London Borough of Haringey
Alexandra Park and Palace Board, Tuesday 13 December 2022 at 7.30pm

CEOs REPORT

Noted Committee 1 paper

Alexandra Park and Palace Board noted this item on Tuesday 13 December 2022. Below is the council's own wording, with the papers it was decided on.

Item8

Resolved

RESOLVED 1. To note the content of the attached report; 2. To approve the proposal to apply to the Local Planning Authority for Planning and Listed Building Consent to extend the use of the shaded wooden structure (the pagoda) on the space outside the Phoenix Bar and Kitchen known as “The Beach” for two additional months a year from March to November following consultation with the Advisory and Consultative Committees; 3. To approve the New Year’s Eve road closure between 21:00hrs on 31 st December 2022 and 02:00hrs on 1 st January 2023, except for the W3 bus.
Word for word from the decision Haringey published for this meeting. Source: www.minutes.haringey.gov.uk

Follow this further

Built from Haringey's papers

What the report saysPro

Report to Alexandra Park and Palace Board, 7 pages

Recommendations

1.1To note the content of this report;

1.2To approve the proposal to apply to the Local Planning Authority for Planning and Listed Building Consent to extend the use of the shaded wooden structure (the pagoda) on the space outside the Phoenix Bar and Kitchen known as “The Beach” for two additional months a year from March to November following consultation with the Advisory and Consultative Committees;

1.3To approve the New Year’s Eve road closure between 21:00hrs on 31 st December 2022 and 02:00hrs on 1st January 2023, except for the W3 bus.

Executive summary

2.1This report provides a general update including Creative Learning and Park activity, the Christmas Programme and progress on planning and environmental sustainability projects.

3. Environmental Sustainability

3.1The Trustee Board approved the Environmental Sustainability Policy in September, which was also presented to the Advisory & Consultative Committees in November with an update of the work undertaken to date, including an energy audit and LED lighting replacements across the site.

3.2An energy action plan is in place and a Sustainability Working Group has been set up to examine ways we can reduce our energy costs. This will explore actions we can all do to help, short term wins and longer term projects. 3.3 Our Head of Park and Environmental Sustainability has been reviewing energy data from the 80 electrical meters across the Park and Palace to understand the baselines and, in time, set priorities for improvements.

3.4The team have also been supported by the Council’s Carbon Reduction team to apply for grants to fund feasibility work for sustainability projects such as renewable energy sources.

4. Planning applications

4.1The Listed Building Consent application to create a new opening from the East Court into the South East Office Building and the planning and advertisement consent application for the Parking Management System (parking charges) project have been submitted.

4.2On 15 July, a formal pre-application meeting with the Haringey team took place to discuss the skywalk adventure proposal. Representatives from planning, conservation and transport were present. In principle, there was unanimous support for the proposal, as the planning team appreciated how the project aligned with the Trusts objectives and that it was a new, exciting and innovative way for visitors to enjoy the heritage setting of the Park and Palace, whilst learning about its eclectic and inspiring past, present and future.

4.3The Planning Authority has advised that to ensure the proposal is acceptable in planning and heritage terms, there needs to be an assessment undertaken on the existing make-up and condition of the Great Hall roof and a clear understanding of how new interventions into the listed fabric will be minimal, and the impact mitigated. It is also required that the proposal does not have a negative impact on the local views of the Palace. These are all matters and considerations that had been previously identified by the APPCT team and therefore we are confident that these matters will be addressed as part of the application.

4.4On 17th November the Advisory and Consultative Committee were consulted on the proposal to apply for an extension to the time limit for the temporary pagoda on the Beach (the area in-front of the Phoenix Bar and Kitchen). Currently the Trust is permitted to have the pagoda in place during the months from March to September (inclusive). The Committees noted the proposal and had no objections to the proposal to apply to extend planning permission for the pagoda of 2 months (March – November inclusive).

5. Creative Learning

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
CEOs REPORTMinutes 7 pages DownloadRead as text

At this meeting

Whole meeting

More from Haringey Alexandra Park and Palace Board

All decisions
MeetingDecisionOutcome
29 Oct 2026 Charitable Trust Progress ReportThe Committee noted the report. Noted Open
29 Oct 2026 FRRAC Chair's Report (Verbal update)The Committee noted the report. Noted Open
29 Oct 2026 Finance ReportThe Committee noted the 2026/27 forecast against revised budget. Noted Open
29 Oct 2026 Panorama Room ReportThe Committee noted the report. Noted Open
29 Oct 2026 Environmental Sustainability UpdateThe Committee noted the contents of this report and approve the Carbon Reduction Plan at Appendix 1. Noted Open