Resolved
RESOLVED 1. To approve a further variation (no. 2), to increase the Contract Award to Lilstone Limited (no.1) of £1,027,414.08, by £473,934.00 to a maximum of £1,501,400. Reasons for decision During the construction works, the project has suffered significant delays attributed to the delay in receiving NR technical approvals, unforeseen and unforeseeable heritage repairs, and sequencing of works. This variation Report seeks approval to vary the contract award made by Cabinet on 18 th January 2022, which in itself was, a variation to the original contract awarded in July 2021. At the end of March 2022 NR advised that the technical approval process for NR had changed. At the same time, officers were made aware that due to the minor design changes to the accommodate the new building extension within our title boundary a new full technical approvals application would be needed. The delays with obtaining the NR technical approvals have impacted on the construction programme. The contractor has not been able to commence with the demolition or piling works, which are critical path items, as these are located on the boundary line with NR. Whilst there have been some movement recently from NR to allow some works to progress with certain elements of work to reduce the impact on the programme, due to the ongoing delays with approvals, the works have reached a critical stage in the project resulting the contractor advising in August 2022 that they had run out of work which could be completed on site. Due to the nature of the building and dereliction over a number of years, elements of unforeseeable heritage repairs to preserve the Grade II Listed status of the Pavilion Building have been uncovered. Listed Building Consent was also required for these repairs, which has contributed to the delay. Alternative Options Considered Option 1: Continue with the refurbishment works Continue with the refurbishment works whilst the NR and Listed Building Consents are gained; this option was discounted as it would have allowed the contractor to maintain a site presence and charge full preliminary costs whilst they waited for NR approvals ... view the full minutes text for item 12.