London Borough of Haringey
Cabinet Member Signing, Thursday 4 December 2025 at 1.00pm

BWF - FRA PROGRAMME VAIATION

Approved Executive 1 paper

AI summaryHaringey's Cabinet Member Signing approved £690k more for the Broadwater Farm fire safety programme, taking the contract to £5.94m and targeting final sign off and the end of the defects period by March 2026 [D] [3.2] [4.2].

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedA further £690k, contingency use and programme extension were approved [D] [3.2] [P4]
Money£690k further increase [3.2]Revised contract value £5.94m, funded from programme budget [3.2] [6.8]
What happens nextCommence additional fire safety works [6.10]Final sign off and defects period end by March 2026 [4.2] [6.10]
Who it affectsEight Broadwater Farm blocks [4.1]Residents and visitors at the eight programme blocks [4.1] [5.1]

What was decided

The Cabinet Member Signing approved the BWF contract variation in the sum of £5.25m and authorised a further £690k increase. The revised contract value is £5.94m. Report 3.1, 3.2

Approval was given to use the contingency in Appendix A and extend the contract programme. Report 3.2, P4

The total costs and scope of works in Appendix A, Exempt Report, were agreed. Report 3.3

Why

Fire risk assessments identified essential work in eight blocks so residential buildings meet current fire safety legislation, resist fire spreading through communal areas and provide protected escape and fire brigade access. Report 4.1

The project team identified additional essential works during delivery, after they had not been identified at tender. They include replacing all windows and stairwell spandrel panels at Kenley, a 17 storey block, enhanced emergency lighting in all wing blocks, fire rated doors on external balconies, upgraded wayfinding and safety signage, and safety features and surface finishes across all eight blocks, plus further works in Appendix A. These measures are intended to ensure compliance with current building and fire safety across the estate. Report P7, P8, P9, P10, P11, P12, P13, P14, P15

Doing nothing was not an option because current fire safety regulations had to be met for residents and visitors. Extending the existing contract and programme was the only available option. Report 5.1, P21

What happens next

After approval, the appointed contractor and the multi disciplinary consultant will be notified so the additional works can begin. Report 6.10

The programme will proceed towards full completion, with final project sign off and the end of the defects period anticipated by March 2026. Report 4.2, 6.10

The Council must publish a notice of the contract modification under Reg 51. Leasehold discussions will continue, with notice served for any works outside the original Section 20 scope. Report P37, P58

The money

  • £690k Further increase for the additional fire safety works Report 3.2
  • £5.94m Revised contract value for the programme Report 3.2, 6.8
  • £5.25m Contract sum stated for the variation Report 3.2
  • £672,750.00 Additional spend in 25/26 Report P31, P32
  • £17,250.00 Additional spend in 26/27 Report P31, P32
  • £690,000.00 Total additional contract spend profile Report P31, P32
  • £3.5m Initial contract award on 21 September 2023 Report 6.1
  • £5.25 million Contract sum after the August 2024 variation Report 6.1, P23

Options considered

  • Rejected: Do nothing. Current fire safety regulations had to be met for residents and visitors to the eight blocks, while bringing forward elements of the major works programme would improve communal areas and residents' quality of life. Report 5.1
  • Chosen: Extend the current contract sum and programme for the existing contractor. It was the only available option and would allow essential fire safety features to be incorporated into the programme. Report P21

Implications

  • Financial: The £690k increase is funded from the Broadwater Farm Refurbishment Programme budget. The 2026/27 Broadwater Farm capital budget includes provision for it, so no further funding is required. Report 6.8, P47
  • Financial: The additional spend is split between 25/26 and 26/27: £672,750.00 and £17,250.00 respectively, giving a total of £690,000.00. Report 6.7, P31, P32
  • Legal: The report relies on regulation 72(1)(b) of the Public Contracts Regulations 2015. Additional works must have been necessary and not included in the initial procurement, a change of contractor cannot be made for economic or technical reasons and would cause significant inconvenience or substantial duplication, and any price increase must not exceed 50% of the original contract value. The Council must publish a modification notice under Reg 51. Report P49, P54, P55, P56, P57, P58
  • Legal: No further Section 20 consultation is required because Leasehold Services considers the additional works within the original scope and notices. Ongoing discussions will continue, with notice served for any works outside the original scope. Report P37, P60
  • Risk: The appointed cost consultant reviews costs and will continue monitoring for efficiencies, while a quality inspector conducts daily checks on workmanship, health and safety, and programme progress. Completion moved from November 2024 to December 2025, while the defects period remained due in November 2025, and approval moves the target end of the defects period to March 2026. Report P28, P42, 6.1, 6.10
  • Equalities: No new Equality Impact Assessment is required because an assessment was included in the original Cabinet report dated 21 September 2023. Report P64
  • Other: Completing the works is intended to bring the eight programme blocks into compliance with existing fire and building safety regulations. Rochford and Martlesham are outside this scope and will receive upgrade work through the separate Pilot Refurbishment Programme. Report P17, P18, P19
  • Other: Residents in the eight blocks met the lead architect and main contractor in design sessions and helped choose wall and door colours. Their feedback informed final design and colour communications for each block. Report P38, P39, 6.12, 7.1

Who and where

  • Residents and visitors at the eight Broadwater Farm blocks Report 4.1, 5.1
  • Leaseholders for whom some works are chargeable Report 6.11
  • The appointed main contractor Report 6.10, P42
  • The appointed cost consultant Report 6.5, P28
  • The quality inspector Report P42
  • Residents of Rochford and Martlesham, who are outside this contract but will receive separate upgrade works Report P18, P19

Timeline

  • 21 September 2023: Cabinet agreed the £3.5m contract award, with contingency spending subject to approval. Report 6.1
  • November 2023: The works formally commenced. Report 6.1, P23
  • August 2024: Cabinet approval led to a variation to £5.25 million and moved completion from November 2024 to December 2025, without extending the defects liability period. Report 6.1, P23
  • November 2024: Original scheduled completion date. Report 6.1, P23
  • November 2025: Original scheduled end of the defects period. Report 6.1, P23
  • December 2025: Completion date set by the August 2024 variation. Report 6.1, P23
  • 2025-12-04: Cabinet Member Signing approved the further increase, contingency use and programme extension. Report 3.2, P4, 3.3
  • March 2026: Final project sign off and the target end of the defects period after the extension. Report 4.2, 6.10

Plain English for the jargon

  • BWF: Broadwater Farm [6.1]
  • FRA: Fire Risk Assessment [4.2]
  • EQIA: Equality Impact Assessment [P64]
  • PCR 2015: Public Contracts Regulations 2015 [P49]
  • Section 20: Consultation requirements under the Landlord and Tenants Act 1985 [6.11] [P37]
  • Reg 51: Requirement to publish a notice of a contract modification [P58]
  • Reg 72: Rules allowing a contract to be modified without following a procurement [P54]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item6

Resolved

RESOLVED Pursuant to (CSO) 0.08, 2.01(d) and 18.03, to approve the variation of the BWF – Fire Risk Assessment and Protective Coatings contract in the sum of £5.25m, authorises an increase in the contract sum by a further £690k, and approves the use of contingency as set out in the report. The revised contract value will be £5.94m. To agree the total costs and scope of works contained within Appendix A of the Exempt Report. Reasons for decision The BWF – Fire Risk Assessment and Protective Coatings Contract was developed following a series of fire risk assessments, which identified essential fire safety works to 8 blocks on the estate. The works were required to ensure that residential buildings met current fire safety legislation and adequately resisted the spread of fire throughout the communal areas and provided a protected means of escape to allow the safe evacuation of residents and safe access by the fire brigade. The project commenced November 2023. During the works, the project team identified and agreed that additional works were required to ensure the project met current fire safety regulations. The additional works were not identified at tender stage; however, they were considered essential for compliance and include the following:  Replacement of all windows, including spandrel panels to the communal stairwell of Kenley, a 17-storey residential block  Installation of enhanced emergency lighting across all wing blocks  Provision of additional fire-rated doors on external balconies  Upgraded wayfinding and fire safety signage  Implementation of essential fire safety features and surface finishes across all eight blocks on the Estate  Additional works to complete the programme as detailed in the table in Appendix A – Exempt Report The above measures would ensure compliance with current building and fire safety across the estate. Subject to approval of the additional budget allocation, the Broadwater Farm (BWF) – Fire Risk Assessment (FRA) Programme would proceed towards full completion. The current programme ... view the full minutes text for item 6.
Word for word from the decision Haringey published for this meeting. Source: www.minutes.haringey.gov.uk

Follow this further

Built from Haringey's papers

What the report saysPro

Report to Cabinet Member Signing, 7 pages

Recommendations

It is recommended that:

3.1The Cabinet Member for Housing Services, Private Renters, and Planning:

3.2Pursuant to (CSO) 0.08, 2.01(d) and 18.03 approves the variation of the BWF – Fire Risk Assessment and Protective Coatings contract in the sum of £5.25m and authorises an increase in the contract sum by a further £690k to deliver the works set out in the report. The revised contract value will be £5.94m. Approval also

Page 1 of 7 required to expend the contingency sum in Appendix A – Exempt Report and extend the contract programme.

3.3Agrees the total costs and scope of works contained within Appendix A - Exempt Report.

Reasons for decision

4.1The BWF – Fire Risk Assessment and Protective Coatings Contract was developed following a series of fire risk assessments, which identified essential fire safety works to 8 blocks on the estate. The works are required to ensure that our residential buildings meet current fire safety legislation and adequately resist the spread of fire throughout the communal areas and provide a protected means of escape to allow the safe evacuation of residents and safe access by the fire brigade.

The project commenced November 2023. During the works, the project team identified and agreed that additional works are required to ensure the project meets current fire safety regulations.

The additional works were not identified at tender stage; however, they are considered essential for compliance and include the following:

 Replacement of all windows, including spandrel panels to the communal stairwell of Kenley, a 17-storey residential block

 Installation of enhanced emergency lighting across all wing blocks

 Provision of additional fire-rated doors on external balconies

 Upgraded wayfinding and fire safety signage

 Implementation of essential fire safety features and surface finishes across all eight blocks on the Estate

 Additional works to complete the programme as detailed in the table in Appendix A – Exempt Report

The above measures will ensure compliance with current building and fire safety across the estate.

4.2Subject to approval of the additional budget allocation, the Broadwater Farm (BWF) – Fire Risk Assessment (FRA) Programme will proceed towards full completion. The current programme anticipates a final project sign-off and end of defects period by March 2026.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
BWF: FRA PROGRAMME VAIATIONMinutes 7 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

1 of 1 attended
SW
Councillor Sarah WilliamsCommittee Member, present

More from Haringey Cabinet Member Signing

All decisions
MeetingDecisionOutcome
2 Nov 2026 Deaf Outreach Services ContractDECLARATIONS FOR THIS ITEM: NONE Decided Open
28 Oct 2026 Administrative amendment to Merchant Acquirer Re-ProcurementRESOLVED 1. To note the administrative error in the original report referring to Global Pay and Global Payments; 2. T... Noted Open
20 Oct 2026 Approval of Additional Expenditure and Final Payment to Accora Limited reportDECLARATIONS FOR THIS ITEM: NONE RESOLVED The Cabinet Member for Adults and Health: 1. Approved the variation of cont... Approved Open
16 Oct 2026 Approve Funding from Arts Council England to Haringey Music Service for the North London Music HubDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
13 Oct 2026 Filming at meetingsThe notice of filming at meetings was noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies