Park View School - Replacement of Sports Hall Roof and Wall Cladding with Associated Works - Further Variation of Construction Contract

Approved Executive 1 paper

Cabinet Member Signing approved this item on Thursday 1 December 2022. Below is the council's own wording, with the papers it was decided on.

Item4

Resolved

RESOLVED 1. Pursuant to Contract Standing Order 16.02, to approve a further variation of the construction contract to Cosmur Construction (London) Ltd in the sum of £85,668.24 giving a varied contract value of £1,039,806.11. 2. To waiver Contract Standing Order 3.01d and delegate authority to the Director of Children’s Services to approve any subsequent variations which may be required in the settlement of the final account up to £50,000. Reasons for decision The initial variation of construction supported additional condition works to replace the hall flooring, lighting (bulb replacement only) and redecoration. Works which had been discovered once the works commenced and the contractor was able to fully access and intrusively inspect the hall flooring and lighting. Scaffolding and working crash deck in place for new mechanical works provided greater access to inspect lighting. A further variation is requested to support additional gantry works for the air handling unit, temporary ventilation supplies over the exam period, raising the height of the new ventilation sock, fire alarm modifications, additional drainage works and adjustments to the design for damp proof membrane. These works have been approved by the Client under change control and are contained within the programme budget. The additional works provide the Council with greater value for money by including the works within the current contract on site, as opposed to returning with a separate contract, which as a result of the current climate – construction inflation and material shortages - would likely result in inflated market rates and cause further disruption to the school. The additional work has led to the contractor requesting further time to accommodate all additional work condition works, some of which may not been fully considered ... view the full minutes text for item 4.
Word for word from the decision Haringey published for this meeting. Source: www.minutes.haringey.gov.uk

Follow this further

Built from Haringey's papers

What the report saysPro

Report to Cabinet Member Signing, 6 pages

Recommendations

For Cabinet Member for Children, Schools, and Families is recommended:

3.1Pursuant to Contract Standing Order 16.02, to approve a further variation of the construction contract to Cosmur Construction (London) Ltd in the sum of £85,668.24 giving a varied contract value of £1,039,806.11.

Page 1 3.2 To waiver Contract Standing Order 3.01d and delegate authority to the Director of Children’s Services to approve any subsequent variations which may be required in the settlement of the final account up to £50,000. 4. Reasons for decision

4.1The initial variation of construction supported additional condition works to replace the hall flooring, lighting (bulb replacement only) and redecoration. Works which had been discovered once the works commenced and the contractor was able to fully access and intrusively inspect the hall flooring and lighting. Scaffolding and working crash deck in place for new mechanical works provided greater access to inspect lighting.

4.2A further variation is requested to support additional gantry works for the air handling unit, temporary ventilation supplies over the exam period, raising the height of the new ventilation sock, fire alarm modifications, additional drainage works and adjustments to the design for damp proof membrane. These works have been approved by the Client under change control and are contained within the programme budget.

4.3The additional works provide the Council with greater value for money by including the works within the current contract on site, as opposed to returning with a separate contract, which as a result of the current climate – construction inflation and material shortages - would likely result in inflated market rates and cause further disruption to the school.

4.4The additional work has led to the contractor requesting further time to accommodate all additional work condition works, some of which may not been fully considered as part of the original variation request.

4.5The final account has not been agreed and will require to be fully evidenced to achieve the allowance requested in this report.

4.6The Children’s Capital Programme Budget is sufficient to cover this contract increase.

Alternative options considered

5.1Do nothing – a decision not to support the increase in the value of the construction works contract would leave the school with inadequate facilities to meet curriculum requirements which the community also benefit from.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Park View School: Replacement of Sports Hall Roof and Wall Cladding with Associated Works: Further Variation of Construction ContractMinutes 6 pages DownloadRead as text

At this meeting

Whole meeting
3Haringey Family Hubs ProgrammeApproved
4Park View School - Replacement of Sports Hall Roof and Wall Cladding with Associated Works - Further Variation of Construction ContractThis decision
5Seven Sisters Primary School Building Services and External Envelope Improvement Works Phase 1 & 2 - Variation of Construction ContractApproved

On this subject at Haringey

Search all
  1. Park View School - Replacement of Sports Hall Roof and Wall Cladding with Associated Works - Further Variation of Construction ContractThis decision
  2. Review of Parking Fees and Charges 2026-2027Decided
  3. Park View Secondary School Block A Roof Replacement - Award of Contract for Construction Related Consultancy ServicesDecided
  4. Park View Secondary School Block A Roof Replacement - Permission to initiate tender action for Construction Related Consultancy ServicesApproved
  5. Park View Secondary School Temporary Accommodation – Variation of Hire ContractApproved
  6. Car parking charges reviewApproved

More from Haringey Cabinet Member Signing

All decisions
MeetingDecisionOutcome
2 Nov 2026 Deaf Outreach Services ContractDECLARATIONS FOR THIS ITEM: NONE Decided Open
28 Oct 2026 Administrative amendment to Merchant Acquirer Re-ProcurementRESOLVED 1. To note the administrative error in the original report referring to Global Pay and Global Payments; 2. T... Noted Open
20 Oct 2026 Approval of Additional Expenditure and Final Payment to Accora Limited reportDECLARATIONS FOR THIS ITEM: NONE RESOLVED The Cabinet Member for Adults and Health: 1. Approved the variation of cont... Approved Open
16 Oct 2026 Approve Funding from Arts Council England to Haringey Music Service for the North London Music HubDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
13 Oct 2026 Filming at meetingsThe notice of filming at meetings was noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies