Update on progress of proposals for Major Sites 08 September 2024
Site Description Timescales/comments Case Officer Manager APPLICATIONS DETERMINED AWAITING 106 TO BE SIGNED Berol Quarter Berol House Members resolved to grant Phil Elliott John McRory Berol Yard, Ashley Refurbishment of Berol House for a mix of planning permission subject to Road, N17 flexible commercial and retail floorspace with the signing of legal agreement. additional floors on the roof. Comprising HGY/2023/0261 refurbishment of c. 3,800sqm of existing Negotiations on legal agreement commercial floorspace and addition of c. are ongoing. 2,000sqm new additional accommodation at roof level. Targeting net zero.
2 Berol Yard 2 Berol Yard will comprise circa 200 new Build to Rent (BTR) homes with a mix of flexible retail and commercial space at ground floor level. The BTR accommodation will include 35% Discount Market Rent affordable housing. Tallest element 33 storeys.
And associated public realm and landscaping within the quarter.
Warehouse Living Construction of two new buildings to provide Members resolved to grant Phil Elliott John McRory proposal – 341A new warehouse living accommodation (Sui planning permission subject to Seven Sisters Road / Generis (warehouse living)), ground floor café/ the signing of legal agreement. Eade Rd N15 workspace (Use Class E) and associated waste collection and cycle parking. Erection of 10 Negotiations on legal agreement HGY/2023/0728 stacked shipping containers (two storeys) to are ongoing. provide workspace/ artist studios (Use Class E), toilet facilities and associated waste collection and cycle parking. Landscape and public realm enhancements including the widening of and works to an existing alleyway that connects Seven Sisters and Tewkesbury Road, works to Tewkesbury Road, the creation of rain gardens, greening, seating, signage and artworks and all other associated infrastructure works, including the removal of an existing and the provision of a new substation to service the new development.
Mecca Bingo, 707- Demolition of the existing building and Members resolved to grant Valerie Okeiyi John McRory 725 Lordship Lane, redevelopment to provide affordable homes, planning permission subject to Wood Green, N22 purpose-built student accommodation, and the signing of legal agreement. flexible ground floor commercial (Class E) HGY/2024/0450 floorspace within buildings ranging between 3 – Negotiations on legal agreement 9 storeys, public realm and landscaping works, are ongoing. cycle parking, and associated works. To be referred to GLA for Stage 2 decision 807 High Road Full planning application for the demolition of Negotiations on legal agreement Phil Elliott John McRory Tottenham, London, existing buildings and the erection of a are ongoing. N17 8ER replacement building of up four storeys to include purpose-built student accommodation HGY/2024/0692 (Sui Generis) and flexible commercial, business and service uses (Class E), hard and soft landscaping, and associated works.
Tottenham Hotspur Minor Material Amendment application under Members resolved to grant Samuel Uff John McRory Stadium, 748 High Section 73 of the Town and Country Planning planning permission subject to Road, Tottenham, Act for the variation to Condition B9 (Major the signing of legal agreement. N17 Non-association Football Events) of the hybrid planning permission HGY/2023/2137 (as HGY/2024/1008 amended) for amendments to allow up to 30 Negotiations on legal agreement major non-association football events including are ongoing. music concerts; and other associated changes.
APPLICATIONS SUBMITTED TO BE DECIDED Capital City College New Construction and Engineering Centre, To be reported to Members at Roland Sheldon John McRory Group, Tottenham extending to 3,300 sq. m the 8th September Planning Centre) N15 Committee
HGY/2024/0464
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
32 Major sites list to Committee September 2024Minutes | 12 pages | DownloadRead as text |
PDF |
UPDATE ON MAJOR PROPOSALSMinutes | 2 pages | Download |
Follow Planning Sub Committee at Haringey and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 5 Oct 2026 | MINUTESRESOLVED To confirm and sign the minutes of the Planning Sub Committee held on 7 th September as a correct record. | Decided | Open |
| 5 Oct 2026 | Update on major proposalsRESOLVED To note the report. | Noted | Open |
| 5 Oct 2026 | Applications determined under delegated powersRESOLVED To note the report. | Noted | Open |
| 27 Jul 2026 | MINUTESRESOLVED To confirm and sign the minutes of the Planning Sub Committee held on 8 th June as a correct record. In rela... | Noted | Open |
| 27 Jul 2026 | Update on major proposalsRESOLVED To note the report. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.