Decentralised Energy Network Programme Decision to Start Design and Build (D&B) Procurement - NON KEY

Agreed Executive 1 paper

Cabinet agreed this item on Tuesday 17 January 2023. Below is the council's own wording, with the papers it was decided on.

Item13

Resolved

RESOLVED to 1. Agree to commence the Design and Build (D&B) procurement for the Council’s Decentralised Energy Network (DEN) Programme in accordance with the Utilities Contract Regulations (UCRs) utilising Negotiation with Prior Call for Competition as permitted under UCR 47. 2. Agree the procurement strategy set out in section 7 of the report. Reasons for decision Procurement of the DEN infrastructure must start in early 2023 in order to deliver the FBC by late 2023 and to support the Council to fulfil obligations in the Development Agreement at High Road West. A full range of options has been considered and the proposed strategy will deliver best value to the Council. Alternative options considered Note a glossary is provided in Section 10 of the report to explain some terminology Do nothing If procurement is not commenced, the costs and contract terms for building DEN infrastructure would not be known and the Council will not be able to deliver the FBC for the DEN programme which in turn would not deliver the government requirements of the Heat Networks Investment Project (HNIP) funding. This option has not been considered further. See also further information on the Do nothing option in paragraph 5.1.1 of the Exempt Report, Seek Third Party Investors It is possible to run a procurement to select a third party investor who will then deliver the project directly (including procuring the infrastructure) or to simultaneously seek to find a third party investor as a partner while procuring the infrastructure (with this second route, the pool of investors is limited to those bidding for the works). The OBCs for the various projects have considered the potential for 3 rd party investors in the Haringey DEN projects. The projects are large, complex, at an advanced stage and the Council does not have control over significant parts of the projects. This makes it difficult to find a third party investor under either of the routes summarised above. Even if it were possible to attract third parties to invest in Haringey’s DEN projects, there are two principal reasons why this has been discounted. Firstly, there is a preference for the future provider created by the project to be publicly owned which suggests first seeking a partner and then procuring the infrastructure (rather than seeking an investor at the same time as procuring the assets). Secondly, the three opportunities are all time-limited and there is insufficient time for the Council to select a project partner and to then deliver the projects. It is important to note two things. Firstly, that any effort to seek a third party investor will be time and resource intensive. Seeking to do this while also trying to get the projects off the ground is not recommended. Secondly, there is nothing preventing the Council from seeking investors in the projects at a later date. This option has not been considered further. Contract Aggregation Options Given the above, it will be the Council procuring the infrastructure. The options for aggregating the different ... view the full minutes text for item 13.
Word for word from the decision Haringey published for this meeting. Source: www.minutes.haringey.gov.uk

Follow this further

Built from Haringey's papers

What the report saysPro

Report to Cabinet

Recommendations

Cabinet is asked to:

3.1Agree to commence the Design and Build (D&B) procurement for the Council’s Decentralised Energy Network (DEN) Programme in accordance with the Utilities Contract Regulations (UCRs) utilising Negotiation with Prior Call for Competition as permitted under UCR 47.

3.2Agree the procurement strategy set out in section 7 of this report.

Reasons for decision

4.1Procurement of the DEN infrastructure must start in early 2023 in order to deliver the FBC by late 2023 and to support the Council to fulfil obligations in the Development Agreement at High Road West.

4.2A full range of options has been considered and the proposed strategy will deliver best value to the Council.

Alternative options considered

Note a glossary is provided in Section 10 of this report to explain some terminology

5.1Do nothing If procurement is not commenced, the costs and contract terms for building DEN infrastructure would not be known and the Council will not be able to deliver the FBC for the DEN programme which in turn would not deliver the government requirements of the Heat Networks Investment Project (HNIP) funding.

This option has not been considered further.

See also further information on the Do nothing option in paragraph 5.1.1 of the Exempt Report,

5.2Seek Third Party Investors It is possible to run a procurement to select a third party investor who will then deliver the project directly (including procuring the infrastructure) or to simultaneously seek to find a third party investor as a partner while procuring the infrastructure (with this second route, the pool of investors is limited to those bidding for the works).

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Decentralised Energy Network Programme Decision to Start Design and Build (D&B) Procurement: NON KEYMinutes 719 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 22 attended
PA
Councillor Peray AhmetChair, present
MH
Councillor Mike HakataCommittee Member, present
ZB
Councillor Zena BrabazonCommittee Member, present
DC
Councillor Dana CarlinCommittee Member, present
SC
Councillor Seema ChandwaniCommittee Member, present
LD
Councillor Lucia das NevesCommittee Member, present
JD
Councillor Julie DaviesCommittee Member, apologies
RG
Councillor Ruth GordonCommittee Member, present
AJ
Councillor Adam JogeeCommittee Member, present
SW
Councillor Sarah WilliamsCommittee Member, apologies
AD
Andy DonaldOfficer, expected
FA
Fiona AldermanCouncil Staff, expected

All 22 on the meeting page

On this subject at Haringey

Search all
  1. Decentralised Energy Network Programme Decision to Start Design and Build (D&B) Procurement - NON KEYThis decision
  2. Decentralised Energy Networks (DEN) Outline Business Case (OBC)Approved
  3. North Tottenham Decentralised Energy NetworkApproved
  4. London Development Agency - Decentralised Energy Support Programme for BoroughsNoted

More from Haringey Cabinet

All decisions
MeetingDecisionOutcome
10 Nov 2026 Corporate Delivery Plan 2026-2028DECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
10 Nov 2026 Draft 2027-28 Budget and 2027-2032 Medium Term Financial Strategy ReportDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
10 Nov 2026 Regulation 19 consultation on Proposed Submission version of Haringey Local Plan 2027-2042 and submission to Secretary of StateDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
10 Nov 2026 Admission to Schools - Proposed Admission Arrangements for 2028/29DECLARATIONS OF INTEREST FOR THIS ITEM: None Decided Open
10 Nov 2026 Approval to extend current Highways and Street Lighting Contracts and approval of the procurement strategy for a future combined Highways and Street Lighting ContractDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies