Broadwater Farm - Northolt Strip-Out Contract

Approved Executive 1 paper

Cabinet Member Signing approved this item on Thursday 25 July 2024. Below is the council's own wording, with the papers it was decided on.

Item7

Resolved

RESOLVED In line with Contract Standing Order (CSO) 16.02, to approve the award of contract to Tenderer A (as set out in Appendix A of the report), to a total value of £725,345.00. To delegate authority to the Director of Broadwater Farm Estate, in consultation with the Director of Finance, to authorise and expend sums as set out within the exempt part of the report. To delegate authority to the Director of Broadwater Farm Estate in consultation with the Director of Finance, to extend the contract period from July 2026 to December 2026 if required due to unforeseen works and other relevant reasons to extend the contract. To approve issuance of a letter of intent up to the value of £100,000.00 prior to issuing a formal contract. The Letter of Intent will enable the contractor to place an order with their supply chain to enable the programme to be met. Reasons for decision The regeneration of the Broadwater Farm Estate would see the construction of 294 new homes across the estate. Once demolished, the Northolt block and surrounding areas will see a total of 68 new homes constructed on the site. The development of the Northolt site will commence May 2028 and complete June 2031. To ensure the block was demolished and the site cleared and ready for hand over to the appointed new homes contractor - the Council needed to ensure that all risks associated with the block and surrounding areas are removed. Therefore, it was suggested that the demolition was carried out in 2 phases i.e., an initial strip-out phase to remove asbestos and services provided by statutory authorities. The second phase which allow for the physical dismantling of the block. Awarding a contract to Tenderer A in the sum of £725,345.00 for phase one of the demolition programme, would protect the Council against financial and programme risks. Alternative options considered Do nothing was not an option as the strip-out works to Northolt was essential to remove asbestos and terminate all existing mechanical and electrical services to enable the block to be demolished. The works would also remove risks associated with carrying out these works at a later stage, and the financial and programme impact this could have on the project. The option to include the strip-out works as part of the second ... view the full minutes text for item 7.
Word for word from the decision Haringey published for this meeting. Source: www.minutes.haringey.gov.uk

Follow this further

Built from Haringey's papers

What the report saysPro

Report to Cabinet Member Signing
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
Broadwater Farm: Northolt Strip-Out ContractMinutes 302 KB Copy on its way

At this meeting

Whole meeting

On this subject at Haringey

Search all
  1. Broadwater Farm - Northolt Strip-Out ContractThis decision
  2. Major Works Programme Broadwater Farm EstateApproved
  3. Approval of contract for demolition of Northolt and the Stapleford wing block and approval for contract for Phase two of the Broadwater Farm new homes programmeDecided
  4. Contract Variation for UK Power Networks (UKPN) to carry out essential electrical works on the Broadwater Farm EstateApproved
  5. Broadwater Farm Resident AccessApproved
  6. Broadwater Farm Major works programmeApproved

More from Haringey Cabinet Member Signing

All decisions
MeetingDecisionOutcome
2 Nov 2026 Deaf Outreach Services ContractDECLARATIONS FOR THIS ITEM: NONE Decided Open
28 Oct 2026 Administrative amendment to Merchant Acquirer Re-ProcurementRESOLVED 1. To note the administrative error in the original report referring to Global Pay and Global Payments; 2. T... Noted Open
20 Oct 2026 Approval of Additional Expenditure and Final Payment to Accora Limited reportDECLARATIONS FOR THIS ITEM: NONE RESOLVED The Cabinet Member for Adults and Health: 1. Approved the variation of cont... Approved Open
16 Oct 2026 Approve Funding from Arts Council England to Haringey Music Service for the North London Music HubDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
13 Oct 2026 Filming at meetingsThe notice of filming at meetings was noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies