Resolved
RESOLVED 1. To approve a contract award to Mulalley and Company Ltd of £896,261. 2. To approve a client construction contingency of 10% that equates to £89,626 which will be strictly managed under change control governance arrangements. 3. To approve the issuance of a letter of intent for up to 10% of the contract value. Reasons for decision A major review of the condition and suitability of the Children’s Services estate has been undertaken, which has informed the Children’s Service’s asset management plan (CSAMP). This identified condition and suitability deficiencies in the primary, secondary, and wider Children’s Service estate that need addressing in the short, medium, and long-term. Campsbourne Primary School is high priority for major works due to issues relating to health and safety or risk of school closure. In 2018, an initial brief was given to undertake the most immediate (short term) health and safety, compliance, and resilience work. These findings included fire compartmentation, fire doors and heating resilience works and were subject to a separate award under delegated powers. In 2019, a further commission was approved, to further investigate and address urgent works relating to the condition of building services (i.e., heating, electrics, and plumbing), external envelope (i.e., roofs, windows) and boundary security. This condition project will bring a number of benefits to the school and the council, with the primary objective of providing improved educational environments for Children in line with Haringey’s borough plan. Along with improving educational outcomes, this project will significantly reduce the risk of a health and safety incident or school closure through condition failure such as mechanical failure or roof leaks. The project will also help the school reduce its energy demands and thus reduce carbon emissions through technologies and insulation including double glazing. This work also benefits the Council in reducing the reactive maintenance requirements at the school in future by economically fixing the root cause of the condition issues within a single project whilst avoiding additional temporary repairs costs. The scheme has been granted an allocation of funding £0.243M from the public sector decarbonisation programme, a government initiative sponsored by the Department for Business, Energy & Industrial Strategy and administered by Salix (Salix works). The grant will be used to part ... view the full minutes text for item 532.