RESOLVED 1. In accordance with Contract Standing Order 10.02.1(b) and Contract Standing Order 16.02, to approve additional costs and variations for Firs House Fire Reinstatement Works as follows: 2. To approve a variation of the contract with Cosmur (London) Limited to increase the value of the contract sum of £999,622.88, by £158,938, to an aggregate value of £1,158,561. 3. To approve a variation to the associated consultant contract with Ridge and Partners to increase the value of the contract sum by £33,223 for additional consultants’ fees, resulting in a total aggregate value of £119,103. 4. To agree that the cost of these works will not be recharged to the leaseholders of properties as the majority of the works are expected to be covered by insurance and the Major Works Capital Programme . Reasons for decision The Firs House Fire Reinstatement Works were approved by Cabinet in March 2021 and mobilised in September 2021. Additional works costs are required to reinstate building components that could not be contained within the provisional and contingency sums and to carry out additional improvements works including those recommended by Haringey Building Control, to bring the works up to current building standards. Alternative options considered The option of not doing the works was considered but rejected. As the Landlord, Haringey Council has a duty to ensure that the property meets the Decent Homes and current Health and Safety standards. It was more cost effective to include the works within the existing contract whilst on site as the works were integral to the dwellings and will be less disruptive for our residents.
Word for word from the decision Haringey published for this meeting.Source: www.minutes.haringey.gov.uk
The Cabinet Member for Housing Service, Private Renters & Planning is recommended:
3.1In accordance with Contract Standing Order 10.02.1(b) and Contract Standing Order 16.02, to approve additional costs and variations for Firs House Fire Reinstatement Works as follows:
3.1.1 To approve a variation of the contract with Cosmur (London) Limited to increase the value of the contract sum of £999,622.88, by £158,938, to an aggregate value of £1,158,561.
3.1.2 To approve a variation to the associated consultant contract with Ridge and Partners to increase the value of the contract sum by £33,223 for additional consultants’ fees, resulting in a total aggregate value of £119,103.
3.2To agree that the cost of these works will not be recharged to the leaseholders of properties as the majority of the works are expected to be covered by insurance and the Major Works Capital Programme.
Reasons for decision
4.1The Firs House Fire Reinstatement Works were approved by Cabinet in March 2021 and mobilised in September 2021. Additional works costs are required to reinstate building components that could not be contained within the provisional and contingency sums and to carry out additional improvements works including
Page 1 of 7 those recommended by Haringey Building Control, to bring the works up to current building standards.
Alternative options considered
5.1The option of not doing the works was considered but rejected. As the Landlord, Haringey Council has a duty to ensure that the property meets the Decent Homes and current Health and Safety standards. It is more cost effective to include the works within the existing contract whilst on site as the works are integral to the dwellings and will be less disruptive for our residents.
6. Background information
6.1Approval was given on 30th March 2021, by Cabinet, for the Firs House Fire Reinstatement Works. The scope of works comprised of:-
The rebuild of the main roof structure including fire compartmentation works to the entire roof, new flat roof covering to the communal staircase area, rainwater goods, fascia boards and soffits, External brickwork and concrete repairs, External decoration to the West side of the building Replacement of the windows to Flat 16 which were damaged by the fire. Replacement of FD30s flat entrance doors Re-plastering works Rewiring to the fire damaged flat New internal doors and joinery Replacement of kitchens and bathrooms Replacement of boilers and plumbing works Internal decoration and floor coverings to kitchens and bathrooms
6.2Project details:
The number of dwellings within this project 14 Total budget contract sum £999,623 Revised total budget contract forecast £1,158,561 Building contract variation £158,938 excluding fees Additional consultancy fees total £33,223 Original completion date reported 18/03/2022 Completion date now reported 12/08/2022 Contractor: Cosmur (London) Ltd Site works commenced on 06/09/2021 The original contract period was 26 weeks
6.3Summary of total costs:
Page 2 of 7 Item 1 2 3 4 5 Original Previousl Current Further Revised Total Financial y Financial Approval (3+4) Provision Authorise Provision Now (Tender d Sought Stage) Additions
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.