RESOLVED 1. To approve the Flood Water Management Investment Plan for the 2023/24 financial year as set out in the attached Appendix 1 of the report. 2. To delegate decisions relating to flood water management scheme design and implementation to the Head of Highways and Parking, subject to decisions being reported to Cabinet where a key decision is required. 3. To authorise the Head of Highways and Parking to carry out any required consultation in accordance with Appendix 2 of the report and to make any necessary traffic orders, having had due regard to any prior consultation, to give effect to those schemes, subject to consultation representations regarding key decisions being considered by Cabinet. 4. To authorise the Head of Highways and Parking to consider any objections and representations and to report back to the Cabinet Member for Inequality and Resident Services if there are significant or substantial objections or concerns raised about a scheme not covering two or more wards. Reasons for Decision The FWMIP sets out the Council’s flood water management and highways drainage resilience projects for the coming financial year and how they align with the Council’s strategic objectives. This report provides detail of the funding arrangements and seeks authority to proceed with the development and delivery of these projects. Alternative options considered The Council has a statutory duty to maintain the public highway network and reduce the risk of flooding in the borough. The 2023/24 Flood Water Management Investment Plan has been informed by data from actual flooding events, as well the Council’s Transport and Local Flood Risk Management Strategies, our Surface Water Management Plan, and the developing Highways Asset Management Strategy. The schemes proposed in this programme are those identified as high priority to reduce the risk of future flooding in the borough. Therefore, no alternative options are considered at this point.
Word for word from the decision Haringey published for this meeting.Source: www.minutes.haringey.gov.uk
1 Describe the issue under consideration. 1.1 Haringey, like many London Boroughs is vulnerable to surface water flooding. Our urban environment has reduced natural drainage. Heavy rainfall can swiftly overwhelm the drainage network, quickly leading to flooding of low-lying areas.
1.2Intense rainfall events are becoming more frequent. Haringey, as well as other London boroughs, experienced flooding from extreme rainfall in July 2021 and August 2022. Climate change is projected to increase the frequency and intensity of heavy rainfall, in turn increasing the risk of flooding.
1.3As the ‘lead local flood authority’ (LLFA), the Council, working in partnership with the Environment Agency, Thames Water and other stakeholders, is responsible for managing the risk of flooding from surface water, groundwater, and some of the culverted watercourses.
1.4It is not possible to completely stop flooding, but steps can be taken to reduce the effect through measures including that of highways drainage resilience works and schemes to prevent unmanaged flooding
1.5This report sets out the Council’s Flood Water Management Investment Plan (FWMIP) capital programme and interventions for 2023/2024 and the context in which that programme has been developed. Appendix 1 sets out the proposed allocation of schemes within the overall programme. Those schemes are a 'living document' of proposals which are developed as the Council understands the various issues that have an impact on flooding across the Borough.
2 Cabinet Member Introduction 2.1 I am pleased to introduce this report which sets out the investment plan in flood reduction and drainage improvement schemes for the coming year. Over the past two years, we have seen the devastation that flooding causes in many
1 parts of our borough. It impacted on homes and businesses and disrupted local infrastructure.
2.2Climate change will only increase the frequency and intensity of heavy rainfall, increasing our risk of flooding.
2.3Since the flooding events of July 2021, the Council has significantly increased its investment in drainage, spending £800k in 2022/23 to ensure that all road gullies across Haringey were cleansed at least once each year, and to repair and provide additional road gullies where they were clearly needed.
2.4However, the response to flooding in respect of defences, capacity management and education requires a holistic multi-agency approach. With the impacts of climate change becoming increasingly more evident, we more frequently see flooding at locations such as Turnpike Lane and the junction of Park Road, Muswell Hill and Priory Road due to an aged sewerage system, struggling to cope with anything other than moderate levels of rainfall. We will therefore continue to lobby Thames Water to maintain its assets, and the Government for funding to further green our borough - as well as exploiting every opportunity to bring in funding from external funding sources for flood risk reduction measures.
2.5This year, the Council is investing a total of £1,562,500 of capital funding in the maintenance of our drainage assets, as well as implementing schemes to reduce the risk of flooding across the borough. We will continue to engage with residents, community groups, businesses, and other interested parties to co- design flood schemes that alter the existing infrastructure. This engagement will also extend to the management of any proposed significant disruption resulting from the construction works.
2.6We will also help our communities build resilience and help them protect themselves from unmitigated flooding.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.