

Additional Cost Report for Firs House Fire Reinstatement Works

Approved Executive 1 paper

Cabinet Member Signing approved this item on Friday 21 October 2022. Below is the council's own wording, with the papers it was decided on.

Item4

Resolved

RESOLVED 1. In accordance with Contract Standing Order 10.02.1(b) and Contract Standing Order 16.02, to approve additional costs and variations for Firs House Fire Reinstatement Works as follows: 2. To approve a variation of the contract with Cosmur (London) Limited to increase the value of the contract sum of £999,622.88, by £158,938, to an aggregate value of £1,158,561. 3. To approve a variation to the associated consultant contract with Ridge and Partners to increase the value of the contract sum by £33,223 for additional consultants’ fees, resulting in a total aggregate value of £119,103. 4. To agree that the cost of these works will not be recharged to the leaseholders of properties as the majority of the works are expected to be covered by insurance and the Major Works Capital Programme . Reasons for decision The Firs House Fire Reinstatement Works were approved by Cabinet in March 2021 and mobilised in September 2021. Additional works costs are required to reinstate building components that could not be contained within the provisional and contingency sums and to carry out additional improvements works including those recommended by Haringey Building Control, to bring the works up to current building standards. Alternative options considered The option of not doing the works was considered but rejected. As the Landlord, Haringey Council has a duty to ensure that the property meets the Decent Homes and current Health and Safety standards. It was more cost effective to include the works within the existing contract whilst on site as the works were integral to the dwellings and will be less disruptive for our residents.
Word for word from the decision Haringey published for this meeting. Source: www.minutes.haringey.gov.uk

Follow this further

Built from Haringey's papers

What the report saysPro

Report to Cabinet Member Signing, 7 pages

Recommendations

The Cabinet Member for Housing Service, Private Renters & Planning is recommended:

3.1In accordance with Contract Standing Order 10.02.1(b) and Contract Standing Order 16.02, to approve additional costs and variations for Firs House Fire Reinstatement Works as follows:

3.1.1 To approve a variation of the contract with Cosmur (London) Limited to increase the value of the contract sum of £999,622.88, by £158,938, to an aggregate value of £1,158,561.

3.1.2 To approve a variation to the associated consultant contract with Ridge and Partners to increase the value of the contract sum by £33,223 for additional consultants’ fees, resulting in a total aggregate value of £119,103.

3.2To agree that the cost of these works will not be recharged to the leaseholders of properties as the majority of the works are expected to be covered by insurance and the Major Works Capital Programme.

Reasons for decision

4.1The Firs House Fire Reinstatement Works were approved by Cabinet in March 2021 and mobilised in September 2021. Additional works costs are required to reinstate building components that could not be contained within the provisional and contingency sums and to carry out additional improvements works including

Page 1 of 7 those recommended by Haringey Building Control, to bring the works up to current building standards.

Alternative options considered

5.1The option of not doing the works was considered but rejected. As the Landlord, Haringey Council has a duty to ensure that the property meets the Decent Homes and current Health and Safety standards. It is more cost effective to include the works within the existing contract whilst on site as the works are integral to the dwellings and will be less disruptive for our residents.

6. Background information

6.1Approval was given on 30th March 2021, by Cabinet, for the Firs House Fire Reinstatement Works. The scope of works comprised of:-

 The rebuild of the main roof structure including fire compartmentation works to the entire roof, new flat roof covering to the communal staircase area, rainwater goods, fascia boards and soffits,  External brickwork and concrete repairs,  External decoration to the West side of the building  Replacement of the windows to Flat 16 which were damaged by the fire.  Replacement of FD30s flat entrance doors  Re-plastering works  Rewiring to the fire damaged flat  New internal doors and joinery  Replacement of kitchens and bathrooms  Replacement of boilers and plumbing works  Internal decoration and floor coverings to kitchens and bathrooms

6.2Project details:

The number of dwellings within this project 14 Total budget contract sum £999,623 Revised total budget contract forecast £1,158,561 Building contract variation £158,938 excluding fees Additional consultancy fees total £33,223 Original completion date reported 18/03/2022 Completion date now reported 12/08/2022 Contractor: Cosmur (London) Ltd Site works commenced on 06/09/2021 The original contract period was 26 weeks

6.3Summary of total costs:

Page 2 of 7 Item 1 2 3 4 5 Original Previousl Current Further Revised Total Financial y Financial Approval (3+4) Provision Authorise Provision Now (Tender d Sought Stage) Additions

£ £ £ £ £ Building £999,623 0 £999,623 £158,938 £1,158,561 contract Fees £85,880 0 £85,880 £33,223 £119,103

Total £1,085,503 0 £1,085,503 £192,161 £1,277,664

6.4Additional contract costs

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Additional Cost Report for Firs House Fire Reinstatement WorksMinutes 7 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Haringey

Search all
  1. Additional Cost Report for Firs House Fire Reinstatement WorksThis decision
  2. Additional contract costs for the Homes for Haringey external capital investment programme for year 2 (2019/20)Approved

More from Haringey Cabinet Member Signing

All decisions
MeetingDecisionOutcome
2 Nov 2026 Deaf Outreach Services ContractDECLARATIONS FOR THIS ITEM: NONE Decided Open
28 Oct 2026 Administrative amendment to Merchant Acquirer Re-ProcurementRESOLVED 1. To note the administrative error in the original report referring to Global Pay and Global Payments; 2. T... Noted Open
20 Oct 2026 Approval of Additional Expenditure and Final Payment to Accora Limited reportDECLARATIONS FOR THIS ITEM: NONE RESOLVED The Cabinet Member for Adults and Health: 1. Approved the variation of cont... Approved Open
16 Oct 2026 Approve Funding from Arts Council England to Haringey Music Service for the North London Music HubDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
13 Oct 2026 Filming at meetingsThe notice of filming at meetings was noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies