Cabinet Member Signing, Thursday 10 March 2022 at 10.00am

Park View School - Replacement of Sports Hall Roof and Wall Cladding with Associated Works – Variation of Construction Contract

Approved Executive 1 paper

Cabinet Member Signing approved this item on Thursday 10 March 2022. Below is the council's own wording, with the papers it was decided on.

Item162

Resolved

RESOLVED 1. Pursuant to Contract Standing Order 16.02, to approve a variation of the construction contract to Cosmur Construction (London) Ltd in the sum of £39,271.59 giving a varied contract value of £908,702.83. 2. To approve a contingency allowance of 5% at £45,435.14 offering a total award value up to £954,137.97. The contingency will be managed under strict change control governance. Reasons for decision During construction, additional condition works have been identified that include the replacement of the hall flooring, lighting and redecoration. This was discovered once the works commenced and the contractor was able to fully access and intrusively inspect the hall flooring and lighting. Scaffolding and working crash deck in place for new mechanical works provided greater access to inspect lighting. The opportunity to complete these additional works as part of the current construction contract provides best value for the council and minimises disruption for the school. The Children’s Capital Programme Budget is sufficient to cover this contract increase. Alternative options considered Do nothing – a decision not to support the increase in the value of the construction works contract would leave the school with inadequate facilities to meet curriculum requirements which the community also benefit from.
Word for word from the decision Haringey published for this meeting. Source: www.minutes.haringey.gov.uk

Follow this further

Built from Haringey's papers

What the report saysPro

Report to Cabinet Member Signing

Recommendations

The Cabinet Member for Early Years, Children, and Families is asked:

3.1Pursuant to Contract Standing Order 16.02, to approve a variation of the construction contract to Cosmur Construction (London) Ltd in the sum of £39,271.59 giving a varied contract value of £908,702.83.

3.2To approve a contingency allowance of 5% at £45,435.14 offering a total award value up to £954,137.97. The contingency will be managed under strict change control governance.

Page 1 4. Reasons for decision .

4.1During construction, additional condition works have been identified that include the replacement of the hall flooring, lighting and redecoration. This was discovered once the works commenced and the contractor was able to fully access and intrusively inspect the hall flooring and lighting. Scaffolding and working crash deck in place for new mechanical works provided greater access to inspect lighting.

4.2The opportunity to complete these additional works as part of the current construction contract provides best value for the council and minimises disruption for the school.

4.3The Children’s Capital Programme Budget is sufficient to cover this contract increase.

Alternative options considered

5.1Do nothing – a decision not to support the increase in the value of the construction works contract would leave the school with inadequate facilities to meet curriculum requirements which the community also benefit from.

6. Background Information

6.1London Borough of Haringey are seeking to identify and address building condition and suitability issues across the Education/schools estate.

6.2A major review of the condition and suitability of the Children’s Services estate has been undertaken which has informed the Children’s Service’s asset management plan (CSAMP). This identified condition and suitability deficiencies in the primary, secondary, and wider Children’s Service estate that need addressing in the short, medium, and long-term.

6.3The condition survey for Park View School identified issues relating to the condition of the Sports Hall Roof including regular water penetration during rainfall. These issues were backed up by the school providing information about the history of the water penetration and the failure of recent attempts to repair the roof. During outline and design development the scope of the project evolved to also include:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Park View School: Replacement of Sports Hall Roof and Wall Cladding with Associated Works: Variation of Construction ContractMinutes 339 KB DownloadRead as text

At this meeting

Whole meeting
161Alexandra Primary School Urgent Condition Works - Construction Works Contract AwardApproved
162Park View School - Replacement of Sports Hall Roof and Wall Cladding with Associated Works – Variation of Construction ContractThis decision
163Alexandra Park Library - Enhancement Works - Award of Construction ContractApproved 164Exclusion of the Press and PublicDecided

Who was there

1 of 2 attended
ZB
Councillor Zena BrabazonCommittee Member, present
FR
Fiona RaeSecretary, expected

On this subject at Haringey

Search all
  1. Park View School - Replacement of Sports Hall Roof and Wall Cladding with Associated Works – Variation of Construction ContractThis decision
  2. Review of Parking Fees and Charges 2026-2027Decided
  3. Park View Secondary School Block A Roof Replacement - Award of Contract for Construction Related Consultancy ServicesDecided
  4. Park View Secondary School Block A Roof Replacement - Permission to initiate tender action for Construction Related Consultancy ServicesApproved
  5. Park View Secondary School Temporary Accommodation – Variation of Hire ContractApproved
  6. Car parking charges reviewApproved

More from Haringey Cabinet Member Signing

All decisions
MeetingDecisionOutcome
2 Nov 2026 Deaf Outreach Services ContractDECLARATIONS FOR THIS ITEM: NONE Decided Open
28 Oct 2026 Administrative amendment to Merchant Acquirer Re-ProcurementRESOLVED 1. To note the administrative error in the original report referring to Global Pay and Global Payments; 2. T... Noted Open
20 Oct 2026 Approval of Additional Expenditure and Final Payment to Accora Limited reportDECLARATIONS FOR THIS ITEM: NONE RESOLVED The Cabinet Member for Adults and Health: 1. Approved the variation of cont... Approved Open
16 Oct 2026 Approve Funding from Arts Council England to Haringey Music Service for the North London Music HubDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
13 Oct 2026 Filming at meetingsThe notice of filming at meetings was noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies