CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
London Borough of Haringey
Urgent Decisions, Friday 12 May 2023 at 4.30pm

Park View Secondary School - Contract award for the urgent provision of 11 temporary classroom units

Approved Committee 1 paper

Urgent Decisions approved this item on Friday 12 May 2023. Below is the council's own wording, with the papers it was decided on.

Item3

Resolved

RESOLVED to: 1. Approve, pursuant to Contract Standing Order (CSO) 9.07.1d) and CSO 16.02, the award to Contractor A named in Part B exempt report of a contract to provide temporary accommodation (13 classrooms, 1 office and 4 toilets) for an 18 month hire period at Park View Secondary School for a fixed price of £1,134,000 plus a contingency as set out in the Part B exempt report . 2. Approve, pursuant to CSO 9.07.3, the issuance of a letter of intent for up to 10% of the contract value, namely £113,400. Reasons for decision Following an inspection of teaching Block A at Park View School by an external structural engineer, Reinforced Autoclaved Aerated Concrete (RAAC) was discovered forming part of the structural slab of the roof. On the 14 th of April 2023 due to the risk of failure and collapse of this building element it was recommended that the top floor of the building, consisting of 14 classrooms and office space, immediately be vacated. It has been confirmed by the structural engineer that the other floors of the building can be safely used by students and staff. A curriculum and space analysis has been undertaken and it has been determined that the school requires temporary accommodation including 13 classrooms, 1 shared office and 4 toilets until the structural issue can be remediated. Due to the urgency of providing this temporary accommodation, a Cabinet Member signing has been requested in May 2023 to meet space requirements for teaching and learning and minimise the disruption to the school flowing from the loss of this accommodation. The Chair of the Overview and Scrutiny Committee has, in accordance with Part ... view the full minutes text for item 3.
Word for word from the decision Haringey published for this meeting. Source: www.minutes.haringey.gov.uk

Follow this further

Built from Haringey's papers

What the report saysPro

Report to Urgent Decisions, 6 pages

Recommendations

For the Cabinet Member for Children, Education and Families to:

3.1Approve, pursuant to Contract Standing Order (CSO) 9.07.1d) and CSO 16.02, the award to Contractor A named in Part B exempt report of a contract to provide temporary accommodation (13 classrooms, 1 office and 4 toilets) for an 18 month hire period at Park View Secondary School for a fixed price of £1,134,000 plus a contingency as set out in the Part B exempt report.

3.2Approve, pursuant to CSO 9.07.3, the issuance of a letter of intent for up to 10% of the contract value, namely £113,400.

Reasons for decision

4.1Following an inspection of teaching Block A at Park View School by an external structural engineer, Reinforced Autoclaved Aerated Concrete (RAAC) was discovered forming part of the structural slab of the roof. On the 14th of April 2023 due to the risk of failure and collapse of this building element it was recommended that the top floor of the building, consisting of 14 classrooms and office space, immediately be vacated. It has been confirmed by the structural engineer that the other floors of the building can be safely used by students and staff. A curriculum and space analysis has been undertaken and it has been determined that the school requires temporary accommodation including 13 classrooms, 1 shared office and 4 toilets until the structural issue can be remediated. 4.2 Due to the urgency of providing this temporary accommodation, a Cabinet Member signing has been requested in May 2023 to meet space requirements for teaching and learning and minimise the disruption to the school flowing from the loss of this accommodation.

4.3The Chair of the Overview and Scrutiny Committee has, in accordance with Part Four, Section D, Rule 17.1 of the Council’s Constitution, agreed that the taking of the decision recommended in this report is urgent and cannot reasonably be deferred and has supported the decision to waive the requirements of the Constitution in Part Four, Section D, Rule 13 and the 5-day notice period requirement for key decisions set out in Part Four, Section D. It was agreed the decision was urgent and time critical in accordance with Part Four Section H Rule 18 (a) and 18 (b).

4.4Interim teaching arrangements have been in place at the school from Monday 17th April 2023. These consist of teaching many pupils in shared/communal spaces such as the sports gym. This is not sustainable and is impacting the quality of teaching and learning and additionally the gym is required to support GCSE exams from mid-May.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Park View Secondary School: Contract award for the urgent provision of 11 temporary classroom unitsMinutes 6 pages DownloadRead as text

At this meeting

Whole meeting
3Park View Secondary School - Contract award for the urgent provision of 11 temporary classroom unitsThis decision
4Exclusion of the Press and PublicOn the agenda

On this subject at Haringey

Search all
  1. Park View Secondary School - Contract award for the urgent provision of 11 temporary classroom unitsThis decision
  2. Review of Parking Fees and Charges 2026-2027Decided
  3. Park View Secondary School Block A Roof Replacement - Award of Contract for Construction Related Consultancy ServicesDecided
  4. Park View Secondary School Block A Roof Replacement - Permission to initiate tender action for Construction Related Consultancy ServicesApproved
  5. Park View Secondary School Temporary Accommodation – Variation of Hire ContractApproved
  6. Car parking charges reviewApproved

More from Haringey Urgent Decisions

All decisions
MeetingDecisionOutcome
17 Oct 2023 Household Support Fund in HaringeyRESOLVED 1. To note the Household Support Fund allocation from the government of £4,813,343.44 for the period 1st Apr... Noted Open
12 Sep 2023 Request to approve to vary the and extend the contract with D Shelton Hotel Limited, for Interim night shelter accommodationRESOLVED to: i. approve to vary and extend the contract under the procedures enlisted in Contract Standing Order (CSO... Approved Open
17 Jul 2023 Variation of current electrical inspection report programmeRESOLVED 1. To approve a variation of the two existing contracts with Contractor N and Contractor A, for the provisio... Approved Open
15 Jun 2023 Microsoft Enterprise Agreement - Contract Variation and Extension - for the Provision of Microsoft License Subscriptions, to include E5RESOLVED to 1. Approve, under Contract Standing Order 10.02.1b), an extension to the Council’s Microsoft Agreement wi... Approved Open
22 May 2023 Household Support Fund in Haringey Phase 2: May 2023RESOLVED to 1. Approves the Household Support Fund Scheme Policy: May 2023 Phase 2, which sets out the Council’s arra... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies