Cabinet Member Signing, Thursday 4 December 2025 at 1.00pm

AWARD OF CONSTRUCTION OF CONTRACT

Approved Executive 1 paper

AI summaryHaringey's Cabinet Member for Housing and Planning approved Contractor A's appointment to deliver the new build. [D] [3.1] The contract sum is in the exempt report, and approval was given for a Letter of Intent of up to 10% of the contract value. [3.1] [3.10] [9.2] [11.1]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedFixed price contract covering the new build works. [6.12]
MoneyExempt contract sum [3.1]Rents and total scheme cost are also exempt. [3.2] [3.9] [9.2]
What happens nextIssue Letter of Intent [3.10]Up to 10% of contract value before formal contract. [9.6]
Who it affectsNew homes and land rights [3.5] [3.8]Compensation may be paid for valid third party claims. [3.7] [9.11]

What was decided

The appointment of Contractor A for the new build works was approved at the contract sum stated in the exempt report. [D] [3.1] The stated rents and exemption were also approved. [D] [3.2] [3.3] Engagement and consultation on the site was noted. [D] [3.4] Report 3.1, 3.2, 3.3, 3.4

Appropriation of the land from housing purposes to planning purposes was approved so the authorised works could proceed. [D] [3.5] Section 203 powers were approved to override affected easements and third party rights, with authority delegated to agree compensation for valid claims. [D] [3.6] [3.7] Report 3.5, 3.6, 3.7

Appropriation back to the Housing Revenue Account for housing purposes was approved on practical completion. [D] [3.8] The total scheme cost in the exempt report and a Letter of Intent for up to 10% of the contract value were approved. [D] [3.9] [3.10] Report 3.8, 3.9, 3.10

Why

Contractor A was identified through formal tender as the preferred contractor. Six bids were received, and an independent Quantity Surveyor evaluated the financial submissions. [4.1] [6.6] Report 4.1, 6.6

Initial tender prices showed a 76% difference between the lowest and highest prices, and construction costs varied by approximately 55%. [6.8] The Quantity Surveyor issued queries to all contractors and received all responses by the deadline. [6.9] The Council had no known reasons to believe that third party rights had been infringed. [4.2] Report 6.8, 6.9, 4.2

The scheme supports the Council's commitment to high quality affordable housing and identified local needs. It also supports housing, health and social care integration. [4.3] [9.24] [9.25] Report 4.3, 9.24

What happens next

Contractor A is required to develop the technical design and deliver the construction phase. [6.4] Report 6.4

The approved Letter of Intent may be issued before the formal contract is issued and executed. [3.10] [9.6] Report 3.10, 9.6

Land will be appropriated back to the Housing Revenue Account for housing purposes on practical completion. [3.8] A defects liability period of 12 months will apply following practical completion. [6.12] Report 3.8, 6.12

The money

  • up to 10% of the contract value Letter of Intent before formal contract Report 3.10
  • rents as set out in section 1.5 of the exempt part of this report Approved rents Report 3.2
  • £500,000 or more Threshold for Cabinet contract award approval Report 9.4, 9.16

Options considered

  • Chosen: Use the Dynamic Purchasing System through the London Construction Programme. Strategic Procurement recommended it based on contract value and the need for a fair and transparent process. Report 5.2, 9.3, 9.14
  • Rejected: Do not proceed with the development. The Council has no statutory duty, but excluding the site would undermine its ability to meet identified local needs. Report 5.1
  • Chosen: Appropriate the site from housing purposes to planning purposes. The works would not be authorised under planning powers, and Section 203 could not be used, without appropriation. Report 3.5, 5.4
  • Chosen: Override affected easements and third party rights using Section 203. Affected third party rights become a right to compensation rather than a right to seek an injunction. Report 3.6, 5.4, 9.11
  • Chosen: Appropriate the land back to the Housing Revenue Account on completion. It enables the Council to offer the much needed housing provision described in the exempt report. Report 3.8, 5.5
  • Rejected: Do not appropriate the land back to housing purposes on completion. This would prevent the Council from offering the much needed provision described in the exempt report. Report 5.5
  • Rejected: Use a restricted competitive tender through the Haringey Procurement and Contract System. The Dynamic Purchasing System offered stronger safeguards around quality and pricing through open competition. Report 5.3
  • Rejected: Directly award to one LCP framework provider. The Dynamic Purchasing System offered stronger safeguards around quality and pricing through open competition. Report 5.3

Implications

  • Financial: The contract has a fixed price and covers new build works, site mobilisation, enabling works, contractor management costs, overheads and profit. Recent cost projections suggest the scheme can be accommodated within the existing budget/MTFS. [6.12] [9.17] Report 6.12, 9.17
  • Risk: Initial tender prices showed a 76% difference, with approximately 55% variation in construction costs. The independent Quantity Surveyor issued queries to all contractors. [6.8] [6.9] Report 6.8, 6.9
  • Legal: Under Section 203, affected easements and third party rights may be overridden, with valid claims converted into rights to compensation. [3.6] [3.7] [9.11] Report 3.6, 3.7, 9.11
  • Legal: Land moves from housing purposes to planning purposes and then back to the Housing Revenue Account for housing purposes on practical completion. [3.5] [3.8] Report 3.5, 3.8
  • Risk: The fixed price contract includes a defects liability period of 12 months following practical completion. [6.12] Report 6.12
  • Climate: The design meets the Mayor of London's net zero carbon building definition through on site measures. It includes solar panels, air source heat pumps, green roofs, insulation, airtightness and passive design measures. [8.1] [8.2] [8.3] Report 8.1, 8.2, 8.3
  • Equalities: The scheme will support specialist housing and independent living, and the contractor must comply with the Public Sector Equality Duty. [9.24] [9.26] Report 9.24, 9.26
  • Other: The scheme contributes affordable homes and construction jobs. Resident feedback was considered by the Planning Committee. [7.1] [7.3] [5.4] Report 7.1, 7.3, 5.4

Who and where

  • Contractor A Report 3.1, 6.4
  • Haringey Council Report 3.5, 3.8
  • Housing Revenue Account Report 3.8
  • People needing specialist housing in Haringey Report 9.24
  • Haringey residents Report 5.4, 9.23
  • Holders of third party rights and easements Report 3.6, 3.7, 9.11
  • Construction workers Report 7.3
  • Residents of the new homes Report 8.3, 8.4

Timeline

  • April 2022: Full planning permission was granted for the full scheme. Report P67, 9.10
  • Following the granting of planning permission: The contractor is required to develop the technical design and deliver the construction phase. Report 6.4
  • 12pm on 28 August 2025: All responses to the Quantity Surveyor's post tender queries were received by the deadline. Report 6.9
  • 2025-12-04: The contract award and related approvals were decided.
  • Pending issuance and execution of a formal contract: The approved Letter of Intent may be issued. Report 3.10, 9.6
  • upon practical completion: The land returns to the Housing Revenue Account for housing purposes. Report 3.8
  • following practical completion: The defects liability period of 12 months applies. Report 6.12

Plain English for the jargon

  • Contractor A: The preferred contractor identified through formal tender for the new build works. [4.1]
  • Letter of Intent: Approval to start required work before the formal contract is issued and executed. [9.6]
  • Dynamic Purchasing System: The competitive procurement route used through the London Construction Programme. [5.2] [9.3]
  • Most Economically Advantageous Tender: The tender ranking method using combined Quality, Price and Social Value scores. [6.11]
  • Housing Revenue Account: The Council account that will hold the land for housing purposes after completion. [3.8]
  • Section 122: The Local Government Act 1972 power used to appropriate Council land for planning purposes. [9.7] [9.8]
  • Sections 203 and 204: Housing and Planning Act 2016 powers allowing works despite affected rights and converting those rights into compensation rights. [9.9] [9.10] [9.11]
  • OH&P: Overheads and profit, included in tender prices and post tender variations. [6.10]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7

Resolved

RESOLVED To approve the appointment of Contractor A, as identified in the Appendix 1 exempt part B of this report, to undertake the new build works for the contract sum as set out in the exempt report. To approve the rents as set out in section 1.5 of the exempt part of this report. To approve the exemption as set out in section 1.6 of the exempt part of this report. To note the engagement and consultation undertaken in relation to this site, as detailed in section 3 of the exempt part of the report. To approve the appropriation of the land, shown edged red on the plan at appendix 2 in the exempt part of the report, from housing purposes to planning purposes pursuant to Section 122 of the Local Government Act 1972, as it is no longer required for the purpose for which it is currently held, and for the purpose of carrying out the works approved under the planning permission for the scheme. To approve the use of the Council’s powers under Section 203 of the Housing and Planning Act 2016 to override any easements and other third-party rights and interests relating to the land edged red on the plan at Appendix 2 in the exempt part of the report that may be infringed by the development approved under the planning permission for the scheme and further described in the exempt part of the report. To delegate authority to the Corporate Director of Culture, Strategy and Communities, in consultation with the Corporate Director of Finance and Resources, to agree and make any necessary compensation payments arising from valid claims relating to third-party rights affected by the development, in accordance with the Council’s scheme of delegation. To approve the appropriation of the land shown edged red on the plan at appendix 2 in the exempt part of the report, from planning purposes back to the Housing Revenue Account (HRA) for housing purposes under Section 19 of the Housing Act 1985 upon practical completion of the development. To approve the total scheme cost as set out in the exempt part B of the report. To approve the issuance of a Letter of Intent for up to 10% of the contract value, as detailed in the exempt section of the report. Reasons for decision Contractor A has ... view the full minutes text for item 7.
Word for word from the decision Haringey published for this meeting. Source: www.minutes.haringey.gov.uk

Follow this further

Built from Haringey's papers

What the report saysPro

Report to Cabinet Member Signing, 10 pages

Recommendations

It is recommended that the Cabinet Member for Housing and Planning:

3.1Approves the appointment of Contractor A, as identified in the Appendix 1 exempt part B of this report, to undertake the new build works for the contract sum as set out in the exempt report.

3.2Approve the rents as set out in section 1.5 of the exempt part of this report.

3.3Approves the exemption as set out in section 1.6 of the exempt part of this report.

3.4Notes and considers the engagement and consultation undertaken in relation to this site, as detailed in section 3 of the exempt part of this report.

3.5Approves the appropriation of the land, shown edged red on the plan at appendix 2 in the exempt part of the report , from housing purposes to planning purposes pursuant to Section 122 of the Local Government Act 1972, as it is no longer required for the purpose for which it is currently held, and for the purpose of carrying out the works approved under the planning permission for the scheme .

3.6Approves the use of the Council’s powers under Section 203 of the Housing and Planning Act 2016 to override any easements and other third-party rights and interests relating to the land edged red on the plan at Appendix 2 in the exempt part of the report that may be infringed by the development approved under the planning permission for the scheme and further described in the exempt part of the report.

3.7Delegates authority to the Corporate Director of Culture, Strategy and Communities, in consultation with the Corporate Director of Finance and Resources, to agree and make any necessary compensation payments arising from valid claims relating to third-party rights affected by the development, in accordance with the Council’s scheme of delegation.

3.8Approves the appropriation of the land shown edged red on the plan at appendix 2 in the exempt part of the report, from planning purposes back to the Housing Revenue Account (HRA) for housing purposes under Section 19 of the Housing Act 1985 upon practical completion of the development.

3.9Approves the total scheme cost as set out in the exempt part B of the report.

3.10Approves the issuance of a Letter of Intent for up to 10% of the contract value, as detailed in the exempt section of the report.

4. Reasons for decisions

4.1Contractor A has been identified through a formal tender process as the preferred contractor to deliver the new build.

4.2There are no known reasons to believe that any third-party rights have been infringed by the development for the reasons set out in the section 6.2 (leading to the exempt part of this report).

4.3This scheme will contribute to the Council’s commitment to deliver high-quality, affordable provision as set out in the exempt part of this report in Haringey.

Alternative options considered

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
AWARD OF CONSTRUCTION OF CONTRACTMinutes 10 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

1 of 1 attended
SW
Councillor Sarah WilliamsCommittee Member, present

On this subject at Haringey

Search all
  1. AWARD OF CONSTRUCTION OF CONTRACTThis decision
  2. Woodridings Court N22 Award of Construction ContractApproved
  3. Archway Road, N6 - Award of construction contractApproved
  4. Park View Secondary School Block A Roof Replacement - Award of Contract for Construction Related Consultancy ServicesDecided
  5. Alexandra Primary School Safety Valve Project - Award of Construction Works ContractApproved
  6. The brook on broadwaters safety valve project - award of construction works contractApproved

More from Haringey Cabinet Member Signing

All decisions
MeetingDecisionOutcome
2 Nov 2026 Deaf Outreach Services ContractDECLARATIONS FOR THIS ITEM: NONE Decided Open
28 Oct 2026 Administrative amendment to Merchant Acquirer Re-ProcurementRESOLVED 1. To note the administrative error in the original report referring to Global Pay and Global Payments; 2. T... Noted Open
20 Oct 2026 Approval of Additional Expenditure and Final Payment to Accora Limited reportDECLARATIONS FOR THIS ITEM: NONE RESOLVED The Cabinet Member for Adults and Health: 1. Approved the variation of cont... Approved Open
16 Oct 2026 Approve Funding from Arts Council England to Haringey Music Service for the North London Music HubDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
13 Oct 2026 Filming at meetingsThe notice of filming at meetings was noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies