RESOLVED that the Cabinet Member 1. Approve an award of contract to Contractor A up to a value of £1,683,722.59, pursuant to Contract Standing Order 16.02. 2. Approve a client construction contingency of 10% that equates to £168,372.26, which will be strictly managed under change control governance arrangements. 3. Approve the issuance of a letter of intent for up to 10% of the contract value, totalling £168,372.26. Reasons for decision A competitive tender for Phase 2 was issued to London Construction Programme Major Works 2019 Framework Education and Leisure Lot 2.1b North. Three tenders were received on 1 October 2021 (See Part B report). These works were originally approved on 9 November 2021 but has since changed due to circumstances outlined in Part B of this report. Two tenders were evaluated on 60% cost and 40% quality with all bids meeting the minimum quality criteria. On this basis, this report seeks approval to award the contract to the successful bidder (Contractor A) as outlined in part B of this report. The scheme for Campsbourne Primary School was developed into 2 phases. Phase 1 sought to meet the criteria for Public Sector Decarbonisation ... view the full minutes text for item 85.
Word for word from the decision Haringey published for this meeting.Source: www.minutes.haringey.gov.uk
The Cabinet Member for Children, Education, and Families is asked, pursuant to Contract Standing Order 16.02:
3.1To approve an award of contract to Contractor A up to a value of £1,683,722.59, pursuant to Contract Standing Order 16.02.
3.2To approve a client construction contingency of 10% that equates to £168,372.26, which will be strictly managed under change control governance arrangements.
3.3To approve the issuance of a letter of intent for up to 10% of the contract value, totalling £168,372.26.
Reasons for decision
4.1A competitive tender for Phase 2 was issued to London Construction Programme Major Works 2019 Framework Education and Leisure Lot 2.1b North. Three tenders were received on 1 October 2021 (See Part B report).
4.2These works were originally approved on 9 November 2021 but has since changed due to circumstances outlined in Part B of this report.
Page 1 4.3 Two tenders were evaluated on 60% cost and 40% quality with all bids meeting the minimum quality criteria. On this basis, this report seeks approval to award the contract to the successful bidder (Contractor A) as outlined in part B of this report.
4.4The scheme for Campsbourne Primary School was developed into 2 phases. Phase 1 sought to meet the criteria for Public Sector Decarbonisation (Salix) grant funding (a grant contribution of £0.243m), minimise disruption to the school by maximising access over the 2021 school summer holiday period, ensure resilience for heating and hot water and support a comprehensive phasing plan. A construction award to Mulalley & Co Ltd was supported by Cabinet on 15 June 2021 and commenced on site in July 2021. Phase 1 works include heating distribution system upgrade, loft insulation, flat roof works, masonry repairs and ground floor window replacement works. Both phases of works will improve the condition of the building for better education delivery but will also improve the energy efficiency and reduce carbon emissions during operation.
4.5The Phase 2 works to be undertaken by Contractor A include:
Window replacement and pitched roof repairs External walls repairs New entrance Repairs and replacement of boundary walls and fences Repairs to underground drainage Repairs to external surfaces Replacement of infant school boilers
Alternative options considered
5.1Do nothing option - a decision not to support this award of construction contract will result in the Council’s failure to suitably maintain its education estate by undertaking essential condition improvements. This would increase the likelihood of reactive works which will create greater disruption and cost to the council and potentially result in the loss of education days, all of which would undoubtedly impact on the quality of teaching and learning and potentially could lead to school closure.
6. Background Information
6.1London Borough of Haringey has sought to identify and address building condition and suitability issues across the education/schools estate.
6.2Initial condition and suitability surveys followed by comprehensive feasibility studies have led to the formation of the Children’s Capital Programme which seeks to support essential condition improvements across the education estate.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.