CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
London Borough of Haringey
Cabinet, Tuesday 17 January 2023 at 6.30pm

Bruce Grove Public Conveniences Refurbishment Works

Approved Executive 1 paper

Cabinet approved this item on Tuesday 17 January 2023. Below is the council's own wording, with the papers it was decided on.

Item12

Resolved

RESOLVED 1. To approve a further variation (no. 2), to increase the Contract Award to Lilstone Limited (no.1) of £1,027,414.08, by £473,934.00 to a maximum of £1,501,400. Reasons for decision During the construction works, the project has suffered significant delays attributed to the delay in receiving NR technical approvals, unforeseen and unforeseeable heritage repairs, and sequencing of works. This variation Report seeks approval to vary the contract award made by Cabinet on 18 th January 2022, which in itself was, a variation to the original contract awarded in July 2021. At the end of March 2022 NR advised that the technical approval process for NR had changed. At the same time, officers were made aware that due to the minor design changes to the accommodate the new building extension within our title boundary a new full technical approvals application would be needed. The delays with obtaining the NR technical approvals have impacted on the construction programme. The contractor has not been able to commence with the demolition or piling works, which are critical path items, as these are located on the boundary line with NR. Whilst there have been some movement recently from NR to allow some works to progress with certain elements of work to reduce the impact on the programme, due to the ongoing delays with approvals, the works have reached a critical stage in the project resulting the contractor advising in August 2022 that they had run out of work which could be completed on site. Due to the nature of the building and dereliction over a number of years, elements of unforeseeable heritage repairs to preserve the Grade II Listed status of the Pavilion Building have been uncovered. Listed Building Consent was also required for these repairs, which has contributed to the delay. Alternative Options Considered Option 1: Continue with the refurbishment works Continue with the refurbishment works whilst the NR and Listed Building Consents are gained; this option was discounted as it would have allowed the contractor to maintain a site presence and charge full preliminary costs whilst they waited for NR approvals ... view the full minutes text for item 12.
Word for word from the decision Haringey published for this meeting. Source: www.minutes.haringey.gov.uk

Follow this further

Built from Haringey's papers

What the report saysPro

Report to Cabinet

Report for: Cabinet

Title: Bruce Grove Public Convenience Refurbishment Woks – Variation of Construction Contract Award Report authorised by: David Joyce, Director of Placemaking & Housing

Lead Officer: Sukh Lall, Project Manager, Telephone [phone removed], Email: [email protected]

Ward(s) affected: Bruce Grove

Report for Key/ Non-Key Decision: Key Decision

1. Describe the issue under consideration

1.1The Bruce Grove Public Convenience (BGPC) project aims to refurbish and extend the Grade II listed former public convenience building in order to transform this local landmark into a new café with a social value operator and finally remove it from Historic England’s ‘Heritage at Risk’ Register.

1.2In January 2019, following the adoption of the Strategy for Tottenham High Road, the council secured GLA Good Growth Fund (GGF) to support the delivery of this project as part of the Enterprise Tottenham High Road Grant Agreement. This was followed by a successful bid to Historic England enabling the council to enter grant agreement for Tottenham Heritage Action Zone (HAZ) and bring forward the refurbishment of the Grade II listed landmark.

1.3In April 2021, following a competitive procurement process via the Dynamic Purchasing System (DPS), Cabinet approved the award for the construction contract to Lilstone Limited to deliver the BGPC refurbishment works. The award was approved in the sum of £817,175.13, plus a 10% contingency of £81,717.51 with works commencing 16th July 2021 and completing January 2022.

1.4In July 2021, a boundary discrepancy was highlighted during easement negotiations with Network Rail (NR) which delayed the works commencing on site. This delay was caused by the need to redesign the scheme to fit the correct boundary line and to obtain the revised planning approvals needed; these were granted in November 2021. At the same time the contractor was asked to revisit and adjust their tender costs due to the timeframe between their original tender submission in February 2021 and November 2021 when the redesigns were completed.

1.5The impact of the issues highlighted in 1.4 resulted in a Contract Variation Report (no1.) being presented to Cabinet in January 2022 to increase the contract awarded to Lilstone Limited from £898,892.64 to £1,027,414.08.

Page 1 1.6 Since commencing with the works in January 2022, the project has suffered significant delays with obtaining NR technical approvals.

1.7This report also reflects unforeseen and unforeseeable heritage repairs to the Grade II Listed Pavilion building for which Listed Building Consents (LBC) are needed.

1.8The delays detailed in 1.6 have prevented the contractor commencing with the works on the project critical path as programmed which has resulted with elements of the works being completed out of sequence. This has delayed the project completion and led to increased costs and programme delays.

1.9The delay with NR approval has led to the suspension of works on site in line with the original programme. There is currently an LBC application submitted to cover the unforeseen work on site which is to be determined shortly. NR technical approval is now in place. LBC is expected to be obtained shortly to enable further heritage repairs and temporary works to resume as planned in January 2023.

1.10As a result of 1.6-1.8 this report seeks a variation to the contract awarded to Lilstone Limited by Cabinet in January (detailed in 1.5 above), by £473,943.00 to a maximum of £1,501,400.

2. Cabinet Member Introduction

2.1Tottenham’s town centres are at the heart of their local communities, providing jobs, services, shops, leisure facilities and social spaces. In Bruce Grove, the council is delivering projects to improve and restore our heritage assets including important community and cultural infrastructure. This includes bringing back the Grade II Listed Bruce Grove Public Convenience into active use with a view to support a new social value operator.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Bruce Grove Public Conveniences Refurbishment WorksMinutes 330 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 22 attended
PA
Councillor Peray AhmetChair, present
MH
Councillor Mike HakataCommittee Member, present
ZB
Councillor Zena BrabazonCommittee Member, present
DC
Councillor Dana CarlinCommittee Member, present
SC
Councillor Seema ChandwaniCommittee Member, present
LD
Councillor Lucia das NevesCommittee Member, present
JD
Councillor Julie DaviesCommittee Member, apologies
RG
Councillor Ruth GordonCommittee Member, present
AJ
Councillor Adam JogeeCommittee Member, present
SW
Councillor Sarah WilliamsCommittee Member, apologies
AD
Andy DonaldOfficer, expected
FA
Fiona AldermanCouncil Staff, expected

All 22 on the meeting page

On this subject at Haringey

Search all
  1. Bruce Grove Public Conveniences Refurbishment WorksThis decision
  2. Bruce Grove Public Convenience Refurbishment and Extension Works - Variation of Construction Works Contract AwardApproved
  3. Approve extension (and variation where it applies) of the Bounds Green, Bruce Grove, Harringay, Noel Park, Northumberland Park, Seven Sisters, St Anns, Tottenham Green, Tottenham Hale, West Green and Woodside Wards Alcohol Control PSPO'sDecided
  4. Ratification of the decision to go out to consultation on the extension and minor variation to Bruce Grove Alcohol Control PSPONoted
  5. West Green and Bruce Grove Primary Schools Building Services and External Envelope Works - Variation of Construction ContractNoted
  6. Bruce Grove Public Convenience - Construction Works VariationApproved

More from Haringey Cabinet

All decisions
MeetingDecisionOutcome
10 Nov 2026 Corporate Delivery Plan 2026-2028DECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
10 Nov 2026 Draft 2027-28 Budget and 2027-2032 Medium Term Financial Strategy ReportDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
10 Nov 2026 Regulation 19 consultation on Proposed Submission version of Haringey Local Plan 2027-2042 and submission to Secretary of StateDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
10 Nov 2026 Admission to Schools - Proposed Admission Arrangements for 2028/29DECLARATIONS OF INTEREST FOR THIS ITEM: None Decided Open
10 Nov 2026 Approval to extend current Highways and Street Lighting Contracts and approval of the procurement strategy for a future combined Highways and Street Lighting ContractDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies