CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
London Borough of Haringey
Cabinet Member Signing, Wednesday 30 April 2025 at 11.00am

Broadwater Farm - Contract Extension for Northolt Strip-Out Contract

Approved Executive 1 paper

Cabinet Member Signing approved this item on Wednesday 30 April 2025. Below is the council's own wording, with the papers it was decided on.

Item6

Resolved

RESOLVED 1. Pursuant to CSO 10.02.1 (b) and 16.02 approves the extension of the contract in the sum of £794,655.00. The original contract was awarded for the sum of £725,345.00. Subject to the approval of the contract extension, the total approved sum will be £1.52m. 2. Approval of this extension to the contract will result in a variation in the value and an extension to the programme . 3. Agrees the total costs contained within the exempt report. Reasons for decision The extension to the contract would enable the strip-out works to continue to make the blocks ready for demolition by a specialist contractor. The main demolition was programmed to commence from October - December 2025 and would include for the demolition of the Northolt and Stapleford North blocks. It was essential that the strip-out works to both blocks were completed prior to the start of the main demolition programme , otherwise this could delay the works to demolish the blocks to make the site ready for the construction of 68 new homes. Alternative options considered Do nothing and programme the additional works as a standalone contract. This was considered but quickly discounted. The reason for this was because there was an incumbent contractor on-site, and procuring a separate contractor would not only delay the works, but render the current project incomplete and result in higher costs due to the procurement timeframe if another contractor was appointed to carry out the works. The option to include the additional works as part of the main demolition programme was considered. Discussions with the design team directed the decision to include these works as part of the ... view the full minutes text for item 6.
Word for word from the decision Haringey published for this meeting. Source: www.minutes.haringey.gov.uk

Follow this further

Built from Haringey's papers

What the report saysPro

Report to Cabinet Member Signing

Recommendations

It is recommended that:

Cabinet Member for Council Housebuilding, Placemaking and Development: 3.1 Pursuant to CSO 10.02.1 (b) and 16.02 approves the extension of the contract in the sum of £794,655.00. The original contract was awarded for the sum of £725,345.00. Subject to the approval of the contract extension, the total approved sum will be £1.52m.

3.2Approval of this extension to the contract will result in a variation in the value and an extension to the programme.

3.3Agrees the total costs contained within the exempt report.

Reasons for decision

4.1The extension to the contract will enable the strip-out works to continue to make the blocks ready for demolition by a specialist contractor.

4.2The main demolition is programmed to commence from October - December 2025 and will include for the demolition of the Northolt and Stapleford North blocks.

4.3It is essential that the strip-out works to both blocks are completed prior to the start of the main demolition programme, otherwise this could delay the works to demolish the blocks to make the site ready for the construction of 68 new homes.

Alternative options considered

5.1Do nothing and programme the additional works as a standalone contract. This was considered but quickly discounted. The reason for this is because there is an incumbent contractor on-site, and procuring a separate contractor will not only delay the works, but render the current project incomplete and result in higher costs due to the procurement timeframe if another contractor was appointed to carry out the works.

5.2The option to include the additional works as part of the main demolition programme was considered. Discussions with the design team directed the decision to include these works as part of the existing contract. This is because pre-market engagement with demolition contractors concluded that contractors would rather a project which has been de-risked i.e., made free from asbestos, mechanical and electrical services and all fixtures and fittings. Cost control on a de-risked project would be easier to manage, and programme predictability for the client and contractor is more favourable when a demolition project has been stripped and cleared prior to starting the main demolition works.

6.0Background information

6.1Northolt is a nineteen-storey housing block constructed in the early 1970s using a Large Panel System (LPS) method of construction. Following a detailed structural survey, it was found that the building was not compliant with safety regulations.

6.2At the July 2024 Cabinet, it was agreed to award a contract for the strip-out of the block in the sum of £725,345.00. 6.3 The strip-out works commenced October 2024 with a proposed completion and end of defects date of August 2026.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Broadwater Farm: Contract Extension for Northolt Strip-Out ContractMinutes 235 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

1 of 1 attended
RG
Councillor Ruth GordonCommittee Member, present

On this subject at Haringey

Search all
  1. Broadwater Farm - Contract Extension for Northolt Strip-Out ContractThis decision
  2. Major Works Programme Broadwater Farm EstateApproved
  3. Approval of contract for demolition of Northolt and the Stapleford wing block and approval for contract for Phase two of the Broadwater Farm new homes programmeDecided
  4. Contract Variation for UK Power Networks (UKPN) to carry out essential electrical works on the Broadwater Farm EstateApproved
  5. Broadwater Farm Resident AccessApproved
  6. Broadwater Farm Major works programmeApproved

More from Haringey Cabinet Member Signing

All decisions
MeetingDecisionOutcome
2 Nov 2026 Deaf Outreach Services ContractDECLARATIONS FOR THIS ITEM: NONE Decided Open
28 Oct 2026 Administrative amendment to Merchant Acquirer Re-ProcurementRESOLVED 1. To note the administrative error in the original report referring to Global Pay and Global Payments; 2. T... Noted Open
20 Oct 2026 Approval of Additional Expenditure and Final Payment to Accora Limited reportDECLARATIONS FOR THIS ITEM: NONE RESOLVED The Cabinet Member for Adults and Health: 1. Approved the variation of cont... Approved Open
16 Oct 2026 Approve Funding from Arts Council England to Haringey Music Service for the North London Music HubDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
13 Oct 2026 Filming at meetingsThe notice of filming at meetings was noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies