RESOLVED That the Committee resolve to GRANT planning permission and that the Assistant Director of Planning, Building Standards & Sustainability or the Head of Development Management is authorised to issue the planning permission and impose conditions and informatives subject to the signing of a legal agreement providing the obligations as set out in the Heads of Terms below. That the legal agreement referred to in resolution (2.1) above is to be completed no later than 9th October 2024 or within such extended time as the Assistant Director Planning, Building Standards & Sustainability/Head of Development Management shall in her/his sole discretion allow; and That, following completion of the agreement(s) referred to in resolution (2.1) within the time period provided for in resolution (2.2) above, planning permission shall be granted in accordance with the Planning Application subject to the attachment of the conditions and informatives ; and That delegated authority be granted to the Head of Development Management or the Assistant ... view the full minutes text for item 9.
Word for word from the decision Haringey published for this meeting.Source: www.minutes.haringey.gov.uk
UPDATE FOR CONSIDERATION AT PLANNING SUB-COMMITTEE Item No. 2
Reference No: HGY/2024/1370 Ward: Northumberland Park
Address: 18 West Road & Unit 4 West Mews N17
Proposal:
Redevelopment of 18 West Road and Unit 4 West Mews comprising 2no. warehouses (Use Class B2/B8) with ancillary mezzanine floorspace and associated landscaping, yard, parking, access and infrastructure.
Applicant: VIQR Tottenham 1 Limited
Ownership: Private
Corrected section: The applicant is VIQR Tottenham 1 Limited not Valor Park Corrected section Address to be corrected - Unit 4 to be included in the address of the site. Correction The correct floor area is 6,312 sq.m and not 6132 as stated in some paras within the report. Site location Correction Para 3.2.3 Image 2: Site location plan does not include the existing substation, please ignore plan and refer to image on Appendix 2 in the report. Corrected section S106 Heads of Terms The developer is required to pay a sum of £3,000 (three thousand pounds) per year per travel plan for monitoring of the travel plans for a period of 5 years and the total figure would be £30,000. Correction of wording of condition 15 Energy Strategy Please find the final energy strategy condition wording. Bold font show the changes made. Energy Strategy
(a) Prior to the commencement of development, a revised Energy Statement shall be submitted and approved by the Local Planning Authority. This shall be based on the submitted Energy and Sustainability Statement by Cudd Bentley (dated 16 August 2024), delivering a minimum site-wide carbon emission reduction of 122% from a Building Regulations 2021 Part L compliant building, with high fabric efficiencies, air source heat pumps (ASHPs) and a minimum 260 kWp solar photovoltaic (PV) array and inverter capacity. The revised strategy shall include the following: Confirmation of how this development will meet the zero-carbon policy requirement in line with the Energy Hierarchy; Confirmation of the fabric efficiencies will meet the targets proposed in the Energy and Sustainability Statement by Cudd Bentley (dated 16 August 2024): Floor U- value: 0.18 W/m2K External wall and internal partition U- value: 0.23 W/m2K Roof U-value: 0.15 W/m2K Door U-value: 1.6 W/m2K Window U- value: 1.40 W/m2K (glazing) G-value: 0.34 Air permeability rate: 3 m3/hm2 @50Pa Detailed BRUKL calculations for the non-residential element of the development, demonstrating how it will exceed the 15% improvement on Building Regulations under Be Lean; Details to reduce thermal bridging; Confirmation of location, specification and efficiency of the proposed ASHPs and MVHR with plans showing the relevant pipework, and noise and visual mitigation measures; Confirmation of PV details, demonstrating the roof area has been maximised, with the following details: a roof plan; the number, angle, orientation, type, and efficiency level of the PVs; how overheating of the panels will be minimised; their peak output (kWp); inverter capacity; and how the energy will be used on-site before exporting to the grid; Specification of any additional equipment installed to reduce carbon emissions, if relevant; A metering strategy. The development shall be carried out strictly in accordance with the details so approved prior to first operation and shall be maintained and retained for the lifetime of the development.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.