RESOLVED To authorise virements to cover the cost of capital and revenue expenditure for the financial year April 2023 to March 2024, to a total of £2,100,540.00, of which £980,320.0 is revenue and £1,120,220.00 is capital, in order to implement the fire safety programme. Reasons for decision In January 2023, the Council wrote to the Regulator of Social Housing (RSH), the body that provides independent oversight of all registered social housing providers including local authorities and Housing Associations and made a voluntary self-referral for a potential breach of the Home Standard. The RSH assessed the evidence provided as part of the self-referral and confirmed that the Council has indeed breached two parts of the Home Standard. As a result, the RSH published a Regulatory Notice on 6 th March 2023. This notice remains “live” for 12 months or until full compliance is achieved. In July 2023, the council entered a Voluntary Undertaking with the Regulator of Social Housing with the aim of achieving full compliance and discharge of the Notice. The Voluntary Undertaking was agreed by Cabinet in July 2023 and delegated the authority to the Chief Executive to enter a Voluntary Undertaking with the Regulator. The Voluntary Undertaking ... view the full minutes text for item 22.
Word for word from the decision Haringey published for this meeting.Source: www.minutes.haringey.gov.uk
3.1The Leader of the Council authorises virements to cover the cost of capital and revenue expenditure for the financial year April 2023 to March 2024, to a total of £2,100,540.00, of which £980,320.0 is revenue and £1,120,220.00 is capital, in order to implement the fire safety programme.
Reasons for decision
4.1In January 2023, the Council wrote to the Regulator of Social Housing (RSH), the body that provides independent oversight of all registered social housing providers including local authorities and Housing Associations and made a voluntary self-referral for a potential breach of the Home Standard.
4.2The RSH assessed the evidence provided as part of the self-referral and confirmed that the Council has indeed breached two parts of the Home Standard. As a result, the RSH published a Regulatory Notice on 6 th March 2023. This notice remains “live” for 12 months or until full compliance is achieved.
Page 1 4.3 In July 2023, the council entered a Voluntary Undertaking with the Regulator of Social Housing with the aim of achieving full compliance and discharge of the Notice.
4.4The Voluntary Undertaking was agreed by Cabinet in July 2023 and delegated the authority to the Chief Executive to enter a Voluntary Undertaking with the Regulator.
4.5The Voluntary Undertaking requires Haringey Council clearing the backlog of high-risk fire actions by 31st March 2024. Failure to do so can result in direct intervention from the Regulator of Social Housing.
4.6These works require the use of multiple external contractors due to both resource requirements and specialist certification.
4.7As part of the programme development to deliver the works required to meet our commitments, the value has been established and is additional to previously budgeted provision within the current financial year.
5. Alternative options considered.
5.1Do Nothing
5.1.1 Doing nothing will mean that the Council will fail to meet its commitments to the Regulator provided in the Voluntary Undertaking.
6. Background information
6.1Since the Voluntary Undertaking, good progress has been made to reduce the number of high-risk actions.
6.2This project seeks to deliver over 1300 of the remaining approximately 2000 overdue, high-risk actions to be completed by the deadline. The remainder are in several smaller programmes allocated to individual teams and being delivered through in-house or existing supply chain arrangements, including for example new loft hatches being installed.
6.3The Director of Finance and Director of Placemaking & Housing have identified potential reserve funding capacity to fund the Revenue works and capital programme capacity for the virement needed to fund the capital works.
6.4The breakdown of the projects and finding requirements is as follows.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.