London Borough of Haringey
Cabinet, Tuesday 18 April 2023 at 6.30pm

Civic Centre Project Update

Agreed Executive 2 papers

Cabinet agreed this item on Tuesday 18 April 2023. Below is the council's own wording, with the papers it was decided on.

Item14

Resolved

RESOLVED 1. To agree to continue to proceed with the r estoration and refurbishment of the existing Civic Centre, and its expansion through the addition of an Annex building, up to the conclusion of the procurement process to appoint a main contractor. 2. To note that a further report will be brought to Cabinet to approve the main construction contract for the Civic Centre project, anticipated to be Q4 2023. Reasons for decision The Council office accommodation business case agreed by cabinet in January 2022 demonstrated that the best option to meet the Council’s core office accommodation needs was to restore and refurbish the Civic Centre along with the addition of an annex building. The decision allowed the Council to continue to work to deliver this scheme, with the objectives of restoring the iconic Civic Centre building for civic and democratic functions, and with providing high-quality, accessible, and sustainable office accommodation in the heart of the borough. The January 2022 decision agreed that the scheme would be developed through until the planning application stage, which has now been reached and thus this report seeks authorisation to proceed with the scheme up to the conclusion of the procurement process to appoint the main contractor, at which point the final contract award recommendation will be presented to Cabinet, currently anticipated to be during Q4 2023. The January 2022 report also agreed the award of a preparatory works contract, which removed all redundant building services and asbestos in the Civic Centre building to prepare for the main construction contract and expose any hidden issues. The preparatory works contract has been successful in exposing previously unidentified condition issues and has allowed the project team to complete additional survey work and gain a better understanding of the condition of the existing structure, which has allowed for more detailed design proposals to be prepared. Additionally, the January 2022 report also identified the risk that the construction industry was in a volatile state due to the impacts of Brexit and the Covid pandemic. The situation has worsened over the course of 2022 due the impact of the Ukraine crisis on the supply of materials and labour. The economic impact on these issues has led to the BCIS Tender Price Index projections increasing significantly. ... view the full minutes text for item 14.
Word for word from the decision Haringey published for this meeting. Source: www.minutes.haringey.gov.uk

Follow this further

Built from Haringey's papers

What the report saysPro

Report to Cabinet

Report for: Cabinet – 18 April 2023

Title: Civic Centre Project Update

Report authorised by: David Joyce, Director of Housing, Regeneration & Planning

Lead Officer: Jonathan Kirby, Assistant Director of Capital Projects & Property

Ward(s) affected: Woodside, All Wards

Report for Key/ Non-Key Decision: Key Decision

1. Describe the issue under consideration

1.1The Cabinet agreed on 8 December 2020 to the proposed use of the Haringey Civic Centre as the Council’s headquarters and democratic functions building, and to the repair, refurbishment and extension works set out in that report. It agreed the cost of refurbishing the existing Civic Centre and authorised officers to carry out further work to develop the design brief which will include exploration of the option to extend the Civic Centre or add an annex which could meet all the Council’s headquarters accommodation needs.

1.2In October 2021, the Cabinet agreed to proceed with the design work on the refurbishment of the Civic Centre, including the provision of an annex extension, based on the feasibility work completed since the December 2020 cabinet decision to explore this option.

1.3In January 2022 Cabinet considered and approved the full business case and options appraisal, which recommended the full refurbishment of the Civic Centre, including the annex extension, in order to provide the Council’s core office accommodation. The same report approved the award of a preparatory works contract, approved the project proceeding to planning outcome, and also noted that Cabinet would be updated ahead of the commencement of the main contractor procurement.

1.4This report provides an update on the further progress made on the Civic Centre project and seeks approval to proceed through to the appointment of the main contractor, which will be brought back to cabinet for approval, subject to cabinet approving this updated business case, first presented in January 2022.

2. Cabinet Member Introduction

2.1The Civic Centre has a long and rich local history. We have seen many nationally significant moments in history take place there, as we can see on the illustrations located on the site hoarding. The Council remains committed to the refurbishment of the Grade II listed Civic Centre and the creation of an additional building on the former car park site, to create a central headquarters for civic operations within the heart of Haringey.

Page 1 of 15 2.2. The Council’s commitment to the Civic Centre project means that the impressive building will be protected and revitalised and ensures that it’s long and rich local history continues for future generations.

2.3The Council’s staff deserve a better working environment, and over the last period the Council has engaged with staff to ensure the building is fit for purpose and meets requirements from a service delivery perspective. The Council has also engaged with the public to showcase the benefit the high-quality spaces will provide to ensure services across the borough meet our resident’s needs.

2.4Giving residents and communities a voice in the project development is a key aim of the project and will go a step beyond what is considered standard engagement. Members of the public and local community groups will help co-design elements of the scheme to shape the project and ensure their needs are met.

2.5Members have also played a role in developing the project’s design through the Civic Centre Members Forum. The Civic Centre Members Forum has allowed for cross-party review of design proposals, influence of key democratic areas and meaningful interaction with officers on a regular basis.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix AAppendix A 1 MB Download
PDF
Civic Centre Project UpdateMinutes 774 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 22 attended
PA
Councillor Peray AhmetChair, present
MH
Councillor Mike HakataCommittee Member, present
ZB
Councillor Zena BrabazonCommittee Member, present
DC
Councillor Dana CarlinCommittee Member, present
SC
Councillor Seema ChandwaniCommittee Member, present
LD
Councillor Lucia das NevesCommittee Member, apologies
JD
Councillor Julie DaviesCommittee Member, apologies
RG
Councillor Ruth GordonCommittee Member, present
AJ
Councillor Adam JogeeCommittee Member, present
SW
Councillor Sarah WilliamsCommittee Member, apologies
AD
Andy DonaldOfficer, expected
FA
Fiona AldermanCouncil Staff, expected

All 22 on the meeting page

On this subject at Haringey

Search all
  1. Civic Centre Project UpdateThis decision
  2. Award of contract for the acquisition of Fixtures, Fittings and Equipment (FF&E) for the Civic CentreApproved
  3. Procurement of client fit out items for the Haringey Civic CentreDecided
  4. Civic Centre Redevelopment Project - RIBA 5 and 6 Technical Advisor Services Contract AwardApproved
  5. Civic Centre Project - Hawkins Brown Design Ltd Contract AwardApproved
  6. Civic Centre Refurbishment (and Extension) WorksAgreed

More from Haringey Cabinet

All decisions
MeetingDecisionOutcome
10 Nov 2026 Corporate Delivery Plan 2026-2028DECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
10 Nov 2026 Draft 2027-28 Budget and 2027-2032 Medium Term Financial Strategy ReportDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
10 Nov 2026 Regulation 19 consultation on Proposed Submission version of Haringey Local Plan 2027-2042 and submission to Secretary of StateDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
10 Nov 2026 Admission to Schools - Proposed Admission Arrangements for 2028/29DECLARATIONS OF INTEREST FOR THIS ITEM: None Decided Open
10 Nov 2026 Approval to extend current Highways and Street Lighting Contracts and approval of the procurement strategy for a future combined Highways and Street Lighting ContractDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies